State v. Miller

126 So. 422, 169 La. 914, 1930 La. LEXIS 1615
CourtSupreme Court of Louisiana
DecidedJanuary 6, 1930
DocketNo. 29171.
StatusPublished
Cited by16 cases

This text of 126 So. 422 (State v. Miller) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Miller, 126 So. 422, 169 La. 914, 1930 La. LEXIS 1615 (La. 1930).

Opinions

O’NIELL, O. J.

This is a eoncursus proceeding in settlement of the unpaid claims for work done and materials furnished in the construction of a highway through the parish of Jefferson. The only matter in dispute is *919 the liability, or extent of liability, of the Southern Surety Company, as surety on the bond of the contractor, Paxton Millér, to the several claimants for work done or materials furnished.

Miller’s contract was with the state of Louisiana and the parish of Jefferson, and was governed by the provisions of Act No. 224 of 1918. Accordingly, the contractor’s bond guaranteed the faithful performance of the contract and the payment by the contractor and all subcontractors for all work done, labor performed and material furnished in the construction of the road.

Miller failed to complete the work; and the surety company took it over and completed it at the cost of $19,708.24, and received from the state highway department $16,067.58, leaving a balance of $3,640.66, which the surety company claims out of the fund deposited by the state in the registry of the court. The amount deposited, being the balance due under the contract, is $10,-247.96, which is not of itself sufficient, but which, with the amount of the bond, is sufficient, to pay all outstanding claims for labor and material.

The 'district court gave judgment ordering the deposit of $10,247.96 (less a fee of $750 to be paid- the commissioner) distributed pro rata among the following named eight claimants, defendants in the suit, and gave judgment in their favor and against the contractor and the surety company, in solido, for the balance which would then remain due on the amount allowed each of them, viz.:

(1)Interstate Trust & Banking Company, as assignee and subrogee of the claims of several laborers and furnishers of material, $15,804.68, with interest at 5 per cent, from the 27th of May, 1922;

(2) Prentice E. Edrington, as assignee and subrogee of the claims of several laborers, $2,107.18, with interest at 5 per cent, from the 26th of April, 1923, and 10 per cent, attorney’s fees;

(3) John T. Gibbons, for materials furnished, $1,437.66, with interest at 5 per cent, from the 11th of May, 1922, and 10 per cent, attorney’s fees;

(4) Eelix & Block, for .materials furnished, $61.88, with interest at 5 per cent, from the 22d of May, 1922;

(5) Kenner Lumber Company, for materials furnished, $548.83, with interest at 5 per cent, from the 31st of May, 1922, and 10 per cent, attorney’s fees;

(6) Jahncke Service, Inc., for materials furnished, $1,858.33, with interest at 5 per cent, from the 31st of May, 1922, and 10 per cent, attorney’s fees;

(7) Ole K. Olsen, for materials furnished, $903.29, with interest at 5 per cent, from the 9th of March, 1923, and 10 per cent, attorney’s fees; and

(8) Stanley A. Stewart, for materials furnished, $67.85, with interest at 5 per cent, from the 19th of March, 1923, and 10 per cent, attorney’s fees.

As the surety company is the only party appealing from the judgment, it is not subject to reversal or amendment in any respect except that the liability of the surety company to the eight parties above named, or to any of them, is subject to reduction. In all other respects the judgment appealed from is final.

It is admitted by counsel for appellant that the judgment in favor of Ole K. Olsen, for $903.29, with interest at 5 per cent, per annum from the 9th of March, 1923, and 10-per cent, attorney’s fees, is correct. ■ The bill *921 represents the price of steel sold to the contractor and .used in the reinforcement of concrete in the construction of the road. The claim therefore represents the price of material which actually went into and formed part of the construction. The 10 per cent, attorney’s fee was properly al-lo-wed because the claimant made amicable demand on the contractor and his surety and 30 days elapsed thereafter without payment being made, before suit was filed, and the claimant got judgment for the full amount of his claim. He complied, therefore, with the conditions on which alone the statute (section 8 of Act 224 of 1918) declares that a claimant for material furnished or work done on a public road or other public work shall be allowed 10 per cent, attorney's fee on the amount of his claim.

