Lane v. E. J. Deas Co.

125 So. 514, 12 La. App. 382, 1929 La. App. LEXIS 799
CourtLouisiana Court of Appeal
DecidedDecember 31, 1929
DocketNo. 3030
StatusPublished
Cited by8 cases

This text of 125 So. 514 (Lane v. E. J. Deas Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane v. E. J. Deas Co., 125 So. 514, 12 La. App. 382, 1929 La. App. LEXIS 799 (La. Ct. App. 1929).

Opinion

ODOM, J.

On March 24, 1925, the E. J. Deas Company, Inc., entered into a contract with the police jury of Caddo Parish to pave a portion of the Shreveport-Blanchard public road for the sum of $110,000, and gave bond with the Aetna Casualty Company as surety for the faithful performance of the contract in accordance with the specifications. The contract was entered [384]*384into .and the bond given pursuant to the provisions of Act No. 224 of 1918, p. 406. The contractor defaulted and the surety company took over the contract, re-let the work to another concern, and the police jury turned over to the surety company the full amount of the contract price, less the amount which had been previously paid to the original contractor. This proceeding was in accordance with the bond, from which we quote the following:

“Upon failure of the principal to promptly and efficiently prosecute said work in any respect to the satisfaction of the Parish Engineer, the said sureties shall take charge of the work and complete the contract at their own expense, being allowed, however, any balance in the hands of the Police Jury due under said contract.”

Prior to the date on which the contractor defaulted, and while the work was in progress, the contractor wrote two orders or assignments, one dated June 6, 1925, and the other June 13th, in words and figures as follows:

“Parish of Caddo, Shreveport, Louisiana.

“Please pay--, of Shreveport, Louisiana, the amount of Seven Hundred Dollars Thirty Cents ($700.30) on final estimate for work on Shreveport-Blanchard road.

‘‘E. J. Deas Company, Inc.,

“By E. J. Deas, Pres.”

(Italics ours.)

The other is identical with the above, except as to the amount, which is $461.78. Mr. Deas, president of the contracting company, presented one of the orders to Mr. Bullen, parish engineer, who wrote thereon the following certificate:

“I hereby certify that there is due the E. J. Deas Company, Inc., the amount of $700.30 for work done on. Shreveport-Blanchard road to -June 5th, Inch

“J. T. Bullen,

“Engineer Caddo Parish.”

Mr. Deas presented the above to Mr. L. F. Clawson, parish treasurer, who wrote thereon the following:

“Accepted. L. F. Clawson, Parish Treas.”

The other order was presented to Mr. Gayle, chairman of the road committee, who wrote thereon the following:

“I certify that there is due the E. J. Deas Company, Inc., the amount of $461.78, for work done on Shreveport-Blanchard road to June 12th, Inch

“A. C. Gayle,

“Chairman of Road Committee.”

And Mr. Clawson indorsed it as follows:

In order to secure funds with which to carry on th.e work, Mr. Deas, .president of the company, sold these so-called certificates to 'the plaintiff, C. W. Lane, at a discount and inserted his name, thereon as transferee. Mr. Lane, subsequently told Mr. Clawson, the parish treasurer, and Mrs. Duringer, secretary of the police jury, that he had purchased these certificates. The contractor defaulted in August, and the surety company took over the contract on the 17th of that month.

On October 23rd following, Lane .filed a sworn statement of the amount due him with the recorder of mortgages, as provided in section. 2, Act No. 224 of 1918, which 'statement recites in part that the E. J. Deas Company, Inc., contractor, is due him the sum of $1,162.08 (being the total of the two certificates), “on account of having furnished money to said E. J. Deas Company, Inc., for the purchase of material in the construction of and the payment of labor on the Shreveport-Blanchard road.”.

Lane made demand on both the police jury and the surety company for payment, which demand was refused, and he brought [385]*385this suit against the Deas Company (then in the hands of receivers), the police jury, the surety company, Bullen, and Gayle, in solido. The receivers made no defense, and judgment went against them hy default, ordering them to pay the amount in course of administration. Plaintiff’s demands against all other defendants were rejected, and he appealed.

Counsel for plaintiff in the brief filed in this court say that “the Caddo Police Jury would have paid plaintiff the amount of the assignments had not the surety company intervened and opposed the payment and agreed to take over the work. In consequence of this agreement, the Police Jury turned over to the surety company the funds due the contractor, E. J. Deas Company. Therefore, the actual controversy is between the plaintiff and the surety company.”

The question whether the surety company is liable to plaintiff for the amount of this claim under the circumstances depends upon the obligation which it assumed under the contract and bond, construed, as they must he, with reference to the law under which they were written.

The law relating to public works in force at the time this contract was entered into was Act No. 224 of 1918, section 1 of which provides that, when public roads are about to be constructed under a contract in excess of $500, at the expense of any parish, the parties shall reduce the contract to writing and sign it, and that it shall be the duty of the official representing the parish to require of the contractor bond, with surety, which contract and bond shall he recorded in the office of the recorder of mortgages. The letter of the law was complied with in this case. Under the terms of the contract, which is in evidence, the contractor obligated itself to furnish all materials and to do and perform all labor and work necessary for the completion of the paving according to the specifications, and the parish of Caddo obligated itself to pay for said work the sum of $110,000, “when completed in accordance with the plans and specifications.”

The bond furnished by the contractor is written in exact accord with the law; the obligation of the surety being to “secure the faithful performance of the contract, and the full payment of all suh-contractors, workmen, laborers, mechanics, and furnishers of materials and supplies,” according to the specifications.

The bond further specifically provided that, “upon failure of the principal to promptly and efficiently prosecute said work, in any. respect to the satisfaction of the engineer, the said sureties shall take charge of the work and complete the contract at their own expense, being allowed, however, any balance of the fund in the hands of the Police Jury due under said contract.” The contractor defaulted, and the surety took over the work, and the parish paid to it the balance in its hands under the contract.

That the parish of Caddo has fully complied with the contract and discharged its obligation cannot, we think, be questioned. It -agreed to pay $110,000 to have the road paved, and this it has done. There was never any objection made by this claimant or any other, to the solvency or sufficiency of the bond, which was timely recorded with the contract in the office of the recorder of mortgages of the parish where the work was to be done, all in accordance with the act. By thus complying with the law, the parish was relieved from the payment of any amount beyond the contract price. There is therefore no room [386]*386for any demand by any claimant against the parish.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guillory v. Calcasieu Parish Police Jury
410 So. 2d 1213 (Louisiana Court of Appeal, 1982)
Cox v. WM Heroman & Co., Inc.
298 So. 2d 848 (Supreme Court of Louisiana, 1974)
Stein v. Williams Lumber Co.
36 So. 2d 62 (Louisiana Court of Appeal, 1948)
Glens Falls Indemnity Co. v. Lluch
61 P.R. 822 (Supreme Court of Puerto Rico, 1943)
Columbia Oil Co. v. Police Jury of Natchitoches Parish
184 So. 580 (Louisiana Court of Appeal, 1938)
Puritan Chemical Co. v. Vernon Parish Police Jury
178 So. 888 (Louisiana Court of Appeal, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
125 So. 514, 12 La. App. 382, 1929 La. App. LEXIS 799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-v-e-j-deas-co-lactapp-1929.