Airco, Inc. v. Energy Research and Development Administration, and Cryogenic Technology, Inc., Intervening

528 F.2d 1294
CourtCourt of Appeals for the Seventh Circuit
DecidedDecember 29, 1975
Docket75-1855 and 75-1856
StatusPublished
Cited by43 cases

This text of 528 F.2d 1294 (Airco, Inc. v. Energy Research and Development Administration, and Cryogenic Technology, Inc., Intervening) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airco, Inc. v. Energy Research and Development Administration, and Cryogenic Technology, Inc., Intervening, 528 F.2d 1294 (7th Cir. 1975).

Opinion

PER CURIAM.

Aireo, Inc. brought this suit to challenge the award of a government contract to another bidder, Cryogenic Technology, inc. (CTi). The Energy Research and Development Administration (ERDA) (the successor to the Atomic Energy Commission) and ERDA’s administrator are named as defendants. Other defendants are the purchaser in the procurement in issue here, Fermi National Accelerator Laboratory (Fermilab), and Universities Research Association, a consortium of universities which manages Fermilab. CTi, the successful bidder, intervened as a defendant after suit was filed.

Most of Fermilab’s operating funds are provided by ERDA, which also provides funds to the Lawrence Laboratory in Berkeley, California (Lawrence). Both Fermilab and Lawrence are re *1296 quired by contract with ERDA to obtain that agency’s approval of all their contracts for equipment and services, and they must follow federal procurement regulations in entering into those contracts.

In the negotiated procurement at issue here, Fermilab acted as agent for itself and Lawrence. After an initial round of negotiations, Fermilab selected Aireo as the low bidder. ERDA refused to approve the selection because of allegedly improper discussions between Aireo and Fermilab after Aireo had made its best and final offer. ERDA ordered a new round of negotiations, which ended with the award to CTi.

The District Court granted Airco’s motion for preliminary injunction, under which the defendants are

“enjoined from aiding or supporting performance of and from making any payments under the aggregate contract awarded to CTi in June of 1975, and defendants are further enjoined to suspend all work under the aggregate contract and to stop incurring any costs or making any commitments thereunder.”

The defendants appeal the issuance of the preliminary injunction. We reverse.

There are some disputes about the facts, and about whether the District Court properly resolved these disputes in Airco’s favor on the basis of conflicting affidavits. Cf. General Electric Co. v. American Wholesale Co., 235 F.2d 606, 608—609 (7th Cir. 1956). We find it unnecessary to consider these questions, because we hold that even under Airco’s version of the facts, ERDA’s actions had a reasonable basis and are therefore entitled to judicial deference. Rossetti Contracting Co. v. Brennan, 508 F.2d 1039, 1042-1043 (7th Cir. 1975); M. Steinthal & Co. v. Seamans, 147 U.S.App.D.C. 221, 455 F.2d 1284, 1301-1302 (1971). Consequently, we find no likelihood that Aireo can prevail on the merits. Since the question is one of law, we are not bound by the District Court’s contrary conclusion. Milsen Co. v. Southland Corp., 454 F.2d 363, 369 & n. 9 (7th Cir. 1971); 11 Wright and Miller, Federal Practice and Procedure, § 2962 at 636-637 (1973). 1

The District Court concluded that Air-co’s conduct during the first round of negotiations was proper, that it was therefore improper for ERDA to require a new round of negotiations, and that it was also improper for ERDA to approve the award to CTi following the second round. We will consider these questions in turn, viewing disputed issues of fact in the light most favorable to Aireo.

Before turning to the merits, we must address the issue of standing. In Rossetti Contracting Co. v. Brennan, supra, 508 F.2d at 1042, the court considered the merits of a disappointed bidder’s challenge to a procurement decision after commenting that “the Administrative Procedure Act, 5 U.S.C. § 702, provides a basis for such consideration.” Although the standing issue was not briefed or argued in Rossetti, this remark cannot be dismissed as dictum because the court had a continuing duty to determine whether a statutory basis for its jurisdiction existed. Recent cases in the other circuits have agreed that disappointed bidders have standing to obtain judicial review. See Armstrong & Armstrong, Inc. v. United States, 514 F.2d 402, 403 (9th Cir. 1975), and cases cited therein. We see no need to reconsider the standing issue at this time.

*1297 The First Round of Negotiations

On July 24, 1974, Fermilab issued a request for proposals (or “RFP”) for two helium refrigerators for use in research on superconductivity. It was hoped that this research would lead to the development of energy-saving techniques. The RFP was later modified to call for one refrigerator and one cold box (i. e., a refrigerator minus the compressor unit).

Proposals were submitted by Aireo, CTi, and Lotepro Corporation. All three proposals were technically acceptable but priced too high. At Fermilab’s request, all three offerors agreed to enter into negotiations regarding price. Following these negotiations, “best and final” proposals were submitted to Fermilab, and on November 21 Fermilab selected Aireo as the low bidder. On November 27 and December 6, formal letters of intent were issued to Aireo. Under the terms of the RFP, however, no contract could be formed until ERDA’s approval was obtained.

On December 6, 1974, CTi filed a notice of protest with the Comptroller General. ERDA investigated CTi’s allegations and found them to be baseless. In the course of the investigation, however, ERDA discovered that discussions between Fermilab and Aireo had taken place after Airco’s selection. According to a TWX from ERDA’s area manager to its Director of Procurement, these discussions did not “substantially prejudice” the other offerors, but did create a possible “appearance of impropriety.” .The area manager informed Fermilab that ERDA had decided not to approve any award under the RFP because of “certain irregularities in the procurement process, consisting primarily of failure to adhere to the procedures set forth in [41 C.F.R.] 1-3.804 and [41 C.F.R.] 1-3.805.” These regulations are discussed below.

There is a dispute as to what post-selection discussions took place. Much of the evidence relating to this dispute was destroyed by a Fermilab employee whose husband worked for Aireo. Aireo now concedes, however, that post-selection discussions took place about warranty and F.O.B. terms. 2 Aireo wanted the F.O.B. point changed from Fermilab, as the RFP required, to Airco’s California facility. This would shift the risk of loss in transit to Fermilab. Aireo also wanted a warranty provision that would disclaim all implied warranties and severely restrict its liability for components manufactured by others. This change would be highly material, especially since it appears that Aireo planned to purchase the cold boxes themselves from a foreign supplier.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Club Italia Soccer v. Shelby
Sixth Circuit, 2006
American Cargo Transport, Inc. v. Natsios
429 F. Supp. 2d 139 (District of Columbia, 2006)
Aerolease Long Beach v. United States
31 Fed. Cl. 342 (Federal Claims, 1994)
District of Columbia v. Group Insurance Administration
633 A.2d 2 (District of Columbia Court of Appeals, 1993)
Chemung County v. Dole
804 F.2d 216 (Second Circuit, 1986)
M.W. Kellogg Co./Siciliana Appalti Costruzioni, S.p.A. v. United States
33 Cont. Cas. Fed. 74,380 (Court of Claims, 1986)
Motor Coach Industries, Inc. v. Dole
725 F.2d 958 (Fourth Circuit, 1984)
James Luterbach Const. Co., Inc. v. Adamkus
577 F. Supp. 869 (E.D. Wisconsin, 1984)
Ardmare Construction Co. v. Freedman
467 A.2d 674 (Supreme Court of Connecticut, 1983)
B.K. Instrument, Inc. v. United States
715 F.2d 713 (Second Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
528 F.2d 1294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/airco-inc-v-energy-research-and-development-administration-and-ca7-1975.