Cox v. WM Heroman & Co., Inc.

298 So. 2d 848
CourtSupreme Court of Louisiana
DecidedJune 10, 1974
Docket54094
StatusPublished
Cited by97 cases

This text of 298 So. 2d 848 (Cox v. WM Heroman & Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cox v. WM Heroman & Co., Inc., 298 So. 2d 848 (La. 1974).

Opinion

298 So.2d 848 (1974)

Charles W. COX, Plaintiff-Appellee-Relator,
v.
W. M. HEROMAN & CO., INC., and American Employers Insurance Co., Defendants-Appellants-Respondents.

No. 54094.

Supreme Court of Louisiana.

June 10, 1974.
Rehearing Denied August 30, 1974.

*850 Robert P. Breazeale, Van R. Mayhall, Jr., Breazeale, Sachse & Wilson, Baton Rouge, for defendant-respondent.

R. Boatner Howell, Jr., Howell & Brown, Baton Rouge, for plaintiff-applicant.

TATE, Justice.

A subcontractor ("Cox") sues his general contractor ("Heroman") for the balance due on the subcontract. The general contractor claims a credit for a payment made directly by Heroman to a supplier ("Reulet") of the subcontractor. The trial court did not allow the credit, as not authorized by the subcontract. The court of appeal reversed the trial court's disallowance of the credit. 282 So.2d 734 (La.App. 1st Cir. 1973). We granted certiorari. 286 So.2d 656 (1973).

The issue before us is two fold:

(1) Was Heroman entitled to pay Cox's creditor Reulet directly, over Cox's protect, thus (under Civil Code Article 2134) extinguishing Cox's debt to Reulet as to the extent of the payment and also giving Heroman a right to receive reimbursement of this payment from Cox?;

(2) If Heroman was not entitled to pay Cox's debt to Reulet, nevertheless was not Heroman (by his payment and express agreement with Reulet) subrogated to recover Reulet's debt against Cox (Article 2159), thus entitling Heroman in the present suit to reduce the balance due by Heroman to Cox under the subcontract to the extent that it is extinguished (through the compensation of two debts, Article 2207) by the subrogated (Reulet) debt due by Cox to Heroman?

Facts

Heroman as general contractor entered into a construction contract with a university *851 in the amount of over five hundred thousand dollars. Heroman and Cox entered into a subcontract by which Cox agreed to perform the electrical work for $37,590.00.

In the course of construction, progess payments were made by Heroman to Cox totalling $27,681.27. (An additional ten percent of the total of the progress estimates was retained by Heroman, in accordance with the subcontract agreement, for payment upon final acceptance.)

As the completion of both the general contract and the subcontract neared, the present controversy arose. Heroman was informed by several suppliers of Cox on the job that Cox had not paid them, and Reulet (Cox's principal supplier) informed Heroman that it would lien the job.

The facts forming the basis of the litigation occurred when on April 14, 1971 Heroman paid Reulet directly $4,349.74 to credit against Cox's debt due Reulet for supplies on the job. This sum was the total balance then due by Heroman to Cox. (It did not include the ten percent retained per the contract.) The payment was specifically made for the account of Cox due for supplies on the present contract. Cox was sent a carbon copy of the letter by which payment was made.

Prior to this payment of April 14, 1971, Reulet had conferred with Heroman about an unpaid amount of $8,360.55 due for supplies furnished Cox for the contract. Heroman had then sent to Cox a check for $4,439.74, payable to Cox and Reulet jointly. (This was the same amount later paid Reulet directly, being the then total unpaid balance due by Heroman to Cox.)

Cox returned the check to Heroman. He stated that he considered this direct payment improper and unacceptable. He alleged that there were considerable overcharges claimed by Reulet amounting to over twenty-five hundred dollars.[1]

Reulet then wrote Heroman that it would place a lien on the job unless the amount due was paid at this time. Reulet's letter concluded, that, if Heroman would pay the unpaid invoices due by Cox, Heroman "is subrogated to all rights that we have against Cox in connection with this job and such payment."[2]

Upon receipt of this letter, Heroman immediately paid Reulet the full balance then due Cox ($4,349.74) by progress estimates, as stated above. Reulet accepted this payment, credited Cox's account, and did not lien the job.

Cox then on April 22, 1974 filed a lien for the unpaid balance due on the job. Correspondence introduced by Cox shows that unsuccessful negotiations were subsequently conducted between Cox, Reulet, and other suppliers in an effort to allocate the remaining amount due by Heroman to Cox to unpaid accounts of Cox resulting from his performance of his subcontract.

