Environmental Coalition of Broward County, Inc. v. Myers

831 F.2d 984, 26 ERC 2043
CourtCourt of Appeals for the Eleventh Circuit
DecidedNovember 5, 1987
DocketNo. 86-5143
StatusPublished
Cited by13 cases

This text of 831 F.2d 984 (Environmental Coalition of Broward County, Inc. v. Myers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Coalition of Broward County, Inc. v. Myers, 831 F.2d 984, 26 ERC 2043 (11th Cir. 1987).

Opinions

RONEY, Chief Judge:

Plaintiff Environmental Coalition of Bro-ward County (the Coalition) appeals the refusal of the district court to enjoin work under a dredge and fill permit issued by the Corps of Engineers (the Corps) to the S.A. Horvitz Testamentary Trust (the Trust). We affirm.

The district court considered the application process, the public interest factors, the plans to go forward with the dredging of the Dania Cut-off Canal, the propriety of requiring no Environmental Impact Statement, and the Corps’ consideration of practical alternatives to the applicant’s proposal. The district court found that with respect to all these issues, the Corps’ determination was well reasoned, fully documented, and completely justified. The district court found no need to go beyond the administrative record to reach these conclusions. Camp v. Pitts, 411 U.S. 138, 143, 93 S.Ct. 1241, 1244, 36 L.Ed.2d 106 (1973); Save Our Ten Acres v. Kreger, 472 F.2d 463, 467 (5th Cir.1973).

Such findings of fact made by the district court shall not be set aside unless clearly erroneous, unless the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. Fed.R.Civ.P. 52(a); Anderson v. City of Bessemer, 470 U.S. 564, 573-75, 105 S.Ct. 1504, 1511-13, 84 L.Ed.2d 518 (1985).

REQUIRED SPECIFICATION OF APPLICATION

The Coalition argues that the description of the activities and structures proposed for the fill, which was supplied to the Corps by the Trust, did not contain enough specificity to provide effective public notice or to [986]*986permit adequate analysis of the environmental consequences by the concerned parties or agencies.

The regulations, however, only require general descriptions of the proposed use. Regulations published under Section 404 of the Clean Water Act, 33 U.S.C.A. § 1344, require that, before a dredge and fill permit can be issued, the Corps must be provided with “a complete description of the proposed activity including necessary drawings, sketches or plans sufficient for public notice.” 33 C.F.R. 325.1(d). This public notice is primarily intended to advise all interested parties of the proposed activity for which a permit is sought and to make possible an evaluation of the probable impact on the public interest.

The requirements of the public notice are not couched in terms of inordinate specificity, but need only convey “sufficient information to give a clear understanding of the nature and magnitude of the proposed activity to generate meaningful comment.” 33 C.F.R. 325.3(a). Blueprints of the entire layout are not required items of information. It is sufficient to include only a “brief description of the proposed activity, its purpose and intended use, ... including a description of the type of structures ... to be erected on fills.” 33 C.F.R. 325.-3(a)(5).

Under other regulations, the Corps’ district engineer cannot issue a public notice where the application does not comply with the above regulations. He is required to review all applications for completeness, and can only issue a public notice when an application is found to be complete. 33 C.F.R. 325.2(a)(2); 33 C.F.R. 325.3. A decision made by an administrative agency under authority of this kind is due great deference.

The district court was required to determine whether the Corps’ decision was reasonably supported by the information before it. This does not require that all of the data support the agency’s decision. It is enough that the Corps considered all relevant factors and that there is credible evidence in the record to support its action. Bowman Transportation, Inc. v. Arkansas-Best Freight System, Inc., 419 U.S. 281, 285-86, 95 S.Ct. 438, 441-42, 42 L.Ed.2d 447 (1974). In its review, a court should give deference to the agency determination. This is particularly appropriate in the case of complex environmental statutes such as the Clean Water Act. EPA v. National Crushed Stone Association, 449 U.S. 64, 83-84, 101 S.Ct. 295, 306-07, 66 L.Ed.2d 268 (1980); see also, National Wildlife Federation v. Marsh, 721 F.2d 767, 780 (11th Cir.1983). A court should not substitute its own views for the decision reached by the agency. These principles of judicial review are particularly appropriate where the agency decision under review includes a “balancing” process like the “public interest” review provided for by the Corps’ regulations. 33 C.F.R. 320.-4(b).

Under this standard of review, the Coalition’s assertion of insufficient specificity is not borne out by the record. The Trust filed a development plan describing its intended use for the property in question:

The 221-acre tract north of the DCC [Dania Cut-off Canal] has not otherwise been master planned ... since 1980, but its intended use has been explained in general terms ... to complement and supplement the activities of the Port Everglades Authority in a manner consistent with its industrial zoning classification. It is therefore anticipated that the property will be developed for marine industrial and commercial activities, such as Port-related support facilities and services, ... some degree of container cargo or warehousing ... along with some trucking/distribution activities. These projections are simply educated guesses or examples of specific uses that are representative of the more generic marine industrial/commercial classification given this project. Clearly, market demand and market conditions will have a major impact on the ultimate land uses, [987]*987and these variables cannot be evaluated at this point.

Adjacent uses and structures provided sources of reference and information concerning environmental consequences resulting from the type of activity and proposed use under this description. The Coalition has at no time demonstrated how the Corps’ consideration of the Trust’s permit application was impeded by failure to include additional information.

The district court cannot be faulted in deciding that the description provided, along with the comparison to other developments within the immediate area, was sufficient to justify the determination reached by the Corps of Engineers.

THE DANIA CUT-OFF CANAL

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ocean Conservancy v. Evans
260 F. Supp. 2d 1162 (M.D. Florida, 2003)
United States v. Irizarry
98 F. Supp. 2d 160 (D. Puerto Rico, 2000)
Sierra Club v. Glickman
Fifth Circuit, 1995
United States v. Robert A. Stenzel
49 F.3d 658 (Tenth Circuit, 1995)
Sierra Club v. Marsh
First Circuit, 1992
Miree Construction Corp. v. Dole
730 F. Supp. 385 (N.D. Alabama, 1990)
American Littoral Society v. Herndon
720 F. Supp. 942 (S.D. Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
831 F.2d 984, 26 ERC 2043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-coalition-of-broward-county-inc-v-myers-ca11-1987.