Morgan Associates v. United States Postal Service

511 F.2d 1223
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 25, 1975
Docket790
StatusPublished
Cited by3 cases

This text of 511 F.2d 1223 (Morgan Associates v. United States Postal Service) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgan Associates v. United States Postal Service, 511 F.2d 1223 (2d Cir. 1975).

Opinion

511 F.2d 1223

MORGAN ASSOCIATES, a Joint Venture of Terminal Construction
Corporation, et al., Plaintiff-Appellant,
v.
UNITED STATES POSTAL SERVICE et al., Defendants-Appellees,
NAB-Lord Associates, a Joint Venture of NAB Construction
Corp. and Lord Electric Co., Inc., Intervenor-Appellee.

No. 790, Docket 75--7058.

United States Court of Appeals,
Second Circuit.

Argued Feb. 10, 1975.
Decided Feb. 25, 1975.

Allen Ross, New York City (M. Carl Levine, Morgulas & Foreman, Jerrold Morgulas, New York City, on the brief), for appellant.

Patrick H. Barth, Asst. U.S. Atty. (Paul J. Curran, U.S. Atty., S.D.N.Y., Gerald A. Rosenberg, Asst. U.S. Atty., on the brief), for defendants-appellees.

Eli Saul Cohn, New York City (McDonough, Schneider, Marcus Cohn & Tretter, Franklin E. Tretter, New York City, on the brief), for intervenor-appellee.

Before HAYS and FEINBERG, Circuit Judges, and HOLDEN, District Judge.*

FEINBERG, Circuit Judge:

Appellant Morgan Associates1 brought an action in the United States District Court for the Southern District of New York seeking to enjoin the United States Postal Service from awarding to intervenor-appellee Nab-Lord Associates a contract for the reconstruction and mechanization of the Morgan Station Postal Facility in New York City. Morgan's bid on the contract of $54,440,000 was second lowest; Nab-Lord, at a bid of $51,480,000, was lowest. On January 20, 1975, Judge Milton Pollack dismissed Morgan's complaint, concluding that Morgan lacked standing to challenge the Postal Service's imminent award of the contract. This appeal was promptly taken and expedited. We affirm the judgment of the district court but on a different theory.

The basis of Morgan's suit is that an award to Nab-Lord would violate the general spirit of competitive bidding on Postal Service contracts and is specifically prohibited by section 18--511 of the Interim Regulations for the Procurement of Construction contained in the Postal Facilities Contracting Bulletin, which provides:

No contract for construction of a project shall be awarded to a firm or person that designed the project, except with the approval of the Assistant Postmaster General, Real Estate and Buildings Department or his authorized designee.

In support of this legal claim, Morgan alleges substantially the following in its complaint and supporting documents. Nab-Lord's subcontractor for the mechanized mail-handling portion of the construction will probably be Rohr-Plessey Corporation. The president of Rohr-Plessey is Paul Hendrickson, who was until 1970 the Director of Operations of the Department of Research and Engineering of the old Post Office Department.2 In that capacity, Hendrickson was privy to information regarding the initial planning of the Morgan Station renovation. Also associated with Hendrickson and perhaps with Rohr-Plessey are Knight and Cargill, two of his former subordinates at the Post Office; the latter two were apparently employed by the firm that developed the final design specifications for the mechanization work. It is further alleged that Hendrickson told various persons where the Postal Service stood on their proposals involving the project; that Rohr-Plessey was actually going to be a member of a joint venture with Nab-Lord until shortly before the bidding deadline and thus would have worked closely on the bid; and that Morgan sought a quotation from Rohr-Plessey on the mechanization subcontracting but was ignored.

As indicated, Judge Pollack never reached the merits of Morgan's legal claim, holding that Morgan did not have standing under our decision in Edelman v. Federal Housing Administration, 382 F.2d 594, 597 (2d Cir. 1967). In dismissing the complaint, the judge also concluded that the Postal Reorganization Act, see note 2 supra, specifically made the Administrative Procedure Act inapplicable to Postal Service bidding procedures; the judge thought this reflected congressional intent to allow the newly established Postal Service to run its operations as a business would, free from delay caused by judicial acrutiny of bids.

The briefs on appeal understandably deal at length with the question of standing. We agree that the issue is a troublesome one in this case. Ordinarily we would feel constrained to decide, as Judge Pollack did, whether a plaintiff has standing to sue before considering the merits of its claim. But in this suit, time is of the essence. The bids have been extended twice, once during the district court proceeding and again, at our suggestion, after oral argument in this court. The bids will expire shortly, and we have been advised the low bid cannot be extended. No doubt construction costs are increasing daily. We know from experience that the Postal Service needs all the help it can get to speed its handling of the mails. In addition, there has been a significant development since Judge Pollack's decision that completely undercuts appellant's position. Because of this unusual need for a prompt decision, and because we consider appellant's legal position on the facts before us so weak on the merits, we affirm the judgment for appellee without passing upon the standing issue.3

Morgan's case on the merits is that the Postal Service has not complied with its own regulations. Morgan does not allege fraud or bribery. It does not claim violation of any other federal law. Its argument is, in essence, that appellee has violated section 18--511, quoted above. The Postal Service responds that the mechanization plans were not finalized until two years after Hendrickson left the Postal Service. It also argues that award of the contract to Nab-Lord in no way violates section 18--511 because Nab-Lord is not 'a firm or person that designed the project' and neither Hendrickson nor Rohr-Plessey is the bidder to whom the contract is being awarded. Although this argument rests upon the letter, rather than the spirit, of the Regulation, an agency interpretation of its own regulation is certainly entitled to weight. Udall v. Tallman, 380 U.S. 1, 16--17, 85 S.Ct. 792, 13 L.Ed.2d 616 (1965).

Much more significantly, however, appellee points out that section 18--511 is by its express terms permissive. Its ban may be waived if award of a contract to the designer is approved by the Assistant Postmaster General, Real Estate and Buildings Department. The Postal Service has filed an affidavit, sworn to on February 5, 1975, by Alfred C. Maevis, Assistant Postmaster General, Real Estate and Buildings Department, which sets forth all of the facts of the alleged relationship and concludes that an award to Nab-Lord would not violate 'Postal Service policy.' More importantly, the Maevis affidavit states that even if the award were covered by section 18--511,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B.K. Instrument, Inc. v. United States
715 F.2d 713 (Second Circuit, 1983)
Union Carbide Corp. v. Train
73 F.R.D. 620 (S.D. New York, 1977)