Western Coating, Inc. v. Gibbons & Reed Co.

788 P.2d 503, 128 Utah Adv. Rep. 3, 1990 Utah LEXIS 89, 1990 WL 16563
CourtUtah Supreme Court
DecidedFebruary 15, 1990
Docket880289
StatusPublished
Cited by1 cases

This text of 788 P.2d 503 (Western Coating, Inc. v. Gibbons & Reed Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Coating, Inc. v. Gibbons & Reed Co., 788 P.2d 503, 128 Utah Adv. Rep. 3, 1990 Utah LEXIS 89, 1990 WL 16563 (Utah 1990).

Opinion

HOWE, Associate Chief Justice:

Plaintiff Western Coating, Inc., a third-tier supplier in a public contract, appeals from a summary judgment in favor of the general contractor, Gibbons and Reed Company, in this suit to determine the coverage of a payment bond.

The Utah Department of Transportation contracted with defendant Gibbons and Reed Company to construct a public road. Gibbons and Reed obtained a payment bond from its surety, American Insurance Company, in accordance with Utah Code Ann. § 63-56-38 (Supp.1985). Gibbons and Reed subcontracted with Pacheco & Martinez for the installation of black and epoxy reinforcing steel on the project. Pacheco & Martinez then entered into a contract with Continental-Hagen to supply the black and epoxy reinforcing steel. Continental-Ha-gen in turn contracted with plaintiff Western Coating for epoxy coated rebar to be used in the project.

Gibbons and Reed paid Pacheco & Martinez, but Western Coating was not paid by Continental-Hagen. Western Coating made a demand upon Gibbons and Reed and its surety under the payment bond for the $30,904.80 balance due on materials. The district court granted a motion for summary judgment by Gibbons and Reed. In its memorandum decision, the court relied on federal interpretation of the Miller Act, 40 U.S.C. § 270b (1935), in holding that Western Coating was too remote in the contract chain to recover under the Utah Procurement Code’s payment bond provision, section 63-56-38. The sole issue on appeal is whether third-tier suppliers are covered by the Utah Procurement Code.

Western Coating contends that the Utah Procurement Code and Utah’s mechanic’s lien statutes, Utah Code Ann. §§ 38-1-1 to -26 (1988), are similar in purpose; therefore, the coverage of the mechanic’s lien, which extends to third-tier suppliers in private contracts should be imputed to the Utah Procurement Code. Western Coating argues that this would further public policy by extending to public contract suppliers the same security they enjoy in private contracts.

This Court has recognized that public bonding and mechanic’s lien statutes are “closely related in purpose.” King Bros., Inc. v. Utah Dry Kiln Co., 13 Utah 2d 339, 341, 374 P.2d 254, 255 (1962). We have *504 reasoned that since mechanic’s lien protection is not available in public contracts, “performance bonds are required on public projects to provide substitute protection for laborers and material providers.” CECO v. Concrete Specialists, Inc., 772 P.2d 967, 970 (Utah 1989).

However similar in purpose, the language of the pertinent mechanic’s lien statute and that of the Utah Procurement Code evidence that the two statutes were not intended to be co-extensive. Section 38-1-3 (1988) provides that those entitled to a mechanic’s lien are “[cjontractors, subcontractors, and all persons performing any services or furnishing or renting any materials or equipment used in the construction, alteration, or improvement of any building or structure_” (Emphasis added.)

In contrast, the pertinent section of the Utah Procurement Code provides:

(1) When a construction contract is awarded, the following bonds or security shall be delivered to the state and shall become binding on the parties upon the execution of the contract:
[[Image here]]
(b) a payment bond satisfactory to the state, in an amount equal to 100% of the price specified in the contract, executed by a surety company authorized to do business in this state or any other form satisfactory to the state, for the protection of all persons supplying labor and material to the contractor or its subcontractors for the performance of the work provided for in the contract.
[[Image here]]
(3) Any person who has furnished labor or material to the contractor or subcontractor for the work provided in the contract, in respect of which a payment bond is furnished under this section, who has not been paid in full within 90 days from the date on which the last of the •labor was performed or material was supplied by the person for whom the claim is made, may sue on the payment bond...[ 1 ]

Utah Code Ann. § 63-56-38 (Supp.1985) (emphasis added).

We recently decided whether the rental of equipment, expressly mentioned in the mechanic’s lien statute but not in section 63-56-38, was covered by the latter section in view of its common purpose with the mechanic’s lien. In Johnson v. Gallegos Construction Company, 785 P.2d 1109, 1111-12 (1990), we noted that the absence of language covering rental of equipment manifested an intent by the legislature not to include such rental. We were unwilling to extend mechanic’s lien coverage to the procurement code on the basis of a “common purpose” theory.

The mechanic’s lien covers all persons performing services or furnishing material used in the construction of a building or structure. Section 63-56-38 coverage is narrower: any person who has supplied labor or material to the contractor or its subcontractors for the work provided for in the contract. Since the coverage is stated differently, we must look to the legislative history of the Utah Procurement Code to ascertain the scope of its coverage.

Congress passed the Miller Act in 1935 to provide protection in public contracts for

[ejvery person who has furnished labor or material in the prosecution of the work provided for in such contract[s].... Provided, however, [t]hat any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond....

40 U.S.C. § 270b (1982) (emphasis in original).

In 1944, the United States Supreme Court held that subcontractors in a relationship more remote than sub-subcontractor were not covered under the Miller Act. Clifford F. MacEvoy Co. v. United States, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163 (1944). While the act provided that coverage extended to “every person who has *505

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
788 P.2d 503, 128 Utah Adv. Rep. 3, 1990 Utah LEXIS 89, 1990 WL 16563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-coating-inc-v-gibbons-reed-co-utah-1990.