SaBell's, Inc. v. City of Golden

832 P.2d 974, 1991 WL 278365
CourtColorado Court of Appeals
DecidedJuly 20, 1992
Docket90CA0861
StatusPublished
Cited by15 cases

This text of 832 P.2d 974 (SaBell's, Inc. v. City of Golden) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SaBell's, Inc. v. City of Golden, 832 P.2d 974, 1991 WL 278365 (Colo. Ct. App. 1992).

Opinion

Opinion by

Judge RULAND.

Defendant, Indiana Lumbermens Mutual Insurance Co. (Indiana), appeals the judgments entered against it and in favor of plaintiffs, SaBell’s, Inc., and Sports Facilities Contractors, Ltd., for contract and public bond claims arising out of a public works project and from the denial of its cross-claim against the City of Golden. Sports Facilities cross-appeals the amount of interest awarded on its claim. We affirm in part and reverse in part.

The City entered into a construction contract with Jorn Electric Corp. to make improvements to the Ulysses Park athletic field located in Golden. The improvements contracted for included landscaping and lighting. Jorn, in turn, subcontracted with SaBell’s to perform the landscaping and with Sports Facilities to install the lighting.

Before commencing work, and pursuant to § 38-26-101, C.R.S., (1982 Repl.Vol. 16A), Jorn was required to purchase a performance bond and a labor and material payment bond. Jorn purchased these bonds from Indiana. Indiana’s bond agent, James Misken, however, prepared a rider to the bonds and an escrow agreement.

This rider and the escrow agreement required the City to make payments jointly to Jorn and T.F. Bauerle, an escrow agent. Under this agreement, Bauerle was obligated to ensure that these funds were paid to the subcontractors as a form of security for Indiana.

Misken delivered the bonds and the escrow agreement to the director of the City’s parks and recreation department. The director supervised the project.

The director initially told Misken that she did not have the authority to enter into the escrow agreement but that she would contact the City’s attorney to discuss that issue. She subsequently told Misken that she had the authority to enter into the agreement and, therefore, signed it on behalf of the City.

The City failed to disburse the funds jointly to Jorn and Bauerle. Instead, the City paid only Jorn. Jorn failed to pay SaBell’s and Sports Facilities for all of their work, thereby defaulting on the subcontracts. Jorn also defaulted on its general contract, and consequently, the City completed the project.

SaBell’s and Sports Facilities brought suit against Indiana for failure to pay the remaining balance on the subcontracts and for damages pursuant to § 38-26-101, et seq., C.R.S. (1982 Repl.Vol. 16A). Sports Facilities also alleged a tort claim against Indiana. Alternatively, the subcontractors claimed damages against the City.

Indiana denied liability, claiming that the bonds were void because the City failed to abide by the escrow agreement. Indiana also asserted defenses based upon the statute of limitations and an alleged failure to mitigate damages.

In other pleadings, Indiana asserted a cross-claim against the City for indemnification. The City denied liability and filed a claim against Indiana for indemnification.

Following a bench trial, the trial court ruled that both SaBell’s and Sports Facilities had a right of recovery against Indiana for the amount due under their subcontracts. Also, the trial court determined that both subcontractors were entitled to eight per cent interest on the entire amount of the judgment.

With reference to the indemnification claims, the court ruled that Indiana had no right of indemnification against the City. It concluded that the bond rider was unenforceable as against public policy, that the director had no authority to sign the es *977 crow agreement, and that Indiana knew or should have known this fact. Finally, the trial court ruled that both SaBell’s and Sports Facilities were entitled to reasonable attorney fees for prosecuting their claims against Indiana because it concluded that Indiana’s defenses were frivolous and groundless.

Indiana asserts that the trial court erred in various respects in resolving the contested issues at trial. It is unnecessary to resolve Indiana’s contentions relative to the bond rider. Instead, we need only address its contentions relative to the trial court’s rulings on damages, interest, and attorney fees.

