OVERTON, J.

On July 6, 1922, Leopold Klein, the plaintiff herein, entered into a written contract with the contracting and building firm of J. D. & J. M. Collins to erect a duplex apartment house on General Pershing street, in the city of New Orleans, for the sum of $10,310, payable in five installments of $2,062 each; the last installment being payable 45 days after the completion and recordation of the acceptance of the work, and the production of a certificate from the recorder of mortgages showing that no liens for labor performed or material furnished were of record against the building. The contractors, pursuant to the provisions of Act No. 221 of 1914, as amended by Act No. 262 of 1916, furnished a bond in favor of the owner, all subcontractors, workmen, laborers, mechanics, and furnishers of material, as their interests might appear, for the faithful performance of the contract, and for the payment of all subcontractors, workmen, mechanics, furnishers of material, etc., “up to the sum of $5,155,” with the Boyal Indemnity Company as surety thereon.

The contractors undertook to erect the building. About the time that they were entitled, under the terms of the contract, to the second payment, considerable complaint was made by some of the furnishers of material to the effect that they were not being paid. The architect examined into the matter and found, not only that some of the materialmen had not been paid the full amount that was due them, but that the contractors were in arrears with some of the laborers. The architect spoke to the contractors relative to the complaints against them, and they *707 advised him that they did not have the funds with which to make the payments, and sought his advice as to what to da under the circumstances. He advised them that the logical thing to do would be to see the surety on their bond. A conference was held on August 31, 1922, in the office of the surety on the bond, at whiclkplaintiff’s attorney, J. H. Wiener,. the architect, Albert Bear, the contractors, J. D. & J. M. Collins, and S'. T. Mikell, the representative and attorney in fact of the surety company, were present.

It is contended by plaintiffs, and by those having claims against the building, that at this conference it was agreed that the surety company would undertake the completion of the building, and that all future payments would be made to it, .and that the company would disburse the money to be thus paid. On the other hand, the surety company contends that the only obligation which it assumed at the conference mentioned was the obligation of receiving and disbursing the money to be paid by the owner for the erection of the building.

Pretermitting for the moment what was actually agreed to at this conference, it may be said that the building was finally completed, though some time after the elate fixed in the contract for its completion.

At the time of the completion of the building, plaintiff had made all of the payments, stipulated in the contract, except the last payment, and had also paid for all extra work done. At the time of the completion of the building, o,r shortly thereafter, there were also of record against the building a number of claims.

In view of these claims, plaintiff deposited in court the last payment dile by him, less $930, which he claimed he was entitled tó as penalty, under the terms of the contract for delay in the delivery of the building to him, and instituted the present proceedings, provoking a concursus, to which he made the surety company and the contractors parties, and in ¿phich he prayed that those who had filed cláimsj against the premises fie cited to appear ^cf assert their rights against the fund depfosited by him and against the contractors ,and surety company, and prayed, among other things, that the liens, resulting from the Recordation of the claims against the premises be canceled, and that he be decreed relieved of all liability to any person whatsofever on account of stiid contract. Later, under orders of court,\plaintiff deposited in court the $930 withheld by him on the last payment, thus making,the sum of $2,062 deposited by him altogether.

The surety company appeared and filed an answer to the proceeding. The matter was referred to a special commissioner appointed by the court. Those who had filed claims against the building appeared before the commissioner and made proof - of their claims. At the hearing had, the commissioner found that these claims were due. He also found that the total of the claims proved, including the damages claimed by, pjaintiff for delay in delivering the building, but exclusive of the amount due him for .acting as commissioner and such amount as might be found due to the attorney for plaintiff as fees, exceeded by several thousand dollars the total of the funds on hand with which to pay these claims and the amount of the bond signed by the surety company. The commissioner also found, among other things, as we appreciate his findings, that, at the conference held on August 31, 1922, after the contractors had admitted that they were without sufficient funds to complete the building, the surety agreed to undertake and did undertake, to complete it and to receive and disburse all further payments to be made thereon.' In view of these and other findings, the commissioner, in a judgment prepared by him, recommended to the lower court that there be judgment in favor of the claimants, who had proved their claims, for the amounts thereof, naming the claimants *709 and stating the amounts, and against the contractors, the surety company, and plaintiff, in solido, and that there he judgment in favor of plaintiff and against the surety company for the amounts found due and owing the various claimants, for which amounts judgment was recommended against plaintiffs in favor of said claimants, this recommendation evidently having been made for' the purpose of protecting plaintiff as against the surety company. The commissioner also recommended that judgment be rendered in favor of the attorneys for the plaintiff for the sum of $250, as attorneys’ fees, and against the contractors and surety company in solido, and that there be judgment against these defendants in solido in favor of plaintiff for $930 damages for the delay in delivering the building. The report of the commissioner contains other recommendations unnecessary to mention.

The findings and recommendations of the commissioner were excepted to by the surety company and by the attorneys for plaintiff; the latter complaining of the amount recommended as their fee. These exceptions were overruled by the lower court, and judgment was rendered in accordance with the recommendations of the commissioner.

The surety company and plaintiff have appealed from the judgment rendered; the appeal of plaintiff bearing the number 27245, appearing in the title, and that of the surety company the number of 26860, appearing therein. The attorneys for plaintiff have filed an answer to the appeal, praying that the fees allowed them be increased from $250 to $1000. No one else complains of the judgment rendered.

The only complaint that plaintiff seems to make against the judgment rendered is as to the fee allowed his attorneys, which he deems insufficient.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm.
2016 Ohio 8580 (Ohio Court of Claims, 2016)
Scott v. Red River Waterway Commission
926 So. 2d 830 (Louisiana Court of Appeal, 2006)
Barrientos v. Government of Capital
97 P.R. 539 (Supreme Court of Puerto Rico, 1969)
Barrientos v. Gobierno de la Capital
97 P.R. Dec. 552 (Supreme Court of Puerto Rico, 1969)
Caron v. Andrew
284 P.2d 544 (California Court of Appeal, 1955)
American Surety Co. of New York v. Ryan
170 So. 34 (Supreme Court of Louisiana, 1936)
New York Indemnity Co. v. Niven
133 So. 261 (Supreme Court of Alabama, 1931)
Lane v. E. J. Deas Co.
125 So. 514 (Louisiana Court of Appeal, 1929)
Silver v. Harriss
115 So. 376 (Supreme Court of Louisiana, 1927)
Dendinger, Inc. v. Royal Indemnity Co.
5 La. App. 302 (Louisiana Court of Appeal, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
106 So. 120, 159 La. 704, 1925 La. LEXIS 2290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/klein-v-j-d-j-m-collins-la-1925.