Sierra Club v. United States Army Corps of Engineers

772 F.2d 1043, 23 ERC 1153
CourtCourt of Appeals for the Second Circuit
DecidedSeptember 11, 1985
DocketNos. 304, 315, Dockets 85-6297, 85-6299
StatusPublished
Cited by27 cases

This text of 772 F.2d 1043 (Sierra Club v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. United States Army Corps of Engineers, 772 F.2d 1043, 23 ERC 1153 (2d Cir. 1985).

Opinions

CARDAMONE, Circuit Judge:

A change in something from yesterday to today creates doubt. When the anticipated explanation is not given, doubt turns to disbelief. This case is capsulized in that solitary simile. Following review during a 30-day trial of a remanded administrative proceeding, the United States District Court for the Southern District of New York (Griesa, J.) entered a judgment in favor of plaintiffs, Sierra Club and others on August 8, 1985. That judgment declared null and void a landfill permit for the West Side Highway Project (Westway) issued by the U.S. Army Corps of Engineers (Corps) on February 25, 1985 and funding approvals for Westway granted by the Federal Highway Administration (FHWA) on March 18, 1985. The judgment also permanently enjoined defendant New York State Department of Transportation (State) from construction of Westway.

In its 132-page opinion the district court found that the Corps’ decisionmaking process had violated the National Environmental Policy Act (NEPA), the Clean Water Act and court orders previously issued in 1982. From this judgment the Corps, FHWA and the State appeal and an expedited hearing was held before us on August 29, 1985. We affirm the district court’s conclusion with respect to the inadequacy of the federal defendants’ Final Supplemental Environment Impact Statement (FSEIS), but reverse the grant by the district court of a permanent injunction and remand the matter to the federal defendants.

To put this case in proper perspective, we outline briefly its chronology, prior legal proceedings, actions taken on remand and the opinion below.

I Background

A. Early Chronology and Prior Legal Proceedings

The highway portion of Westway presently proposed contemplates a mostly underground six-lane highway extending from the Battery to 42nd Street bordering the Hudson River on the west side of Manhattan. Approval of Westway as a link in the interstate highway system made New York State eligible for 90 percent federal funding for the project. The redevelopment project envisions a 93 acre park, planted on a roof covering the highway, together with extensive residential and commercial development. The total cost of the project is estimated to be 2 billion dollars and requires that 242 acres of the Hudson be landfilled to complete it.

The selection of the Westway project resulted from a process of lengthy study and consultation that began in late 1971 when the City and State of New York requested approval of the West Side highway corridor as part of the Interstate System. That process included discussion with a broad range of State and City agencies and community groups, not only concerning alternatives to the dilapidated West Side Highway, but also about methods of coordinating the highway reconstruction with redevelopment in the deteriorating pier and [1047]*1047shoreline areas on the west side of Manhattan.

In April 1974 a draft environmental impact statement (EIS) was circulated for public review. Extensive public hearings were held during the following six-month period for comment, and five alternatives were identified. In January 1977 a Final EIS (FEIS) was approved that selected Westway as the preferred alternative. Later in 1977 the State filed an application with the Corps for a dredge-and-fill permit that was issued on March 13, 1981.

Litigation brought to challenge the permit’s issuance has been before us previously. Sierra Club v. United States Army Corps of Engineers, 701 F.2d 1011 (2d Cir.1983); Sierra Club v. Hennessy, 695 F.2d 643 (2d Cir.1982). In these two decisions we upheld essentially the district court’s conclusion that the 1977 FEIS— which described the Westway area as a “biological wasteland” (suggesting no fish lived there) — had failed to reveal to the public the possible importance of the site as a winter habitat for juvenile striped bass. Action for Rational Transit v. West Side Highway Project, 536 F.Supp. 1225, 1229 (S.D.N.Y.1982). At that time many experts believed the juvenile striped bass used the Westway landfill area as an “overwintering” habitat — a place where these young fish remained more or less constantly throughout the winter months. 701 F.2d at 1024; 536 F.Supp. at 1246-1247.