I

The trial court found that the evidence failed to establish any damage to Indiana resulting from the City’s noncompliance with the rider and the escrow agreement. Relying upon cases such as Garcia v. Chase Manhattan Bank, 735 F.2d 645 (2d Cir.1984), Indiana contends that its damage claim was established as a matter of law. It reasons that the claim was established simply by proving that the City made payments to someone other than the specific individuals designated in the escrow agreement. On this basis, Indiana argues that the City must indemnify it by paying Indiana the same amount the City paid Jorn. We reject this contention.

The Garcia rule applies when the claimant is the one entitled to the funds and the stakeholder improperly transfers the funds to a third party. Here, however, the City paid the funds to a proper claimant, and there is no showing that the funds were not applied in conformance with the contract between the City and Jorn. Thus, the record supports the trial court’s finding that Indiana’s damages were uncertain and speculative.

Under such circumstances, damages may not be awarded because the fact of damages is uncertain. See Peterson v. Colorado Potato Flake & Manufacturing Co., 164 Colo. 304, 435 P.2d 237 (1967); Hyman & Co. v. Velsicol Corp., 123 Colo. 563, 233 P.2d 977 (1951).

II

The trial court concluded that pursuant to § 38-26-106, C.R.S. (1982 Repl.Vol. 16A), SaBell’s and Sports Facilities were entitled to eight per cent interest from Indiana on the amount not paid to them under the subcontracts. The amount of interest due was calculated from the date notice of their claims was given.

Indiana initially contends that the interest award was in error because Sports Facilities failed to request the interest rate allowable under § 38-26-106(2), C.R.S. (1991 Cum.Supp.) in its complaint. Instead, Sports Facilities claimed interest at the rate of 18 per cent based upon its contract with Jorn. Consequently, Indiana asserts that Sports Facilities waived its entitlement to the statutory interest rate. We disagree.

Pursuant to § 38-26-106, C.R.S. (1982 Repl.Yol. 16A): “[I]f the contractor or his subcontractor fails to duly pay for any labor, materials ... the surety will pay the same in an amount not exceeding the sum specified in the bond together with interest at the rate of eight percent per annum.” While Sports Facilities requested the contract rate in its complaint, its memorandum brief in support of a motion for summary judgment did request the statutory interest rate under § 38-26-106(2), C.R.S. (1991 Cum.Supp.). Presentation of the issue in this manner, in effect, constituted an amendment to the complaint. See Discovery Land & Development Co. v. Colorado-Aspen Development Corp., 40 Coio.App. 292, 577 P.2d 1101 (1977).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Wunder
2016 COA 46 (Colorado Court of Appeals, 2016)
In re the Marriage of Tognoni
313 P.3d 655 (Colorado Court of Appeals, 2011)
Fowler Irrevocable Trust 1992-1 v. City of Boulder
992 P.2d 1188 (Colorado Court of Appeals, 2000)
Vaughn Excavating & Construction, Inc. v. P.S. Cook Co.
981 P.2d 485 (Wyoming Supreme Court, 1999)
M Life Insurance Co. v. Sapers & Wallace Insurance Agency, Inc.
962 P.2d 335 (Colorado Court of Appeals, 1998)
State v. Golden's Concrete Co.
962 P.2d 919 (Supreme Court of Colorado, 1998)
Bernhardt v. Hemphill
878 P.2d 107 (Colorado Court of Appeals, 1994)
Wood Bros. Homes, Inc. v. Howard
862 P.2d 925 (Supreme Court of Colorado, 1993)
McCormick v. Bradley
870 P.2d 599 (Colorado Court of Appeals, 1993)
Howard v. Wood Bros. Homes, Inc.
835 P.2d 556 (Colorado Court of Appeals, 1992)
Thrifty Rent-A-Car System, Inc. v. City & County of Denver
833 P.2d 852 (Colorado Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
832 P.2d 974, 1991 WL 278365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sabells-inc-v-city-of-golden-coloctapp-1992.