Anstine v. Lake Darling Ranch, Inc.

233 N.W.2d 723, 305 Minn. 243, 1975 Minn. LEXIS 1320
CourtSupreme Court of Minnesota
DecidedAugust 29, 1975
Docket45584
StatusPublished
Cited by16 cases

This text of 233 N.W.2d 723 (Anstine v. Lake Darling Ranch, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anstine v. Lake Darling Ranch, Inc., 233 N.W.2d 723, 305 Minn. 243, 1975 Minn. LEXIS 1320 (Mich. 1975).

Opinion

Yetka, Justice.

Appeal by defendant and third-party plaintiff, Lund-Martin Construction Company, from orders of the District Court of Douglas County granting motions for summary judgment made by a number of third-party defendants and from judgments entered pursuant to said orders.

We affirm.

Summary judgment has been entered in favor of the following third-party defendants-respondents: Acoustics Associates, Inc., Arrigoni Brothers Company, Custom Pools, Inc., Engelen Twin City Company, Glenmar-Hutchinson Company, Gust Lagerquist & Sons, Inc., Pella Products, Inc., and Thompson Lightning Pro *245 tection, Inc. 1 Third-party defendant Spancrete-Midwest also moved for summary judgment, but the motion has apparently not been ruled on by the trial court. Third-party defendants Egan & Sons Company, Egan-McKay Electrical Contractors, and Randy Whitehead did not move for summary judgment.

This is a personal injury action commenced by Kermit Anstine, a workman at the Lake Darling Ranch construction site, against the owner of the project and Lund-Martin Construction Company, the prime contractor. Lund-Martin joined all of the subcontractors connected with the prime project as third-party defendants, seeking indemnity from them.

The accident which caused this injury occurred on October 8, 1969, when Anstine, a plumber apprentice employed by third-party defendant Egan & Sons Plumbing and Heating Company, fell off the roof of a building under construction at the project site. The roof was wet at the time and plaintiff slid off it when he crawled upon a piece of loose cedar shingle, apparently left lying upon the roof by the employees of Randy Whitehead, a roofing subcontractor.

The project under construction was rather large, consisting of several separate buildings constituting restaurant, convention, and living unit facilities, and construction was carried on over a substantial period of time. Lund-Martin entered into identical standard Minnesota Associated General Contractors (AGC) subcontract agreements with all of the subcontractors named here as third-party defendants. Each of these subcontracts contained an indemnity clause that forms the basis of Lund-Martin’s third-party indemnity claims. In order to simplify the complicated facts, the various subcontractors, the work done by them, and *246 the dates on which they entered into the subcontracts with LundMartin are summarized below:

Subcontractor Type of Work Date Subcontract Signed Working on Site at time of Accident?

Custom Pools, Inc. construction of swimming pool July 18, 1969 No

Thompson Lightning Protection, Inc. installing lightning protection devices May 13, 1969 No

Pella Products, Inc. installation of windows July 18, 1969 No

Gust Lagerquist & Sons, Inc. installation of elevators June 2, 1969 No

Acoustics Associates, Inc. acoustical and resilient floor work August 11, 1971 No

Arrigoni Bros, tile work February 16, 1971 No

Engelen Twin City Company bituminous work in drive and park March 31, 1971 No

GlenmarHutchinson Co. installation of folding walls June 17, 1971 No

The legal issue raised on this appeal is: Under a subcontract which provides that a subcontractor shall indemnify the general contractor for liability for injury to persons “arising out of, resulting from or in any manner connected with, the execution of the work provided for in this Sub-Contract,” is a subcontractor liable to indemnify the prime contractor for liability for all injuries arising out of the entire construction project, without regard to whether the parties had entered into the subcontract *247 at the date of the injury, whether the subcontractor was working on the site at the time of the injury, and whether there was any causal connection between the work performed by the subcontractor and the injury?

