South-Way Construction Co. v. Adams City Service

458 P.2d 250, 169 Colo. 513, 1969 Colo. LEXIS 597
CourtSupreme Court of Colorado
DecidedSeptember 2, 1969
Docket22472
StatusPublished
Cited by18 cases

This text of 458 P.2d 250 (South-Way Construction Co. v. Adams City Service) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South-Way Construction Co. v. Adams City Service, 458 P.2d 250, 169 Colo. 513, 1969 Colo. LEXIS 597 (Colo. 1969).

Opinion

Mr. Justice Pringle

delivered the opinion of the Court.

This action was brought under C.R.S. 1963, 86-7-7, by a materialman, Adams City Service, to recover the cost of certain materials which it had supplied to Acme Sand and Gravel Co. for work on a public property. The Metropolitan Denver Sewage Disposal District had let the construction contract to Mead & Mount Construction Company, Inc., which subcontracted part of the work to South-Way Construction Co., Inc. In turn, South-Way Construction subcontracted part of its work to Acme Sand. Thus Adams City Service is the materialman to a sub-subcontractor. Summary judgment was entered against Acme Sand. After a trial, judgment was also entered against Mead & Mount and South-Way for nearly $10,000. The surety on the bond required by C.R.S. 1963, 86-7-4, et seq., has never been a party to this action. The City of Denver, acting by and through the Metropolitan *516 Denver Sewage Disposal District, was made a party to the suit in the trial court and stipulated that it would pay out of funds withheld from the prime contractor in accordance with any final judgment rendered here.

Mead & Mount and South-Way contend here (a) that C.R.S. 1963, 86-7-7, whose terms extend protection to those who supply materials “used or consumed by such contractor, or his subcontractor,” does not authorize an action brought by one who supplies materials to a sub-subcontractor; (b) that the remedy provided by the statute must be employed against the surety on the bond which the contractor is required to execute, and not against the contractor; and (c) that the judgment is not supported by the evidence.

I.

Under the terms of our statute, any person who has furnished labor or materials “used or consumed by such contractor, or his subcontractor, in or about the performance of the work contracted to be done,” may file with the public agency awarding the contract a verified statement of the amount unpaid. C.R.S. 1963, 86-7-7 (1). Upon the filing of this claim, the public agency must withhold from all payments to the contractor sufficient funds to insure the payment of the claim. C.R.S. 1963, 86-7-7(2). The contractor and subcontractor contend here, however, that the statute does not include within its scope of protection a person who has supplied materials to a sub-subcontractor. We do not agree.

To construe the term “subcontractor” so as to exclude a “sub-subcontractor” from the protection granted by the contractor’s bond statute would require us to ignore the purpose of the statute. Since the benefits of our mechanic’s lien act do not apply to projects constructed by governmental agencies, a remedy similar to our mechanic’s lien statute was provided by the legislature for the protection of those furnishing supplies or material for such projects. Continental Casualty Co. v. Rio Grande Fuel Co., 108 Colo. 472, 119 P.2d 618. See *517 also Western Lumber & Pole Co. v. City of Golden, 23 Colo. App. 461, 130 P. 1027. The statute stands in lieu of the mechanic’s lien statute, and is designed to protect those who supply labor and materials for public works. Flaugh v. Empire Clay Products, Inc., 157 Colo. 409, 402 P.2d 932.

Plaintiff in error contends that Stryker v. Toliver & Kinney Mercantile Co., 77 Colo. 347, 236 P. 993, requires us to adopt the construction which the United States courts have placed upon the Miller Act, 40 U.S.C. § 270a, et seq., which is the federal contractor’s bond statute. We do not agree. In Stryker, supra, our Court gave “great force” to earlier federal and state decisions construing an earlier federal contractor’s bond statute, pointing out that there was no distinction between the language of the federal statute and that of the state statute as to the particular point in issue. Stryker, supra, it is to be noted, adopted a more liberal interpretation than was afforded by the mechanic’s lien statute with respect to what items of supply were protected by the statute.

