Security Insurance v. Kaye Milling Supply, Inc.

211 N.W.2d 519, 297 Minn. 348, 1973 Minn. LEXIS 1099
CourtSupreme Court of Minnesota
DecidedOctober 12, 1973
DocketNo. 43450
StatusPublished
Cited by8 cases

This text of 211 N.W.2d 519 (Security Insurance v. Kaye Milling Supply, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Security Insurance v. Kaye Milling Supply, Inc., 211 N.W.2d 519, 297 Minn. 348, 1973 Minn. LEXIS 1099 (Mich. 1973).

Opinion

Otis, Justice.

These proceedings arise out of a claim for damages brought by the owner against a building contractor who was enlarging and modernizing a grain storage bin which collapsed when it was filled with wet soybeans. The contractor’s liability carrier seeks a declaratory judgment holding that the damage resulted from a “completed operations hazard,” and that coverage is therefore expressly excluded by the terms of its policy. The district court heard the case without a jury and held that the exclusion did not apply. We reverse.

Prairie Farm Service, Inc. (Prairie) operates a grain storage and drying facility in Blooming Prairie, Minnesota. In May 1969, Prairie contracted with Kaye Milling Supply, Inc. (Kaye) for construction of facilities which would enlarge and improve Prairie’s operation. At the time work was begun, Kaye was covered by a contractor’s liability policy written by Security Insurance Company of Hartford (SIC), which policy is the subject of this litigation.

The issues are (1) whether, by the storage of beans in the bin which collapsed before construction was actually completed, Kaye is excluded from coverage with respect to Prairie’s claim under the “completed operations” provisions of the policy; and (2) whether the liability carrier is estopped from asserting the exclusion because of the time which elapsed before it denied coverage.

[350]*350The pertinent language of the exclusion is as follows:

“It is agreed that such insurance as is afforded by the Bodily Injury Liability Coverage and the Property Damage Liability Coverage does not apply to bodily injury or property damage iñcluded within the Completed Operations Hazard or the Products Hazard.”

The policy goes on to define “completed operations hazard” in this manner:

“* * * Operations shall be deemed completed at the earliest of the following times:

* * ‡ * s¡:

“(3) when the portion of the work out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project.”

The action brought by Prairie against Kaye has not been tried pending the disposition of the coverage issue. Consequently, there has not been an exhaustive presentation of the facts surrounding the accident. For purposes of this litigation the parties assume as facts matters which are not in dispute.

Prairie is in the business of purchasing grain from farmers in small quantities which it dries, stores, and sells in larger quantities. Before construction began, grain was unloaded in a pit and elevated to a point from which it was distributed by gravity to holding bins and then conveyed to dryers by horizontal augers. After being dried, the grain was returned to the storage bins. The bins and dryers were originally at ground level. One of the purposes of the construction was to place two holding bins above the dryers in order to empty them by gravity. The new elevated bins were held in place and supported by towers with four legs.

On the morning of October 24, 1969, a shipment of wet or “hot” soybeans was brought to the plant. It required drying to [351]*351prevent spoilage. Prairie thereupon sought and secured permission from Kaye to process the beans in the newly constructed north dryer. The south bin and dryer had already been in use some 10 days. Within half an hour of the time the north bin was filled, one of the legs supporting the tower collapsed, dropping the tower, bin, and dryer to the ground, resulting in extensive damage to the entire plant. The evidence does not establish the precise reason for the collapse of the tower. The parties agree that for purposes of this litigation it is not an issue. Nevertheless, they all assume, for obvious reasons, that the direct and immediate cause of the collapse was the stress created by filling the bin with several tons of soybeans.

The trial court, without an accompanying memorandum or further elaboration, made the following finding in construing the policy:

“That the accident referred to in paragraph 3 of these Findings occurred during the course of the construction work undertaken by Defendant, Kaye Milling Supply, Inc., under contract referred to in paragraph 2 of these Findings, and was not excluded from coverage under the completed operations exclusion contained in the policy issued by Plaintiff herein.”

Defendants Kaye and Prairie argue that under the facts and under the law the construction undertaken by Kaye was not a “completed operation” at the time the accident happened, and consequently the exclusion does not apply. They stress the fact that much remained to be done before the work was finished. Supporting cables to hold the bins in position had not been made secure; corner posts had not been bolted to the concrete base; cross bracing had not been completed; and a number of other attachments remained to be added, amounting to some 450 man-hours of work. Defendants take the position that the language of the policy which deems operations to be completed when the “portion of the work out of which the injury or damage arises [352]*352has been put to its intended use” has no bearing in the context of this case. They point out that the parties intended the operation of the plant to continue during the construction period. Because it is an integrated plant, it is defendants’ contention that no portion of the work has been put to its intended use until the entire plant has been put to such use. As an example of what the policy means, Prairie cites a contract to build three houses, upon the completion and occupancy of any one of which the exclusion would apply to that portion of the work. Here, it is argued, the erection of the towers and bins was not a segregated operation but rather a phase of the entire project. Unless such a phase can be segregated and completed, the exclusion has no application according to the defendants. They concede only that had the structure which held the bins been completed, the exclusion would be effective. In summary, they assert that the “intended use” test is only one indication of completion but does not, standing alone, constitute an exclusion. Finally, it is argued that the liability of Kaye may be predicated on its permitting the north bin to be used for the bin’s intended purpose at a time when it was structurally incomplete and not ready for the operation for which it was ultimately to be utilized.

SIC points out that this appears to be the first reported case dealing with the language contained in paragraph (3) of the “completed operations” exclusion. All of the litigation which has heretofore stemmed from the exclusion was directed at determining the point at which the entire contract was completed. The present language was adopted in October 1966. The change was made in response to such decisions as Heyward v. American Cas. Co. of Beading, Pa. 129 F. Supp. 4 (E. D. S. C. 1955). There, the United States District Court held there was no showing that the entire work which the contractor was obliged to perform had been completed. In rejecting the claim of exclusion, the court observed that the insurer was in effect attempting to amend its policy to read “if the accident or occurrence takes place after any [353]*353portion, or part of such operations have been completed * *1 129 F. Supp. 10.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ames Construction, Inc. v. Intermountain Industrial, Inc.
712 F. Supp. 2d 1160 (D. Montana, 2010)
Seward Housing Corp. v. Conroy Bros. Co.
573 N.W.2d 364 (Supreme Court of Minnesota, 1998)
R. E. M. IV, Inc. v. Robert F. Ackermann & Associates, Inc.
313 N.W.2d 431 (Supreme Court of Minnesota, 1981)
Prieto v. Continental Ins. Co.
358 So. 2d 851 (District Court of Appeal of Florida, 1978)
Abco Tank & Manufacturing Co. v. Federal Insurance Co.
550 S.W.2d 193 (Supreme Court of Missouri, 1977)
Tollefson v. American Family Insurance Co.
226 N.W.2d 280 (Supreme Court of Minnesota, 1974)
Security Ins. Co. of Hartford v. KAYE MILL. SUP., INC.
211 N.W.2d 519 (Supreme Court of Minnesota, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
211 N.W.2d 519, 297 Minn. 348, 1973 Minn. LEXIS 1099, Counsel Stack Legal Research, https://law.counselstack.com/opinion/security-insurance-v-kaye-milling-supply-inc-minn-1973.