Vaughn Excavating & Construction, Inc. v. P.S. Cook Co.

981 P.2d 485, 1999 Wyo. LEXIS 89, 1999 WL 330226
CourtWyoming Supreme Court
DecidedMay 26, 1999
DocketNo. 98-114
StatusPublished
Cited by1 cases

This text of 981 P.2d 485 (Vaughn Excavating & Construction, Inc. v. P.S. Cook Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vaughn Excavating & Construction, Inc. v. P.S. Cook Co., 981 P.2d 485, 1999 Wyo. LEXIS 89, 1999 WL 330226 (Wyo. 1999).

Opinion

TAYLOR, Justice, Retired.

At issue in this case is whether the prime contractor and its surety are liable under a public works bond for interest, penalties and attorney’s fees owed by the subcontractor to his supplier. The district court granted summary judgment to the prime contractor and the surety, finding that the statutory obligations on the bond did not include benefits on a contract to which the prime contractor was not a party. We affirm.

I. ISSUES

Appellant, Vaughn Excavating and Construction, Inc. (Vaughn), the supplier, presents a single issue for review:

Whether a bond claimant is entitled to recover, under a public works bond, late [486]*486payment penalties, interest and costs of collection, in addition to the agreed price for the materials supplied

Appellees, P.S. Cook Company, the prime contractor, and American Casualty Company, its surety submit three issues for review:

1. Does the record show the existence of any contract between the supplier and the subcontractor to pay attorneys’ fees, credit charges or interest?
2. If so, can the supplier of a subcontractor enforce credit and collection charges in its contract with the subcontractor against the surety of the general contractor, pursuant to the public works bonding statute, even though the general contractor a) did not agree to be responsible for those charges; b) did not cause or contribute to the subcontractor’s default which led to the imposition of those charges; and c) promptly made arrangements to pay the supplier its quoted price for the materials used in the project?
3. When figuring interest under the public works bonding statute, did the trial court properly apply the statutory rate of 7% per annum rather than the 2% per month rate which the supplier claims?

II.FACTS

The prime contractor, P.S. Cook, hired Richland Construction as a subcontractor for work on two public works projects. Richland Construction defaulted on payment to its supplier, Vaughn. Vaughn then asserted a claim against P.S. Cook’s payment bond for $40,370.18. The claim included a two percent per month interest rate on past due accounts and reasonable attorney’s fees pursuant to a credit application completed by Richland Construction’s predecessor corporation. A ten percent late payment penalty was also included, pursuant to the quotes given by Vaughn to Richland Construction for the project.

P.S. Cook did not deny that it owed the costs of the materials supplied by Vaughn nor did it maintain that Vaughn could not collect the statutory prejudgment interest on its liquidated claims. However, P.S. Cook denied that its obligations under the bond included the interest, the late penalties or the attorney’s fees demanded by Vaughn. When the parties could not agree as to the amounts owed, P.S. Cook filed a declaratory judgment action for resolution of the dispute. Vaughn countered with a third-party complaint against P.S. Cook’s surety, American Casualty Company.

After a hearing on the parties’ cross-motions for summary judgment, the district court determined that appellees’ liability under Wyo. Stat. § 16-6-112 (1997), the public works bond statute, is limited to payment for goods used in the contract and extraordinary costs incurred for supplying labor and materials. Because Vaughn’s claim sought only the benefits accruing from its contract with Richland Construction, the district court granted summary judgment in favor of ap-pellees. This timely appeal followed.

III.STANDARD OF REVIEW

Summary judgment is appropriate when no genuine issue of material fact is present and the prevailing party is entitled to judgment as a matter of law. Murphy v. Housel & Housel, 955 P.2d 880, 883 (Wyo.1998); Hermreck v. United, Parcel Service, Inc., 938 P.2d 863, 866 (Wyo.1997); Woodard v. Cook Ford Sales, Inc., 927 P.2d 1168, 1169 (Wyo.1996). See also W.R.C.P. 56(c). The record must be examined from the view most favorable to the party opposing the motion, and that party must be given the benefit of all favorable inferences which may be fairly drawn from the record. Nowotny v. L & B Contract Industries, Inc., 933 P.2d 452, 455 (Wyo.1997) (quoting Thomas by Thomas v. South Cheyenne Water and Sewer Dist., 702 P.2d 1303, 1304 (Wyo.1985)). We make an independent examination of the record for genuine issues of material fact and review a summary judgment without according deference to the decision of the district court on any issues of law. Murphy, 955 P.2d at 883.

IV.DISCUSSION

Vaughn’s position is relatively straightforward. Since Richland Construction contracted to pay certain interest, penalties, and costs on materials supplied for a [487]*487public works project, the public works bond should cover those amounts.

[A] surety on an official bond undertakes no liability for anything which is not within the letter of the surety * ■* *; the surety has consented to be bound only within the express terms of the surety contract. * * * However, it is equally true that where a surety bond is given pursuant to the requirements of a particular statute, the statutory provisions are incorporated into the bond * * *.

Washington Intern. Ins. Co. v. Superior Count (G.K. Backlund, Inc.), 62 Cal.App.4th 981, 73 Cal.Rptr.2d 282, 285 (1998). There is no dispute that the terms of the general contract for the project and the bond included liability for payment to Vaughn for its materials and statutory interest on that amount. The parties also agree that the express terms of the general contract and the bond do not include the interest rate, penalties, and attorney’s fees demanded by Vaughn. Therefore, P.S. Cook and its surety have no obligation to pay interest and penalties unless required by statute. SaBell’s, Inc. v. City of Golden, 832 P.2d 974, 979 (Colo.App.1991).

Wyo. Stat. § 16-6-112 provides, in relevant part:

(a) Except as provided under W.S. 9-2-1016(b)(xviii), any contract entered into with the state, any county, city, town, school district or other political subdivision of the state for the erection, construction, alteration, repair or addition to any public building or other public structure or for any public work or improvement and the contract price exceeds seven thousand five hundred dollars ($7,500.00), shall require any contractor before beginning work under the contract to furnish the state or any political subdivision, as appropriate, a bond ⅜ ⅜ ⅜. rpjjg ]30n(j * * ⅜ sbau be;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Family Mutual Insurance Co. v. Allen
102 P.3d 333 (Supreme Court of Colorado, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
981 P.2d 485, 1999 Wyo. LEXIS 89, 1999 WL 330226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vaughn-excavating-construction-inc-v-ps-cook-co-wyo-1999.