After Stryker was decided, however, the protection available under the federal contractor’s bond law was substantially changed by the enactment of the Miller Act, 40 U.S.C. § 270a, et seq., (1935). See MacEvoy Co. v. United States ex rel. Calvin Tompkins Co., 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163. The Miller Act contained a proviso (without counterpart in the former federal statute), which made it clear that the right to bring an action on the bond was limited to those materialmen who had a direct contractual relationship with a subcontractor. A House of Representative Report stated, moreover, that “[a] sub-subcontractor may avail himself of the protection given in the bond in giving written notice to the contractor, but this is as far as the bill goes. It is not felt that more remote relationships ought to come within the purview of the bond.” It was upon this “expressed will of the framers of the Act” that the United States Supreme Court held that the Miller Act *518 was extremely limited in its application to materialmen. MacEvoy Co. v. United States ex rel. Calvin Tompkins Co., 322 U.S. 102, 108. The expressed will of Congress in 1935, dealing with a revision of its statutes, certainly can have no effect on the interpretation of our statute which has been in existence in its present form since at least 1923. We decline to depart from the rule of liberal construction which we applied in Stryker, supra, and which we have enunciated several times since then. We hold that a materialman to a sub-subcontractor is within the scope of protection granted by our statutes, just as he would be protected under the mechanic’s lien statute.

II.

Plaintiffs in error contend that the only remedy provided under C.R.S. 1963, 86-7-7 is an action against the surety on the bond required in Section 86-7-6. We do not agree. In our view, C.R.S. 1963, 86-7-7, provides alternate methods of relief. The statute specifically requires the governmental agency to withhold sufficient funds to insure payment of claims by materialmen provided proper and timely notice is given. An action must be begun to enforce the unpaid claims within ninety days of the time of final settlement and lis pendens filed within that ninety-day period with the contracting body. If such procedure is followed, the contracting body must retain such funds to insure the payment of judgments tohich may result from the suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brannan Sand & Gravel Co. v. Federal Deposit Insurance Corp.
928 P.2d 1337 (Colorado Court of Appeals, 1996)
Western Metal Lath v. Acoustical & Construction Supply, Inc.
851 P.2d 875 (Supreme Court of Colorado, 1993)
SaBell's, Inc. v. City of Golden
832 P.2d 974 (Colorado Court of Appeals, 1992)
Western Coating, Inc. v. Gibbons & Reed Co.
788 P.2d 503 (Utah Supreme Court, 1990)
Elliott Electric Supply Co. v. Adolfson & Peterson, Inc.
765 P.2d 1079 (Colorado Court of Appeals, 1988)
E.B. Jones Construction Co. v. City & County of Denver
717 P.2d 1009 (Colorado Court of Appeals, 1986)
CPS Distributors, Inc. v. Federal Insurance Co.
685 P.2d 783 (Colorado Court of Appeals, 1984)
Heinrichsdorff v. Raat
655 P.2d 860 (Colorado Court of Appeals, 1982)
Weld Colorado Bank v. E & E Construction, Inc.
653 P.2d 758 (Colorado Court of Appeals, 1982)
Rocky Mountain Ass'n of Credit Management v. Marshall
615 P.2d 68 (Colorado Court of Appeals, 1980)
ROCKY MOUNTAIN ASS'N v. Marshall
615 P.2d 68 (Colorado Court of Appeals, 1980)
Peters v. Hartford Accident & Indemnity Co.
389 N.E.2d 63 (Massachusetts Supreme Judicial Court, 1979)
Lovell Clay Products Co. v. STATEWIDE SUPPLY
580 P.2d 1278 (Colorado Court of Appeals, 1978)
Kobayashi v. Meehleis Steel Co.
472 P.2d 724 (Colorado Court of Appeals, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
458 P.2d 250, 169 Colo. 513, 1969 Colo. LEXIS 597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-way-construction-co-v-adams-city-service-colo-1969.