Spencer, White & Prentis, Inc. v. United States of America Environmental Protection Agency

641 F.2d 1061, 28 Cont. Cas. Fed. 81,088
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 10, 1981
DocketNo. 157, Docket 80-6099
StatusPublished
Cited by1 cases

This text of 641 F.2d 1061 (Spencer, White & Prentis, Inc. v. United States of America Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spencer, White & Prentis, Inc. v. United States of America Environmental Protection Agency, 641 F.2d 1061, 28 Cont. Cas. Fed. 81,088 (2d Cir. 1981).

Opinion

MANSFIELD, Circuit Judge:

Plaintiffs, Spencer, White & Prentis, Inc. (Spencer), a joint venture with its subsidiary Seatec International Ltd., and Morrison-Knudsen Company, Inc., were bidders on a contract for completion of a federally subsidized sewer system being constructed for the County of Suffolk, New York (Suffolk), a state subdivision.1 Plaintiffs claim that their bids were rejected by Suffolk in favor of another joint venture, Edward B. Fitzpatrick, Jr. Construction Corp. and Arundel Corp. (Fitzpatrick-Arundel), as the result of fraud, contractual invalidity and violation of regulations issued under the Federal Water Pollution Control Act, 33 U.S.C. §§ 466, et seq. (Act). After failing to obtain relief from the United States Environmental Protection Agency (EPA), which had granted funds under the Act for the project and therefore exercised some supervisory administration over it, plaintiffs sued that Agency, Suffolk and the Great American Insurance Company (American), surety for Fitzpatrick-Arundel, to whom the contract was let by Suffolk after renegotiation. Plaintiffs sought damages and declaratory relief. Judge Henry Bramwell granted summary judgment in favor of the defendants dismissing the action on the ground that rejection of plaintiffs’ bids was, as found by the EPA Regional Administrator, for “good cause” under the Act. We affirm.

[1063]*1063In 1977 Fitzpatrick-Arundel was awarded a contract by Suffolk to lay sewer pipe for the county’s federally subsidized water pollution control project in Great South Bay, near Islip, New York. As low bidder it agreed to construct the sewer pipe portion of the project for $10,646,000. Defendant Great American Insurance Company was the surety for Fitzpatrick-Arundel’s bid. The sewer pipe was part of a water pollution control project to be constructed for Suffolk’s Southwest Sewer District No. 3 at an estimated cost of $307,600,000, of which $230,700,000 would be reimbursed by the EPA to Suffolk under the terms of the Federal Water Pollution Control Act, 33 U.S.C. §§ 466, et seq., and the Clean Water Act, 33 U.S.C. § 1282.

In April, 1979, Suffolk announced that it considered Fitzpatrick-Arundel to be in default for inadequate progress on the job. Negotiations then began with the surety, American, to determine the future course of the project. When these negotiations reached an impasse, Suffolk advertised for bids to complete the unfinished part of the project, without announcing that it was still negotiating with the surety or that its solicitation of bids was only tentative. Spencer was the lowest responsive bidder at $13,-850,000, and plaintiff Morrison-Knudsen Company was second lowest at $27,000 more.

Meanwhile Suffolk continued negotiations with the surety. On July 27, 1979, Spencer filed with Suffolk a bid protest, as permitted by 40 C.F.R. § 35.939,2 issued by the EPA under the Act, asserting that it should be awarded the contract. On August 9, Suffolk and the surety signed a new contract, in which Fitzpatrick-Arundel was reinstated to complete the job. Pursuant to 40 C.F.R. § 35.939(h), Spencer asked the EPA to send Suffolk and the surety a letter prohibiting them from executing the new contract until 10 days after delivery of the protested decision to the parties in interest. The EPA did so. The parties disagree over whether Suffolk complied with this requirement, with Spencer claiming that the contract was executed on August 9 and Suffolk claiming that only the surety executed the contract on August 9, while Suffolk waited until September 18 to execute the contract for its part. On August 13, 1979, Suffolk informed plaintiffs that it was rejecting their protest.

Spencer next filed a protest appeal with the Regional Administrator of the EPA which, as the funding agency, performs a general supervisory function over such projects. Spencer claimed that the surety had waived its right to complete the job by failing to reach an agreement with Suffolk prior to the latter’s advertisement for new bids, that Suffolk had waived its right to continue negotiations with the surety for completion of the job by failing to require the surety to complete the job before advertising for new bids, that Suffolk had engaged in bid fraud by advertising for new bids without disclosing that it was still negotiating with the surety, and that Suffolk’s rejection of the bids was not based on “good cause,” as required by § 35.938-4(h)(2), which states “Unless all bids are rejected for good cause, award shall be made to the low, responsive, responsible bidder.” Jurisdiction -to protest before the Administrator was premised upon this provision and on the bid advertisement’s statement, in conformity with 40 C.F.R. § 35.-938-4(b)(5), that the procurement would be “subject to regulations contained in 40 C.F.R. 35.936, 35.938, and 35.939.”

The Regional Administrator rejected plaintiffs-appellants’ claim, finding that Suffolk had acted with good cause in rejecting all bids for the completion contract. He accepted Suffolk’s argument that it felt constrained to let the surety continue with the contract because it believed FitzpatrickArundel would sue it for wrongful termination and knew that a victory for Fitzpatrick-Arundel in that suit would cancel the [1064]*1064surety’s obligation, leaving the county with a bill for significantly more than the $10,-646,000 originally budgeted. By agreeing with the surety to let Fitzpatrick-Arundel continue with the job, the Regional Administrator observed, Suffolk was increasing the likelihood that any costs above the originally budgeted amount would be borne by the surety rather than by Suffolk County taxpayers. Having found the County’s rejection to be supported by good cause, he declined to rule on whether Spencer’s procurement procedures violated federal law. Finally, in exercise of his duty under federal regulations, the Administrator declined to examine issues which rested primarily on state law. Accordingly, he dismissed all claims against Suffolk and the surety.3

Appellants’ suit in the federal district court challenged the Regional Administrator’s decision, seeking damages and declaratory relief. On May 29, 1980, Judge Bramwell upheld the Regional Administrator in an order granting summary judgment to the defendants. Judge Bramwell rejécted defendants’ jurisdictional attacks on the appellants’ case, but agreed that the bid rejection was supported by good cause and was not arbitrary or capricious.

DISCUSSION

The role of the federal government in overseeing bidding for construction contracts partially funded under the Federal Water Pollution Control Act is narrowly circumscribed. Once the EPA has granted funds to projects like the parent project in the present case for the pipeline job in Great South Bay, it plays only a general supervisory role over the administration of the projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spencer, White & Prentis, Inc. v. United States
641 F.2d 1061 (Second Circuit, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
641 F.2d 1061, 28 Cont. Cas. Fed. 81,088, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spencer-white-prentis-inc-v-united-states-of-america-environmental-ca2-1981.