The form of indemnity clause used in all the contracts involved in these appeals was Article VII of the AGO standard form subcontract, which provides as follows:

“The Sub-Contractor agrees to assume entire responsibility and liability for all damages or injury to all persons, arising out of, resulting from or in any manner connected with, the execution of the work provided for in this Sub-Contract or occurring or resulting from the use by the Sub-Contractor, his agents or employees, of materials, equipment, instrumentalities or other property, whether the same be owned by the Contractor, the SubContractor or third parties, and the Sub-Contractor agrees to indemnify and save harmless the Contractor, his agents and employees from all such claims including, without limiting the generality of the foregoing, claims for which the Contractor may be, or may be claimed to be, liable, and legal fees and disbursements paid or incurred to enforce the provisions of this paragraph, and the Sub-Contractor further agrees to obtain, maintain and pay for such general liability insurance coverage as will insure the provisions of this paragraph.” (Italics supplied.)

Appellant asks this court to construe that language to mean that all of the subcontractors working on the construction site formed a pool for the benefit of the general contractor and must be held liable to indemnify the general contractor for all personal injuries arising out of the entire construction project. Appellant contends that the phrase “work provided for in this SubContract” refers to the entire project and not just the items of work to be performed by the subcontractor signing each particular subcontract. Appellant expressly contends that it is irrelevant whether any of the subcontractors had entered into their subcontracts at the time of the accident, whether they were *248 working on the project at the time in question, and whether their actions had any causal connection with plaintiff’s accident.

Appellant apparently suggests that it should be entitled to summary judgment. It did move for judgment on the pleadings in the trial court. In the alternative, appellant suggests that the matter be remanded for trial to determine as a question of fact the intention of the parties in entering into the subcontract provisions.

Appellant’s entire argument is grounded upon two recent decisions of this court involving the same provision of the standard AGC subcontract: Christy v. Menasha Corp. 297 Minn. 334, 211 N. W. 2d 773 (1973), and Jacobson v. Rauenhorst Corp. 301 Minn. 202, 221 N. W. 2d 703 (1974).

In each of those cases, this court held that the prime contractor was entitled to indemnity from a subcontractor whose employee had been injured on the job, even though the cause of the injury in each case was the negligence of the prime contractor. Since the injury in each case arose out of the specific work performed by the specific subcontractor from whom indemnity was sought, whether other subcontractors whose work had no relation to the injury could be required to indemnify the prime contractor was not in issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen v. Burnet Realty, LLC
801 N.W.2d 153 (Supreme Court of Minnesota, 2011)
Allen v. BURNET REALTY, LLC
784 N.W.2d 84 (Court of Appeals of Minnesota, 2010)
Seward Housing Corp. v. Conroy Bros. Co.
573 N.W.2d 364 (Supreme Court of Minnesota, 1998)
National Hydro Systems v. M.A. Mortenson Co.
529 N.W.2d 690 (Supreme Court of Minnesota, 1995)
Holmes v. Watson-Forsberg Co.
488 N.W.2d 473 (Supreme Court of Minnesota, 1992)
Holmes v. Watson-Forsberg Co.
471 N.W.2d 109 (Court of Appeals of Minnesota, 1991)
Oster v. Medtronic, Inc.
428 N.W.2d 116 (Court of Appeals of Minnesota, 1988)
Fossum v. Kraus-Anderson Construction Co.
372 N.W.2d 415 (Court of Appeals of Minnesota, 1985)
R. E. M. IV, Inc. v. Robert F. Ackermann & Associates, Inc.
313 N.W.2d 431 (Supreme Court of Minnesota, 1981)
Johnson v. McGough Const. Co., Inc.
294 N.W.2d 286 (Supreme Court of Minnesota, 1980)
Farmington Plumbing & Heating Co. v. Fischer Sand & Aggregate, Inc.
281 N.W.2d 838 (Supreme Court of Minnesota, 1979)
Sargent v. Johnson
551 F.2d 221 (Eighth Circuit, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
233 N.W.2d 723, 305 Minn. 243, 1975 Minn. LEXIS 1320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anstine-v-lake-darling-ranch-inc-minn-1975.