Sierra Club v. United States Nuclear Regulatory Commission

825 F.2d 1356, 18 Envtl. L. Rep. (Envtl. Law Inst.) 20
CourtCourt of Appeals for the Ninth Circuit
DecidedAugust 21, 1987
DocketNo. 85-7003
StatusPublished
Cited by3 cases

This text of 825 F.2d 1356 (Sierra Club v. United States Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. United States Nuclear Regulatory Commission, 825 F.2d 1356, 18 Envtl. L. Rep. (Envtl. Law Inst.) 20 (9th Cir. 1987).

Opinion

BRUNETTI, Circuit Judge:

I

FACTS AND PROCEEDINGS BELOW

Petitioners challenge two orders of the Nuclear Regulatory Commission (NRC or Commission) relating to the operation of San Onofre Unit 1 (Unit 1 or SONGS 1), a nuclear reactor located on the California coast near Oceanside. The first of the challenged orders, dated November 21, 1984, permitted restart of Unit 1 which had been shut down since 1982 pursuant to Commission order, for upgrading. The second order, dated February 19, 1985, denied petitioners’ request for stay and a hearing on the November 1984 order.

San Onofre Unit 1, operated by inter-venor Southern California Edison (Edison), was first licensed for operation in 1967. The original seismic design basis for the plant required that safety related plant systems meet 0.5g Housner response spectra for “functional limits,” based on the Commission’s determination that the maximum earthquake that could be expected at the San Onofre site (the Safe Shutdown Earth[1358]*1358quake or SSE) would generate ground motion of 0.5g.

In 1973, when Edison sought permission to construct two additional nuclear power plants at San Onofre (Units 2 and 3), it discovered an additional fault zone lying approximately five miles from Unit 1. The Commission realized it had underestimated the seismicity of the San Onofre site, and that the maximum expected earthquake could give rise to ground motion of 0.67g. Accordingly, Units 2 and 3 were by regulation required to meet a seismic design basis of 0.67g. Unit 1, however, remained for the moment as it was.

Subsequently, in 1973, Edison undertook to reevaluate and modify as necessary the capability of Unit 1 to withstand a 0.67g earthquake. Edison’s analysis indicated that certain systems and structures had resistance capacities in excess of those required to meet 0.67g Housner Spectra; other components were modified during a plant outage in 1976-1977.

In 1977, the Commission began a Systematic Evaluation Program (SEP) to assess the design and operation of older operating nuclear power plants, as against current safety criteria, and to provide the basis for integrated and balanced plant backfitting decisions. As part of the SEP, the Commission required Edison to submit details of the seismic evaluation program for Unit 1. Submissions by Edison in 1982 revealed unexpected high stress values for certain equipment. NRC staff then became concerned whether Unit 1 met its original design basis of 0.5g. Following a meeting with Edison in May 1982, NRC staff determined that Edison needed to demonstrate that Unit 1 met its licensed design basis before the plant, then in an outage, could be permitted to restart.

Apparently the original design calculations and supporting materials for Unit 1 had been destroyed. However, Edison announced it would extend the outage until the plant had been upgraded to 0.67g, and thus demonstrate that the plant met its original design basis, and, presumably as well, assure that the plant could survive the maximum earthquake expected at the San Onofre site.

Edison completed a substantial part, but not all, of the upgrade work. At the request of Edison the NRC staff had by September 1984 decided that it would allow Unit 1 to resume operation. The staff sought advice from the Commission whether the Commission had to hold a public hearing before authorizing restart. The Commission instructed them that the August 1982 Order should be treated as a license suspension, rescission of which would not require a hearing. On November 5 and November 20, the Commission published notice of a public meeting in which it stated that it would discuss “the NRC Staffs technical basis for restart of San Onofre Nuclear Generating Station Unit 1.” 49 Fed. Reg. 44253, Nov. 5, 1984; see also 49 Fed. Reg. 45284, Nov. 20, 1984. Those hearings were not conducted, apparently because the Commission concluded that the rescission of the license suspension was not a license amendment.

On November 21, 1984, the staff issued a “Contingent Rescission of Suspension,” order allowing restart of Unit 1, provided that the remainder of the seismic reevaluation and upgrade would be completed by the end of the next refueling outage or that Edison would submit an adequate justification for an extension of time. Three days later, Unit 1 resumed operation.

On December 7, 1984, the petitioners filed with the Commission a request for (1) a hearing on the November 21 order,1 (2) a [1359]*1359stay of the November 21 order pending a hearing on the order, and (3) a request for expedited treatment — that its requests be heard no later than Wednesday, December 12, 1984.

On December 10, 1984, the Commission filed a “procedural order”2 in which it denied petitioners’ request for an immediate decision, but ordered that the briefing be expedited. The Commission directed the licensees and NRC staff to file responses to petitioners’ request on or before December 14,1984, and directed petitioners to file a reply to the response no later than December 18, 1984. The Commission did not rule on the request for a hearing or the request for a stay.3

On December 18, 1984, petitioners filed a lengthy reply to the licensee and NRC staffs opposition to the request for a hearing and a stay, and on December 20, the Commission granted the Edison’s motion to extend the time for it to reply to January 9, 1985.

On January 3, 1985, the petitioners filed a petition with this court, seeking review of the November 21, 1984 and December 10, 1984 orders.

On February 19, 1985 the NRC entered an order denying both the request for hearing and the request for a stay.

II

JURISDICTION

We must determine whether we have jurisdiction to hear this petition. National Steel and Shipbuilding Co. v. Director of Workers Compensation Programs, 626 F.2d 106, 107 (9th Cir.1980). Citizens for a Safe Environment v. Atomic Energy Commission, 489 F.2d 1018 (3rd Cir.1973).

If we have jurisdiction in this case, it exists pursuant to 28 U.S.C. § 2344. That section provides: “Any party aggrieved by the final order may, within 60 days after its entry, file a petition to review that order in the court of appeals.... ” This sixty day period is jurisdictional, and may not be expanded by the courts. Chem-Haulers, Inc. v. United States, 536 F.2d 610 (9th Cir.1976). This jurisdictional bar also applies to petitions filed before a final order has been entered. Western Union Telegraph Co. v. Federal Communications Commission, 773 F.2d 375, 378 (D.C.Cir.1985). Because petitioners have not filed a petition for review of the Commission’s February 19,1985 Order denying the request for a hearing and a stay within this sixty day period, we must dismiss the petition for lack of jurisdiction.

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
825 F.2d 1356, 18 Envtl. L. Rep. (Envtl. Law Inst.) 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-united-states-nuclear-regulatory-commission-ca9-1987.