D & L Building, Inc. v. State Ex Rel. Maltby Tank & Barge, Inc.

747 P.2d 517, 1987 Wyo. LEXIS 564, 1987 WL 25336
CourtWyoming Supreme Court
DecidedDecember 22, 1987
Docket87-149
StatusPublished
Cited by5 cases

This text of 747 P.2d 517 (D & L Building, Inc. v. State Ex Rel. Maltby Tank & Barge, Inc.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & L Building, Inc. v. State Ex Rel. Maltby Tank & Barge, Inc., 747 P.2d 517, 1987 Wyo. LEXIS 564, 1987 WL 25336 (Wyo. 1987).

Opinion

BROWN, Chief Justice.

This is an appeal of a district court order granting summary judgment in favor of appellee, Maltby Tank & Barge, Inc. (Malt-by) to recover on a contractor’s bond for a public construction project. Appellants, D & L Building, Inc. (D & L) and The Travelers Indemnity Company (Travelers) urge the following issues:

“A. Is a second tier materialman within the coverage of a statutory payment bond required for public works projects in Wyoming?
“B. Does a second tier materialman have an action against a prime contractor *518 for the price of equipment sold to a mate-rialman in privity with the prime for use on a public works project in Wyoming?
“C. A second tier materialman has no claim against a prime contractor with whom there is no privity of contract under Sections 16-6-112 through 16-6-117 of the Wyoming Statutes 1977 and their amendments.”

D & L was the general contractor for the construction of a wastewater treatment facility for the City of Riverton, Wyoming. When D & L became the general contractor it obtained a contractor’s bond for the project pursuant to § 16-6-112, W.S.1977 (October 1982 Replacement). Travelers was surety on that bond.

To facilitate the construction, D & L subcontracted with Welles Products Corporation (Welles) for clarifier equipment necessary to completion of the facility. Welles then ordered the equipment from Maltby, and Maltby manufactured the clarifier equipment and shipped it directly to the construction site. Delivery occurred on September 25, 1985. D & L began installing the clarifier equipment on October 16, 1985, and completed installation on August 1, 1986. D & L submitted a request to the City of Riverton for payment on the clarifier equipment in September, 1986, and the project engineer recommended payment in October, 1986. D & L accepted final project payment in late October, 1986.

Maltby billed Welles on October 7, 1985, but did not receive payment. After demanding payment, Maltby filed a complaint in the district court on July 9,1986, naming D & L, Welles and Travelers as defendants. Maltby sought judgment against the defendants in the amount of $30,734, plus interest and costs on the unpaid invoices for the clarifier equipment. D & L and Travelers answered, and D & L cross-claimed against Welles. After an initial wave of discovery, Maltby moved for summary judgment. On April 14, 1987, a hearing was conducted on the motion, and the trial court granted Maltby summary judgment. Following oral motion the trial court dismissed Maltby’s claims against Welles without prejudice. By then Welles had filed for protection under the United States Bankruptcy Code. This appeal is from the summary judgment order.

The three issues raised on this appeal really embody three alternative legal theories in support of the same argument. Appellants urge this court to construe § 16-6-112 narrowly so that the protection of a contractor’s bond on a state public works project only benefits parties in direct contractual privity with the general contractor for the project. We decline this invitation and rely instead on the plain language of the statute.

Section 16-6-112 provides in pertinent part:

“Whenever any contract is entered into with the state, or any county, city, town, school district, high school district or any public board, department, commission or institution, or other public corporation of this state, for the erection, construction, alteration or repair of or addition to any public building, or other public structure, or for making any addition thereto, or for any public work or improvement and the contract price exceeds five thousand dollars ($5,000.00), the contractors shall be required before beginning work under the contract to execute a bond to the state, county, city, town, school district, high school district, or any public board, department, commission or institution with which the contract is made. The bond shall be conditioned for the payment of all taxes, excises, licenses, assessments, contributions, penalties and interest thereon when, and if, lawfully due the state, or any political subdivisions or instrumentalities. The board [bond] shall also be for the use and benefit of all persons who may perform any work or labor or furnish any material or goods of any kind which were totally or partially used or expended in the execution of the contract, conditioned for the performance and completion of the contract according to the terms thereof, compliance with all the requirements of law and payment as due of all just claims for work or labor performed and material furnished and taxes, excises, licenses, *519 assessments, contributions, penalties and interest accrued in the execution of the contract. * * * ” (Emphasis added) 1

When interpreting statutes we begin by looking to the words of the statute, giving them their plain and ordinary meaning in an attempt to determine legislative intent. Paravecchio v. Memorial Hospital of Laramie County, Wyo., 742 P.2d 1276, 1278 (1987). This court last addressed the plain and ordinary meaning of § 16-6-112, in Franzen v. Southern Surety Company, 35 Wyo. 15, 246 P. 30 (1926). 2 With Justice Blume writing for the court, the public contract bond statute was held to include labor and materials contributing “directly or indirectly” to completion of the project. Id. at 27, 246 P. 30. In reaching this conclusion, the court stated it was interpreting the statute “in the light of its own language.” Id. at 26, 246 P. 30.

We now hold that § 16-6-112, again interpreted in the light of its own language, plainly evidences legislative intent that the benefit of a contractor’s bond on a public works project is not limited to those in privity of contract with a subcontractor or the general contractor.

We are not persuaded by appellants’ arguments that § 16-6-112 should receive a narrower construction based on an analogy to federal statutes, or by applying definitions of terms set out in § 29-1-201, W.S. 1977 (June 1981 Replacement). Had the legislature intended to limit the class of persons who benefit under a § 16-6-112 contractor’s bond the way federal statutes do, they could have adopted the express language of the federal statutes. 3 Likewise, had the legislature intended to apply the definitions of “contractors,” “subcontractors” or “materialmen” set out in § 29-1-201 of the Wyoming lien statutes, it could have included such definitions in the contractor’s bond statutes. The bottom line, however, is that the legislature passed § 16-6-112 with express language benefiting materialmen such as Maltby.

*520

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vaughn Excavating & Construction, Inc. v. P.S. Cook Co.
981 P.2d 485 (Wyoming Supreme Court, 1999)
Fitch v. Buffalo Federal Savings & Loan Ass'n
751 P.2d 1309 (Wyoming Supreme Court, 1988)
DeLozier Bros., Inc. v. Fremont County School District No. 14
747 P.2d 515 (Wyoming Supreme Court, 1987)
DeLOZIER BROS. v. FREMONT CTY. SD 14
747 P.2d 515 (Wyoming Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
747 P.2d 517, 1987 Wyo. LEXIS 564, 1987 WL 25336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-l-building-inc-v-state-ex-rel-maltby-tank-barge-inc-wyo-1987.