This text of 159 B.R. 76 (Southern Marine & Industrial Services, Inc. v. AK Engineering, Inc. (In Re AK Services, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Marine & Industrial Services, Inc. v. AK Engineering, Inc. (In Re AK Services, Inc.), 159 B.R. 76, 1993 Bankr. LEXIS 1407, 1993 WL 385529 (Mass. 1993).

Opinion

MEMORANDUM

JOAN N. FEENEY, Bankruptcy Judge.

I. INTRODUCTION

The matter before the Court is the “Motion for Remand of Adversary Proceedings or Alternatively, for Abstention from Proceedings” filed by Southern Marine and Industrial Services, Inc. (“Southern Marine”), the Plaintiff in the above-captioned adversary proceeding that was removed to this Court from the Suffolk Superior Court on July 9, 1993 by AK Services, Inc. (“AK Services” or the “Debtor”), pursuant to Fed.R.Bankr.P. 9027. 1 The Debtor filed an opposition to the motion, as did other parties in interest, including 1) Joseph S.U. Bodoff, Trust Mortgagee of AK Engineering, Inc. (“AK Engineering”); 2) Shawmut Bank, N.A. (“Shawmut” or the “Bank”), Plaintiff-Intervenor in the Suffolk Superior Court action and the purported holder of a perfected security interest in virtually all the assets of AK Engineering; 3) individual Defendants, Patrick Canónica (“Canónica”), Carl Franson (“Franson”), and Patrick Hickey (“Hickey”) (collectively, the “Individual Defendants”), three of the four shareholders of AK Engineering and the shareholders of the Debtor.

II. BACKGROUND

On September 3, 1992, Southern Marine initiated a civil action in Suffolk Superior Court against “AK Engineering, Inc. a/k/a AK Services.” Southern Marine, with leave of court, amended its complaint twice, naming additional defendants. On September 9, 1992, it obtained a preliminary injunction against American Overseas Marine Corporation (“AOMC”) and General Ship Corporation (“GSC”) (collectively, the “Reach and Apply Defendants”) with respect to any monies owed to or standing in the name of “AK Services” up to the value of $145,932.00.

*79 Prior to the filing of the first amended complaint, AK Services intervened in the civil action. On January 20, 1993, as a result of its default, partial judgment was entered against AK Engineering in the amount of $145,932.00. AK Services was not denominated as an alternative name for AK Engineering in the partial judgment that entered on January 20, 1993.

Shawmut moved to intervene in the civil action. Its motion was allowed on May 13, 1993, before the filing of the second amended complaint in which Southern Marine added Canónica, Franson and Hickey as additional defendants. Shawmut also filed a verified complaint, containing four counts. Prior to Shawmut’s intervention, Southern Marine and Shawmut submitted to the Superior Court a “Stipulation and Order to Subordinate Equitable Attachment” in which they agreed that any monies owed to AK Engineering by the Reach and Apply Defendants were subject to and subordinate to the all asset security interest held by the Bank. The state court approved the stipulation on September 30, 1992.

The second amended complaint now before this Court contains eight counts. Through Count I, Southern Marine seeks damages in the amount of $145,932.00 for breach of a contract it had with AK Engineering whereby it was to completely overhaul, rebuild, and prepare for full operation two boilers of a marine vessel known as the SS Cape Avinoff. Through Counts II and VIII, Southern Marine seeks damages for violation of Massachusetts General Laws ch. 93A. In Count III, Southern Marine states a claim for quantum meruit. In Counts IV and V, Southern Marine seeks to reach and apply monies allegedly owed by AOMC and GSC. Finally, Counts VI and VII contain demands for declaratory relief. Specifically, in Count VI, Southern Marine seeks a determination that in an effort to hinder, delay and defraud creditors, AK Engineering transferred to and allowed AK Services, Fore River Shipyard & Iron Works, Inc. (“Fore River”), and AK Technical Services Mid-Atlantic, Inc. (“AK Technical”) (collectively, the “Corporate Defendants”) to use all of AK Engineering’s tangible and intangible assets; that the Corporate Defendants were formed by the sole officers and directors of AK Engineering, who are the real parties in interest; that the Corporate Defendants are the alter egos of and are controlled and exclusively directed by the officers and directors of AK Engineering; and that as a result of the transfer of assets, AK Engineering was rendered insolvent. In Count VII, Southern Marine alleges that Canónica, Franson and Hickey entered into arrangements with AK Technical and AK Services whereby they were paid money that otherwise would be due and owing AK Engineering. It seeks similar relief against the Individual Defendants. In particular, it asks for a resolution of the following issues:

(1) whether the transfer of the tangible and intangible assets from AK Engineering to AK Services, Inc. and AK Technical were fraudulent transfers; (2) whether the payments from AK Services, Inc., and AK Technical to Canónica, Franson and Hickey were fraudulent; (3) whether AK Services, Inc., and AK Technical are alter egos of Canónica, Franson and Hickey requiring that the corporate identities should be disregarded; (4) whether Canónica, Franson and Hickey are now personally liable for the legal obligations due' and owing Southern as a result of AK Engineering becoming insolvent; and (5) whether the corporate veil of AK Engineering, AK Services and/or AK Technical should be pierced and Canóni-ca, Hickey and Franson held liable for the legal obligations of AK Engineering.

Southern Marine amended complaint contains a claim for a jury trial “as to all issues so triable.”

In its complaint, Shawmut alleges that it is owed at least $238,607.67 under a Demand Note and Credit Agreement executed by AK Engineering. It also seeks declaratory relief with respect to 1) the validity of its security interest in the assets of AK Engineering whether standing in the name of the Corporate Defendants, the Reach and Apply Defendants or the Plaintiff; and *80 2) the priority of its security interest in the assets of the Corporate Defendants, if Southern Marine succeeds in proving that one or more of them received fraudulent conveyances from AK Engineering or is the alter ego of AK Engineering or is a successor corporation of AK Engineering.

III. LEGAL PRINCIPLES

A. Remand

Section 1452(b) of title 28 permits the court to which a claim or cause of action has been removed to remand such claim or cause of action “on any equitable ground.” 28 U.S.C. § 1452(b). In Seale v. Owens & O-M Management Group, Inc., 134 B.R. 181 (Bankr.E.D.La.1991), the court identified the following equitable grounds for remand:

(1) forum non conveniens; (2) a holding that, if the civil action has been bifurcated by removal, the entire action should be tried in the same court; (3) a holding that a state court is better able to respond to questions involving state law; (4) expertise of the particular court; (5) duplicative and uneconomic effort of judicial resources in two forums; (6) prejudice to the involuntarily removed parties; (7) comity considerations; and (8) a lessened possibility of an inconsistent result.

Id. at 184, citing, Browning v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
159 B.R. 76, 1993 Bankr. LEXIS 1407, 1993 WL 385529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-marine-industrial-services-inc-v-ak-engineering-inc-in-re-mab-1993.