State v. Smith

119 So. 56, 167 La. 301, 1928 La. LEXIS 2050
CourtSupreme Court of Louisiana
DecidedOctober 2, 1928
DocketNo. 29054.
StatusPublished
Cited by25 cases

This text of 119 So. 56 (State v. Smith) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Smith, 119 So. 56, 167 La. 301, 1928 La. LEXIS 2050 (La. 1928).

Opinion

OVERTON, J.

This is a proceeding brought by the state of Louisiana, the Louisiana highway commission, and the police jury of the parish of Calcasieu, to recover judgment against W. H. Smith, Jr., and his surety, the United States Fidelity & Guaranty Company, in the sum' of $58,582.26, with legal interest thereon from, judicial demand, and 10 per cent, attorney’s fees, as damages for their failure to complete, according to contract, the construction of an embankment for a public highway, in the parish of Calcasieu, through the Sabine swamp, to a bridge crossing the Sabine river. The basis of this demand is that Smith failed to complete the work he had contracted to do, and that his surety failed to complete it in his place, as a result of which plaintiffs, after putting both in default, were forced to readvertise and relet the completion of the work at a loss exceeding the amount sued for, which, excepting the attorney’s fees claimed, represents the amount of the bond furnished by Smith. A number of claimants of privileges for material furnished in the construction of the work were cited to assert whatever claims they *305 might have against Smith and his surety. The proceeding, therefore, partakes of one in concurso.

Those claiming privileges appeared and asserted them. Smith, as a defense to the demand against him, pleads that the contract was not finished by him by reason of any fault of his, and that, had plaintiffs themselves complied with the contract and permitted him to finish it, he would have earned $236,500 for overhauls of dirt with which to construct the embankment, for which amount he asks for judgment in reconvention against the Louisiana highway commission. He also pleads that he is not liable for the loss sued for by plaintiffs, because, in reletting the contract for the completion of the work, plaintiffs relet it on terms and conditions differing from, and more onerous to, the contractor than those in the contract with him, as a result of which the price bid by the new contractor was much greater than it otherwise would have been. The defenses of the surety are substantially the same as those of Smith. Especially does the surety rely on the defense that the changes made in reletting the contract released it from liability under the bond. Both Smith and the surety, in their pleadings, deny the existence of the privileges asserted by those claiming them.

This litigation grows out of the following facts:

On September 14, 1925, the Louisiana highway commission and the police jury of the parish of Calcasieu entered into a contract with Smith for the construction of what was known as Federal Aid Project 43-D, unit 1, being the roadway embankment for the Vinton-Orange Highway in Calcasieu parish. The embankment was to have been built by Smith, 1.857 miles in length, through the Sabine swamp, to a point on the Sabine river. This was a difficult place to construct an embankment, due to the marshy character of the soil and the difficulty in obtaining suitable dirt with which to build it. Smith was to receive a minimum price of $117,164.52 for the work, based on an estimated quantity of 325,457 cubic yards of “borrow” (that is, dirt taken from plots of ground near the sides of the embankment), complete in place, at 36 cents a - cubic yard. The contract provided that Smith should complete the work within six months, and, if he should fail to do so, then that he would pay the Louisiana highway commission $50 a day thereafter, until the completion of the work, as liquidated damages. Smith furnished a bond, under Act 224 of 1918, for $58,582.26, one-half of the minimum price he was to receive, which also represents the amount sued for, with the United States Fidelity & Guaranty Company as surety, conditioned for the faithful performance of the contract, and for the payment by the contractor and all subcontractors for all work done; labor performed, or material furnished in the construction of the embankment. The specifications, which formed part of the contract signed by Smith, for the purpose of guarding, among other things, against any error in the estimated quantity of “borrow,” necessary to be moved into place to complete the embankment, contained the following provisions, numbered 29 in the specifications, to wit:

“The contractor shall perform such work, in additional quantities other than those designated in the approximate estimate, as may be deemed necessary fully to complete the proposed construction as planned and contemplated and shall receive for such additional work payment in full, at prices shown in the contract and in the same manner as if such work had been included in the original estimate of quantities.”