It is admitted also by counsel for appellant that the judgment in favor of Ken-ner Lumber Company for $548.83, with interest at 5 per cent, per annum from the 31st of May, 1922, is correct; but it is denied that the company is entitled to the attorney’s fee, because there is no proof that a demand for payment was made upon the contractor 30 days before judicial demand. In fact there is no proof that amicable demand was made upon the contractor at any time. There is proof that amicable demand was made upon the surety 30 days before the litigation arose; but the statute requires that such demand, without avail, shall be made upon both the contractor and the surety on his bond, in order that the claimant may be allowed the attorney’s fee. The allowance of the attorney’s fee, under section 8 of Act 224 of 1918, is in the nature of a penalty, which should not be imposed unless the claimant has complied literally with the requirements of the statute. In Silver v. Harriss, 165 La. 97, 115 So. 380, 381, it was said:

“Plaintiff also prays for an amendment of the judgment so as to award him the attorneys’ fees demanded in his petition. Our conclusion is that he is not entitled to this relief. Section 8 of Act 224 of 1918, under which the claim is asserted, requires as a condition precedent for a recovery thereon that an amicable demand should have been made * * * prior to the institution of the suit. No such demand was made. The service upon the principal and the surety of copies or duplicates of the sworn statement prepared for filing with the authorities for whom the work was done and for recordation in the mortgage records of the parish in accordance with other sections of the statute is not the amicable demand required.”

For the reason stated, the attorney’s fees allowed Jahncke Service, Inc., and Prentice E. Edrington are contested and must be rejected. Neither of these claimants made amicable demand upon the contractor 30 days before the litigation arose. The demand upon the surety- was not sufficient. Besides, Edrington did not recover all that he demanded of the surety, because his demand included 8 per cent, per annum interest on the amount of his claim, and he was entitled to and was allowed only 5 per cent, interest. He directs our attention to the fact that, in the instrument by which the laborers transferred their claims to him, the contractor acknowledged that the claims were due; hence Edrington argues that it would have been a vain and useless proceeding for him to make amicable demand upon the contractor for the payment of the claims. The presumption that a demand upon the contractor would be without avail does not dispense with the necessity of making the demand as a condition precedent to condemning the surety to pay the penalty of attorney’s fees.

*923

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilkin v. Dev Con Builders, Inc.
561 So. 2d 66 (Supreme Court of Louisiana, 1990)
Davis v. Franklin Parish School Bd.
412 So. 2d 1131 (Louisiana Court of Appeal, 1982)
Daigle v. Great American Indemnity Co.
70 So. 2d 697 (Louisiana Court of Appeal, 1954)
R. P. Farnsworth & Co. v. Electrical Supply Co.
112 F.2d 150 (Fifth Circuit, 1940)
Wunderlich v. Palmisano
177 So. 843 (Louisiana Court of Appeal, 1938)
State Bank of Wheatland v. Turpen
37 P.2d 679 (Wyoming Supreme Court, 1934)
Tennessee-Arkansas Gravel Co. v. Harvey
151 So. 133 (Louisiana Court of Appeal, 1933)
Williams Gray v. Stewart
147 So. 103 (Louisiana Court of Appeal, 1933)
H. R. Hayes Lumber Co. v. McConnell
146 So. 14 (Supreme Court of Louisiana, 1932)
J. T. Gibbons, Inc. v. Stable
144 So. 641 (Louisiana Court of Appeal, 1932)
Calatex Oil & Gas Co. v. Smith
144 So. 243 (Supreme Court of Louisiana, 1932)
J. Watts Kearny & Sons v. Perry
141 So. 13 (Supreme Court of Louisiana, 1932)
Long Bell Lumber Co. v. S. D. Carr Const. Co.
133 So. 438 (Supreme Court of Louisiana, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
126 So. 422, 169 La. 914, 1930 La. LEXIS 1615, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-miller-la-1930.