Seward Housing Corp. v. Conroy Bros. Co.

573 N.W.2d 364, 1998 Minn. LEXIS 29, 1998 WL 19488
CourtSupreme Court of Minnesota
DecidedJanuary 22, 1998
DocketC7-96-351
StatusPublished
Cited by1 cases

This text of 573 N.W.2d 364 (Seward Housing Corp. v. Conroy Bros. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seward Housing Corp. v. Conroy Bros. Co., 573 N.W.2d 364, 1998 Minn. LEXIS 29, 1998 WL 19488 (Mich. 1998).

Opinion

OPINION

BLATZ, Justice.

This appeal concerns issues arising out of a subcontract agreement between Conroy Brothers Company and its subcontractor, Right-Way Caulking. The Hennepin County District Court denied Conroy Brothers’ motion for summary judgment and dismissed its third-party claim for indemnification against Right-Way. Upon petition of Right-Way, we review the court of appeals decision, which affirmed the district court in part, but remanded the case for a factual determination of whether Right-Way’s work on the project was the cause of the underlying damages. We reverse and reinstate the judgment of dismissal.

In the spring of 1984, the owners of a low-income housing apartment building, now known as Seward Towers West, contracted with Conroy Brothers to install a new exteri- or wall system for the building. On September 27, 1984, Conroy subcontracted with Right-Way to provide caulking, sealing, and other services in connection with the installation of the wall system. Right-Way worked on the project in November and December 1984, in June through December 1985, and for two days in 1986. May 4, 1986, was the last day Right-Way employees performed any work on the project.

Seward Housing Corp. (Seward) purchased Seward Towers West in 1990. Cracks in the exterior wall installed by Conroy Brothers appeared as early as November 1987, but Seward maintained that these cracks were merely hairline cosmetic cracks that did not allow any water infiltration. In April 1993, however, a large chunk of the exterior wall fell to the ground. Seward subsequently commenced an action against Conroy Brothers, among others, alleging negligence in the construction of the wall system'. Seward never asserted a claim against Right-Way. Conroy Brothers, in turn, brought a third-party claim against Right-Way and other subcontractors.

Subsequently, Seward and Conroy Brothers entered into a Pierringer release, whereby Conroy Brothers paid Seward $400,000. Conroy Brothers, relying on a provision in the subcontract that required Right-Way to obtain a liability insurance coverage policy, moved for summary judgment against Right-Way for indemnification in the amount of $250,000. This amount represents the property damage limit of the liability insurance policy Right-Way contracted to procure. It is undisputed that Right-Way never purchased such a policy. However, the district court concluded that the subcontract required Right-Way to purchase general liability insurance and that,’ even if purchased, general liability insurance would not have covered the damages alleged in this case. Accordingly, the district court denied Conroy Brothers’ motion for summary judgment and dismissed its claim against Right-Way.

The court of appeals concluded that Rights Way is liable only for damages directly connected with its work on the subcontract. The court of appeals stated that if the damages were due to the negligence of another subcontractor, then Conroy Brothers is not entitled to indemnification from Right-Way. Thus, the court of appeals’ remand required a factual determination of whether Right-Way’s work on the project resulted in the underlying damages. On appeal, this court reviews whether Conroy Brothers’ claim for indemnification falls within the coverage of the liability insurance that Right-Way contracted to purchase.

*366 The relevant language in the subcontract agreement between Conroy Brothers and Righ1>-Way provides:

The Sub-Contractor agrees to assume entire responsibility and liability for all damages or injury to all persons, whether employees or otherwise, and to all property, arising out of, resulting from or in any manner connected with, the execution of the work provided for in this Sub-Contract or occurring or resulting from the use by the Sub-Contractor, his agents or employees, of materials, equipment, instrumental-ities or other property, whether the same be owned by the Contractor, the SubContractor or third parties, and the SubContractor agrees to indemnify and save harmless the Contractor, his agents and employees from all such claims including, without limiting the generality of the foregoing, claims for which the Contractor may be, or may be claimed to be, liable, and legal fees and disbursements paid or incurred to enforce the provisions of this paragraph, and the Sub-Contractor further agrees to obtain, maintain and pay for such general liability insurance coverage as will insure the provisions of this paragraph.

This indemnity language tracks the language of the Association of General Contractors of Minnesota (AGC) standard subcontract. Previously, this court analyzed identical language set forth in an AGC subcontract and concluded that the language “necessarily includes claims of the contractor’s negligence.” Johnson v. McGough Constr. Co., 294 N.W.2d 286, 288 (Minn.1980). Thus, the scope of the indemnity language in the instant case includes damages resulting from Conroy Brothers’ negligence, a fact that neither party disputes. 1

Until 1984, construction contracts that indemnified the indemnitee for claims arising out of its own negligence were upheld by this court, provided that the agreements expressed an unequivocal intent to indemnify for damages resulting from the indemnitee’s own negligence. See Farmington Plumbing & Heating Co. v. Fischer Sand & Aggregate, Inc., 281 N.W.2d 838, 842 (Minn.1979).

In 1983, however, the legislature enacted a statute that limits the enforceability of indemnification agreements in building and construction contracts executed on or after May 1, 1984. Currently, the statute provides that indemnification agreements are:

unenforceable except to the extent that the underlying injury or damage is attributable to the negligent or otherwise wrongful act or omission, including breach of a specific contractual duty, of the promisor or the promisor’s independent contractors, agents, employees, or delegatees.

Minn.Stat. § 337.02 (1996). Thus, no party can be indemnified when its own negligent acts or omissions are the underlying cause of the injury or damages. This restriction ensures that each party remains responsible for its own negligent actions.

Although the legislature clearly expressed its disapproval of indemnification agreements in construction contracts where one party undertakes to indemnify a second party for damages attributable to the second party’s fault, it carved out a narrow exception from this general prohibition, allowing parties to provide specific insurance coverage “for the benefit of others.” Minn.Stat. § 337.05, subd. 1 (1996). 2 Section 337.05, subd. 2, further provides that if:

(a) a promisor agrees to provide specific types and limits of insurance; and
(b) a claim arises within the scope of the specified insurance; and
*367 (c) the promisor did not obtain and keep in force the specified insurance;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No. (1999)
Nebraska Attorney General Reports, 1999

Cite This Page — Counsel Stack

Bluebook (online)
573 N.W.2d 364, 1998 Minn. LEXIS 29, 1998 WL 19488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seward-housing-corp-v-conroy-bros-co-minn-1998.