R. E. M. IV, Inc. v. Robert F. Ackermann & Associates, Inc.

313 N.W.2d 431, 1981 Minn. LEXIS 1532
CourtSupreme Court of Minnesota
DecidedDecember 17, 1981
Docket81-59
StatusPublished
Cited by9 cases

This text of 313 N.W.2d 431 (R. E. M. IV, Inc. v. Robert F. Ackermann & Associates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. E. M. IV, Inc. v. Robert F. Ackermann & Associates, Inc., 313 N.W.2d 431, 1981 Minn. LEXIS 1532 (Mich. 1981).

Opinion

SCOTT, Justice.

This is an appeal from an order of the Ramsey County District Court granting summary judgment, interpreting contractual language requiring subcontractor Norcol, Inc. (Norcol) to indemnify the general contractor Buhler Construction Company (Buh-ler), pursuant to the terms and conditions of a contract and to accept the defense of Buhler or to pay certain costs thereof. We reverse.

Plaintiff R.E.M. IV, Inc., (R.E.M.) brought the original action against the architect, Robert F. Ackermann & Associates, Inc. (Ackermann), the general contractor, Buhler, and the subcontractor, Norcol, for property damage and lost profits caused by the freezing and bursting of fittings on the sprinkler system in plaintiff’s commercial buildings. In its complaint, R.E.M. alleges negligent design,.construction, and installation of the sprinkler system. Each of the three defendants denied liability and brought cross-claims against the other defendants for contribution and indemnity. Buhler’s motion for partial summary judgment against Norcol was granted, and Nor-col appeals that order. R.E.M. and Acker- *432 mann take no part in this appeal since their interests are unaffected by the order. 1

The Ackermann architectural firm designed two buildings for R.E.M. to be built in Fairmont, Minnesota, for use as homes for retarded and handicapped persons. The design provided for the construction and installation of a sprinkler system. On May 19, 1977, respondent Buhler, as general contractor, entered into a subcontract agreement with appellant Norcol to complete the sprinkler system for the sum of $12,905. The contract form used was the Associated General Contractors of Minnesota Standard Subcontract Agreement, 1974 edition. The two buildings were completed on December 1, 1977, and Norcol’s work on the sprinkler system was accepted as complete on that date.

On December 7, 1977, water froze in the sprinkler system, bursting one of the tee fittings and causing water damage to R.E. M.’s building. On January 9,1978, a second fitting burst, causing further damage. R.E.M. then brought this suit seeking $30,-000 in damages.

R.E.M.’s complaint alleges that the water loss was a result of the negligent acts of the defendants in the design and construction of the buildings and in the design, construction, and installation of the sprinkler system. In R.E.M.’s answer to interrogatories of Norcol, R.E.M. states the acts or omissions on which it bases its cause of action as follows: “The building was negligently and defectively designed and constructed in such a way that it allowed cold air to enter the building and freeze the pipes.” According to R.E.M.’s answer to Norcol’s interrogatories, R.E.M.’s expert will testify at trial that the fracture in the cast iron tee fitting “was apparently caused by an excessive internal pressure or force. A build up of ice within the fitting could have caused an increase in pressure sufficient to cause the fracture.”

Whether there was any defect in the pipe fittings is disputed. R.E.M.’s expert states that the fracture in the cast iron tee fitting was not caused by a defect in the casting. In contrast, in statements Buhler obtained immediately after the water damage occurred, non-expert employees of R.E.M. expressed opinions that the tee appeared to be faulty, since there was pipe sealer inside the seam of the pipe.

Buhler tendered its own defense to Nor-col, based on the following contractual indemnification provision in Subdivision 7 of the subcontract:

The Subcontractor agrees to assume entire responsibility and liability for all damages or injury to all persons, whether employees or otherwise, and to all property, arising out of it, resulting from or in any manner connected with, the execution of the work provided for in this Subcontract * * * and the Subcontractor agrees to indemnify and save harmless the Contractor * * * from all such claims.

Norcol refused to accept the tender of defense, claiming that since the work of the subcontract, the installation of the sprinkler system, had been completed and accepted prior to the freezing of the pipes in the sprinkler, the indemnification requirement of Subdivision 7 was not applicable. Norcol interprets the contractual language “the execution of the work provided for in this Subcontract” to require indemnification only for damage occurring while the subcontract work is in progress, and contends that the strict construction rule prevents extension of the contractual indemnity to cover damage occurring after completion of the work.

The only question to be decided on this appeal is whether, under Subdivision 7 of the Associated General Contractors Standard Subcontract Agreement, the subcontractor is required to indemnify the general contractor for the latter’s own negligence for property damage which occurred after the work of the subcontract was completed.

*433 Subdivision 7 of the Associated General Contractors Standard Subcontract Agreement, under which the general contractor Buhler seeks indemnity from Norcol, contains the following language:

To obtain, maintain and pay for such workmen’s compensation insurance as may be required by the General Contract or by law, comprehensive general liability insurance, comprehensive automobile liability insurance, protecting the Subcontractor against claims for bodily injury or death or for damage to property occurring upon, in or about the Project, with limits in amounts at least equal to the greater of those specified in the General Contract or those specified below:
⅜ sje * * * *
The Subcontractor agrees to assume entire responsibility and liability for all damages or injury to all persons, whether employees or otherwise, and to all property, arising out of it, resulting from or in any manner connected with, the execution of the work provided for in this Subcontract or occurring or resulting from the use by the Subcontractor, his agents or employees, of materials, equipment, instrumentalities or other property, whether the same be owned by the Contractor, the Subcontractor or third parties, and the Subcontractor agrees to indemnify and save harmless the Contractor, his agents and employees from all such claims including, without limiting the generality of the foregoing, claims for which the Contractor may be or may be claimed to be, liable and legal fees and disbursements paid or incurred to enforce the provisions of this paragraph and the Subcontractor further agrees to obtain, maintain and pay for such general liability insurance coverage as will insure the provisions of this paragraph.

(Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ALLIANT ENERGY-INTERSTATE POWER v. Duckett
732 N.W.2d 869 (Supreme Court of Iowa, 2007)
Kaydon Acquisition Corp. v. Custum Manufacturing, Inc.
301 F. Supp. 2d 945 (N.D. Iowa, 2004)
Cochran v. Gehrke, Inc.
293 F. Supp. 2d 986 (N.D. Iowa, 2003)
Modern Piping, Inc. v. Blackhawk Automatic Sprinklers, Inc.
581 N.W.2d 616 (Supreme Court of Iowa, 1998)
Seward Housing Corp. v. Conroy Bros. Co.
573 N.W.2d 364 (Supreme Court of Minnesota, 1998)
Campbell v. Mid-America Construction Co. of Iowa
567 N.W.2d 667 (Court of Appeals of Iowa, 1997)
Frederickson v. Alton M. Johnson Co.
390 N.W.2d 786 (Court of Appeals of Minnesota, 1986)
Fossum v. Kraus-Anderson Construction Co.
372 N.W.2d 415 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
313 N.W.2d 431, 1981 Minn. LEXIS 1532, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-e-m-iv-inc-v-robert-f-ackermann-associates-inc-minn-1981.