American Littoral Society v. Herndon

720 F. Supp. 942, 1988 WL 166524
CourtDistrict Court, S.D. Florida
DecidedJune 10, 1988
Docket88-8144-CIV
StatusPublished
Cited by1 cases

This text of 720 F. Supp. 942 (American Littoral Society v. Herndon) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Littoral Society v. Herndon, 720 F. Supp. 942, 1988 WL 166524 (S.D. Fla. 1988).

Opinion

ORDER DENYING PRELIMINARY AND PERMANENT INJUNCTION

ROETTGER, District Judge.

PREFACE

Various environmental groups and individuals filed suit against the Army Corps of Engineers, Secretary of the Army and the City of Boca Raton seeking to block the permit for the beach nourishment project on a portion of Boca Raton’s north beach. Plaintiffs have no quarrel with the City’s having expended funds for the mitigation aspects of the permit and the mitigation portion of the permit has been completed at a substantial cost to the City.

Plaintiffs contend that the permit violates the Endangered Species Act because it requires construction during the months of June, July and August, the nesting season for two species of endangered sea turtles and one threatened species. The federal permit conforms to the state permit’s insistence that the construction be during the summer months only.

The Plaintiffs also contend that the act violates the Clean Waters Act. Plaintiffs seek determination that the beach nourishment project violates NEPA and Plaintiffs also seek the declaration of the Corps that the permit violates the Coastal Zone Management Act.

The parties have stipulated, pursuant to Fed.R.C.P. 65, that matters be considered on the extensive record without the necessity for evidentiary hearing and that the matters presented at the preliminary junction be consolidated with the permanent injunction considerations, as well.

After a brief chronology of events, detailed discussion of the issues raised at hearing is set forth.

CHRONOLOGY OF SIGNIFICANT EVENTS

In 1985, the City of Boca Raton completed a somewhat similar beach nourishment project .6 mile in length near the south end of its 5+ miles beach basically utilizing the same techniques; the project was completed during the month of June, apparently *944 without opposition from Plaintiffs herein or other groups.

On November 21, 1986, the Florida Department of Environmental Regulations, (DER), issued a permit to the City of Boca Raton (hereinafter “CITY”) for a beach restoration project in the northern part of the beach. A final order of dismissal of a prior dispute was entered the same day. Specific condition #3 of the DER permit restricts project construction to the months of June, July and August. Previously, various procedural steps were involved on the project. For example, on May 1, 1985, the Corps of Engineers circulated its draft GDM (General Design Memorandum) and draft EIS (Environmental Impact Statement) to various agencies and organizations, including Plaintiffs Sierra Club and the Audubon Society. Comments were submitted by various federal and state agencies on the drafts, however nothing was offered by Plaintiffs in the instant case. The final GDM and EIS were published by the Corps of Engineers in April of 1987.

The City applied for a permit from the Corps under Section 404 of the Clean Water Act and Section 10 of the Rivers and Harbors Act in December, 1984 and at the same time filed a permit application with the Florida Department of Environmental Regulations (DER) pursuant to state requirements. DER approved the permit in November of 1986 authorizing the construction of a beach 100 to 125 feet wide along a 1.45 miie stretch with 980,000 yards of sand dredged from a “borrow” area located approximately 2500 feet offshore. Because of its concerns about turbidity, DER limited City’s beach nourishment activity to the months of June, July and August only. Additionally, DER required the City to construct a groin to protect the Red Reef Rock formation and to construct six artificial reef modules, each consisting of 25 natural limestone boulders as mitigation for the loss of near-shore limestone rocks that would be covered by the beach nourishment project. After DER’s permit was issued, the City submitted a modified permit application to the Corps that reflected the conditions of the state permit.

As found by the State DER examiner, in May of 1987 the City had requested the three month construction restriction of DER be deleted completely from the permit. (At that time the City hoped to begin construction of the project in the fall of 1987 to avoid construction during the sea turtle nesting session, but otherwise still within the terms. DER’s hydragraphic engineer, Dr. Echternacht, opposed the request to delete the construction time limitation period. Because of the delays in the federal permitting process, the City withdrew the earlier modification requests.)

On September 2, 1987, a public hearing was held by the Corps on City’s “dredge and fill” permit application for a 1.45 mile, 100 to 120 feet wide project. Testimony was received from many witnesses, including several of Plaintiffs, and Plaintiffs’ witnesses.

In October, 1987, the U.S. Fish & Wildlife Service (FWS) issued its biological opinion with several reasonable and prudent measures, which must be implemented or the incidental take of the sea turtles “is not authorized”. As measure # 1: “...beach nourishment should be conducted before May 30th or after October 5th (preferably before May 1st or after October 31st).”

On November 12, 1987, the Corps issued a statement of findings regarding the City’s permit application discussing comments of various agencies, organizations and individuals plus discussion of practicable alternatives in the impacts and 16 separate factors involving the public interest, including economics, esthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, land use, shore erosion and accretion, recreation, water quality, safety, Corps wetland policy, mitigation, cumulative impacts, and endangered species.

The conclusion of the statement of findings of the Corps was that “the issuance of the permit [for the project] is not contrary to public interest”.

Further meetings were held between the Corps of Engineers and FWS in an effort *945 to avoid any encroachment of the project with sea turtle nesting and if that was unavoidable, to expand nest protection efforts to insure earliest relocation of nests in order to achieve maximum hatching success. See letter of December 22, 1987 from FWS to the District Engineer (Defendant Boca’s Exhibit 41).

In December of 1987, the City’s former “self-releasing hatchery” was lost due to erosion of the beach.

EPA initially opposed the Corps decision pursuant to its authority under the Clean Water Act, based on its perceived benefits of the near-shore rock outcroppings that would be covered by the project. Assistant Secretary of the Army for Public Works sent a letter to EPA supporting the determination that the near-shore rocks were not environmentally or ecologically significant.

On January 28,1988, the acting Regional Administrator for EPA for Region 4 concluded that the proposed project did not present an unacceptable adverse effect necessitating the exercise of EPA’s veto authority under Section 404(c) of the Clean Water Act. The Corps granted the City’s permit application on the same day. The work authorized by the Corps’ permit corresponds with the project approved by Florida DER. Also consistent with the state permit the Corps permit limited project activity to the months of June, July and August.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Albuquerque v. Browner
865 F. Supp. 733 (D. New Mexico, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
720 F. Supp. 942, 1988 WL 166524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-littoral-society-v-herndon-flsd-1988.