Thus, in orders dated April 14 and July 23, 1982 the district court enjoined most construction and many other activities related to Westway and set aside the 1981 landfill permit granted by the Corps and the funding approvals granted by FHWA. The district court in its April order included a- provision requiring the Corps to “keep records of all activities, deliberations, and communications (including communications with the FHWA and any other federal official or agency) which occur in relation to [the Westway] permit application.” On appeal, we affirmed “the unusual but appropriate” record-keeping order and directed the federal defendants “to make their own independent evaluations” of the fisheries issue. Sierra Club v. United States Army Corps of Engineers, 701 F.2d at 1048.

B. Remand

On April 22, 1982 the State again applied to the Corps for a landfill permit for West-way. In October 1982 the Corps convened a workshop of experts to discuss whether and what type of further study was necessary to resolve the question of the fishery habitat. This workshop recommended that a 17-month analysis be undertaken and that the program include various habitat studies. In July 1983 a second workshop of experts was called to assess the need for additional fisheries studies. Participants at that workshop were in agreement that determining the severity of Westway’s effect on the striped bass was a matter beyond the state of the art.

Despite this uncertainty, on September 13, 1983 a decision was made by the Corps’ New York District Engineer to conduct two winters of additional study to determine Westway’s impact on the Hudson River bass. The Governor of New York appealed this decision to the Secretary of the Army, who directed the Corps’ Chief of Engineers to determine whether a two-winter project was necessary. A resulting task force report caused the Secretary to decide on December 15, 1983 that although a Supplemental Environmental Impact Statement for Westway could be prepared with existing information under the worst-ease regulations, the Corps’ New York District Engineer should proceed with a study, limited to one winter — or four months — rather than the 17 months the workshop had recommended.

On May 28, 1984 the Corps and FHWA published a Draft Supplemental Environmental Impact Statement (DSEIS or draft report). The DSEIS concluded that the proposed Westway project landfill would cause a significant loss of habitat to Hudson River juvenile striped bass. It stated that such loss would be a “significant adverse impact to the Hudson River Stock of this species.” Though not critical, the [1048]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fund for Animals v. Norton
365 F. Supp. 2d 394 (S.D. New York, 2005)
National Audubon Society v. Hoffman
917 F. Supp. 280 (D. Vermont, 1996)
Abenaki Nation of Mississquoi v. Hughes
805 F. Supp. 234 (D. Vermont, 1992)
Lewis v. Lujan
826 F. Supp. 1302 (D. Wyoming, 1992)
Pension Benefit Guaranty Corp. v. LTV Corp.
875 F.2d 1008 (Second Circuit, 1989)
United States Court of Appeals, Second Circuit
875 F.2d 1008 (Second Circuit, 1989)
Sierra Club v. Marsh
701 F. Supp. 886 (D. Maine, 1988)
Stow v. US ON BEHALF OF SOIL CONSERVATION SERV.
696 F. Supp. 857 (W.D. New York, 1988)
American Littoral Society v. Herndon
720 F. Supp. 942 (S.D. Florida, 1988)
Bersani v. United States Environmental Protection Agency
674 F. Supp. 405 (N.D. New York, 1987)
Hudson River Defense League v. Corps of Engineers
662 F. Supp. 179 (S.D. New York, 1987)
In Re McLean Industries, Inc.
70 B.R. 852 (S.D. New York, 1987)
Friends of the Earth v. Hintz
800 F.2d 822 (Ninth Circuit, 1986)
Eastern Connecticut Citizens Action Group v. Dole
638 F. Supp. 1297 (D. Connecticut, 1986)
Town of Fenton v. Dole
636 F. Supp. 557 (N.D. New York, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
772 F.2d 1043, 23 ERC 1153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-united-states-army-corps-of-engineers-ca2-1985.