The specifications, forming part of the contract, also contained the following provisions defining “roadway excavation” and “borrow,” and providing for the measurement of overhaul of excavation, and the payment therefor, as well as the basis of payment for putting all “borrow” complete in place, to wit:

*307 “72. Roadway Excavation. Roadway excavation shall include the removal and satisfactory disposal of all materials except borrow [defined in paragraph-76], necessary for the construction and preparation of the roadbed, sub-grade, shoulders, slopes, side ditches, incuts, trenches, waterways, intersections, approaches, private entrances, etc., as indicated and directed. * * *
“76. Borrow. When the amount of the embankment exceeds the amount of the excavation, sufficient suitable material shall be obtained by the contractor from the sides of the roadway, side ditches or other borrow pits as directed, by the engineer. This material shall be known as ‘borrow’ and shall be of a satisfactory quality for the purpose for which it is required. Borrow shall include removal and satisfactory placing of the additional material necessary to complete the embankment, subgrades, shoulders, etc. The widening of cuts will not be considered as ‘borrow.’
“77. Overhaul of Excavation. When the distance between the center of mass of any cut and the center of mass of the corresponding-embankment exceeds 400 feet, all of the material obtained from the cut and used in the embankment shall be known as ‘overhaul excavation,’ and the length of overhaul shall be measured as the distance between the center of mass of cut and center of mass of fill, minus 400 feet.
“82 (b). Borrow. All borrow (Defined in paragraph 76), will be paid for at the contract unit price per cubic yard for ‘Borrow’ complete in place, which price will include furnishing and placing the material, and all equipment, tools, labor and work incidental thereto.
“82 (c). Overhaul. Overhaul of excavation will be paid for at the rate of one (1$) cent per cubic yard per station of 100 feet. The amount of overhaul will be estimated in the manner specified under the heading ‘Overhaul of Excavation.’ ”

Before Smith bid on the work, he, in company with an engineer of the Louisiana highway commission, visited the location where the embankment was to be constructed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CENTRAL LOUISIANA ELEC. v. Giant Enterprises
371 So. 2d 641 (Louisiana Court of Appeal, 1979)
Slagle-Johnson Lumber, Inc. v. Landis Construction Co.
366 So. 2d 206 (Louisiana Court of Appeal, 1978)
National Surety Corp. v. Highland Park Country Club, Inc.
111 So. 2d 811 (Louisiana Court of Appeal, 1959)
Glens Falls Indemnity Co. v. Lluch
61 P.R. 822 (Supreme Court of Puerto Rico, 1943)
Sklar v. Oil Incomes, Inc.
133 F.2d 512 (Fifth Circuit, 1943)
Sklar v. Lilly-Thompson Drilling Corp.
45 F. Supp. 470 (W.D. Louisiana, 1942)
Anderson v. Harvey & Jones
154 So. 495 (Louisiana Court of Appeal, 1934)
Tennessee-Arkansas Gravel Co. v. Harvey
151 So. 133 (Louisiana Court of Appeal, 1933)
Williams Gray v. Stewart
147 So. 103 (Louisiana Court of Appeal, 1933)
H. R. Hayes Lumber Co. v. McConnell
146 So. 14 (Supreme Court of Louisiana, 1932)
Smith v. Smith
142 So. 132 (Supreme Court of Louisiana, 1932)
General Lumber & Supply Co. v. Hunter
134 So. 759 (Louisiana Court of Appeal, 1931)
Rester v. Moody & Stewart
134 So. 690 (Supreme Court of Louisiana, 1931)
Long Bell Lumber Co. v. S. D. Carr Const. Co.
133 So. 438 (Supreme Court of Louisiana, 1931)
Southern Gas Line, Inc. v. Dixie Oil Co.
133 So. 181 (Louisiana Court of Appeal, 1931)
Rester v. Moody & Stewart
130 So. 254 (Louisiana Court of Appeal, 1930)
Perry v. J. M. Lewis & Co.
129 So. 406 (Louisiana Court of Appeal, 1930)
State v. Miller
126 So. 422 (Supreme Court of Louisiana, 1930)
Lane v. E. J. Deas Co.
125 So. 514 (Louisiana Court of Appeal, 1929)
John H. Murphy Iron Works v. United States Fidelity & Guaranty Co.
124 So. 768 (Supreme Court of Louisiana, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
119 So. 56, 167 La. 301, 1928 La. LEXIS 2050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-smith-la-1928.