On December 27, 1971, Cox filed the present suit against Heroman and its surety (American Employers) to recover $10,016.62, then allegedly due under the contract, together with ten percent statutory attorney fees. The suit alleged that the unpaid balance included the sum of $4,349.74 *852 74 which had been paid by Heroman to Reulet. In the suit, Cox specifically alleges that he was contesting the total amount claimed by Reulet ($8,360.55) because he estimates "Reulet overcharges and errors in the amount of $2,500.00." See Art. 9 of petition.

Cox alleged that Heroman owed him: $5,448.99 representing the final draw and retainage (which Heroman in its answer conceded owing, except for back charges of $304.45), an alleged add-on due of $107.89 (which both previous courts found not owing), and the $4,349.74 previously paid by Heroman to Reulet.

Heroman's answer pleaded the facts of the dispute, and acknowledged liability for only the final draw and retainage of $5,254.54.

The trial court held that Heroman was not entitled under its contract to pay Reulet, Cox's creditor, directly. It therefore disallowed credit to Heroman for such payment and awarded Cox judgment for that sum, plus the amount due for the final draw and retainage, for a total amount of $9,908.73.[4]

As earlier noted, the court of appeal concluded that the trial court was in error in refusing to allow Heroman credit against Cox's claim for the amount paid by Heroman to extinguish pro tanto Reulet's claim against Cox for supplies furnished for the present job. The court of appeal essentially held that Heroman was entitled to pay the debt due by Cox to Reulet and to be reimbursed by Cox for this payment, by reason of Civil Code Article 2134.[5] See Standard Motor Car Company v. State Farm Mutual Automobile Insurance Co., 97 So.2d 435 (La.App. 1st Cir. 1957).

1. "Payment" under Article 2134

We granted certiorari primarily because of our doubt that, under the circumstances here shown, the debtor Heroman could extinguish a debt due to its creditor Cox by paying, not Cox, but Cox's creditor. We entertained this doubt because: (a) Cox expressly opposed such payment by Heroman of his debt due Reulet; instead, Cox expressly desired to receive amounts due him by Heroman for purposes of negotiating the payment due by him to Reulet in connection with certain disputed items; (b) The subcontract between Heroman and Cox expressly provided for Heroman's remedy, in the event of Cox's non-payment of suppliers on the job, namely, Heroman was to withhold payments due Cox until the grounds for non-payment were removed.

Article 2134 (quoted in full in Footnote 5) provides that an "obligation may even be discharged by a third person in no way concerned in it", provided that, "if he act in his own name, he be not subrogated to the rights of the creditor." (Italics ours.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franklin v. Regions Bank
W.D. Louisiana, 2021
Curole v. Delcambre
224 So. 3d 1074 (Louisiana Court of Appeal, 2017)
Bach v. Board of River Port Pilot Commissioners
193 So. 3d 355 (Louisiana Court of Appeal, 2016)
Turner v. Hidden Lake, LLC of AL
163 So. 3d 66 (Louisiana Court of Appeal, 2015)
Aaron Emigh v. West Calcasieu Cameron Hospital
145 So. 3d 369 (Supreme Court of Louisiana, 2014)
Vagelos v. Abramson
126 So. 3d 639 (Louisiana Court of Appeal, 2013)
Caceras v. Work
110 So. 3d 275 (Louisiana Court of Appeal, 2013)
Schnell v. Mendoza
105 So. 3d 874 (Louisiana Court of Appeal, 2012)
Udomeh v. Joseph
103 So. 3d 343 (Supreme Court of Louisiana, 2012)
Aaron & Turner, L.L.C. v. Perret
22 So. 3d 910 (Louisiana Court of Appeal, 2009)
Cameron v. Bruce
981 So. 2d 204 (Louisiana Court of Appeal, 2008)
DOMINION EXPLORATION & PRODUCTION v. Waters
972 So. 2d 350 (Louisiana Court of Appeal, 2007)
Jackson v. TULANE MEDICAL CENTER HOSP.
942 So. 2d 509 (Supreme Court of Louisiana, 2006)
Kent v. Epherson
864 So. 2d 708 (Louisiana Court of Appeal, 2003)
Webb v. Webb
835 So. 2d 713 (Louisiana Court of Appeal, 2002)
National Gypsum Co. v. Ace Wholesale
738 So. 2d 128 (Louisiana Court of Appeal, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
298 So. 2d 848, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cox-v-wm-heroman-co-inc-la-1974.