Seven County Infrastructure Coalition v. Eagle County

605 U.S. 168
Supreme Court of the United States·Decided May 29, 2025·No. 23-975·Published·Cited by 6 cases

Opinion

(Slip Opinion) OCTOBER TERM, 2024 1

Syllabus

NOTE: Where it is feasible, a syllabus (headnote) will be released, as is being done in connection with this case, at the time the opinion is issued. The syllabus constitutes no part of the opinion of the Court but has been prepared by the Reporter of Decisions for the convenience of the reader. See United States v. Detroit Timber & Lumber Co., 200 U. S. 321, 337.

SUPREME COURT OF THE UNITED STATES

SEVEN COUNTY INFRASTRUCTURE COALITION ET AL. v. EAGLE COUNTY, COLORADO, ET AL.

CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 23–975. Argued December 10, 2024—Decided May 29, 2025 Under federal law, new railroad construction and operation must first be approved by the U. S. Surface Transportation Board. 49 U. S. C. §10901. In 2020, the Seven County Infrastructure Coalition applied to the Board for approval of an 88-mile railroad line connecting Utah’s oil-rich Uinta Basin to the national freight rail network, facilitating the transportation of crude oil to refineries along the Gulf Coast. As part of its project review, the Board prepared an environmental impact statement (EIS) that addressed significant environmental effects of the project and identified feasible alternatives that could mitigate those effects, as required by the National Environmental Policy Act (NEPA). The Board issued a draft EIS and invited public comment. After holding six public meetings and collecting more than 1,900 com- ments, the Board prepared a 3,600-page EIS that analyzed numerous impacts of the railway’s construction and operation. Relevant here, the EIS noted, but did not fully analyze, the potential environmental effects of increased upstream oil drilling in the Uinta Basin and in- creased downstream refining of crude oil. The Board subsequently ap- proved the railroad line, concluding that the project’s transportation and economic benefits outweighed its environmental impacts. Peti- tions challenging the Board’s action were filed in the D. C. Circuit by a Colorado county and several environmental organizations. The D. C. Circuit found “numerous NEPA violations arising from the EIS.” 82 F. 4th 1152, 1196. Specifically, the D. C. Circuit held that the Board im- permissibly limited its analysis of the environmental effects from up- stream oil drilling and downstream oil refining projects, concluding that those effects were reasonably foreseeable impacts that the EIS should have analyzed more extensively. Based on the deficiencies it 2 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Syllabus

found in the EIS, the D. C. Circuit vacated both the EIS and the Board’s final approval order. Held: The D. C. Circuit failed to afford the Board the substantial judicial deference required in NEPA cases and incorrectly interpreted NEPA to require the Board to consider the environmental effects of upstream and downstream projects that are separate in time or place from the Uinta Basin Railway. Pp. 6–22. (a) NEPA ensures that agencies and the public are aware of the en- vironmental consequences of certain proposed infrastructure projects. As a purely procedural statute, NEPA “does not mandate particular results, but simply prescribes the necessary process” for an agency’s environmental review of a project. Robertson v. Methow Valley Citi- zens Council, 490 U. S. 332, 350. Some federal courts reviewing NEPA cases have assumed an aggressive role in policing agency compliance with NEPA, and have not applied NEPA with the judicial deference demanded by the statutory text and the Court’s cases. When, as here, a party argues that an agency action was arbitrary and capricious due to a deficiency in an EIS, the “only role for a court” is to confirm that the agency has addressed environmental conse- quences and feasible alternatives as to the relevant project. Strycker’s Bay Neighborhood Council, Inc. v. Karlen, 444 U. S. 223, 227. Further, the adequacy of an EIS is relevant only to the question of whether an agency’s final decision (here, to approve the railroad project) was rea- sonably explained. Judicial deference in NEPA cases extends to an agency’s determina- tion of what details are relevant in an EIS. While NEPA requires an EIS to be “detailed,” 42 U. S. C. §4332(2)(C), and the meaning of “de- tailed” is a legal question, see Loper Bright Enterprises v. Raimondo, 603 U. S. 369, 391–392, what details need to be included in any given EIS is a factual determination for the agency. The textual focus of NEPA is the “proposed action”—the project at hand—not other sepa- rate projects. §4332(2)(C). Courts should defer to agencies’ discretion- ary decisions about where to draw the line when considering indirect environmental effects and whether to analyze effects from other pro- jects separate in time or place. See Department of Transportation v. Public Citizen, 541 U. S. 752, 767. In sum, when assessing significant environmental effects and feasible alternatives for purposes of NEPA, an agency will invariably make a series of fact-dependent, context-spe- cific, and policy-laden choices about the depth and breadth of its in- quiry—and also about the length, content, and level of detail of the resulting EIS. Courts should afford substantial deference and should not micromanage those agency choices so long as they fall within a broad zone of reasonableness. Even a deficient EIS does not neces- sarily require vacating an agency’s project approval, absent reason to Cite as: 605 U. S. ____ (2025) 3

believe that the agency might disapprove the project if it added more to the EIS. Cf. 5 U. S. C. §706. Pp. 6–15. (b) Contrary to the D. C. Circuit’s NEPA analysis, the Board’s deter- mination that its EIS need not evaluate possible environmental effects from upstream and downstream projects separate from the Uinta Ba- sin Railway complied with NEPA’s procedural requirements, particu- larly NEPA’s textually mandated focus on the “proposed action” under agency review. While indirect environmental effects of the project it- self may fall within NEPA’s scope even if they might extend outside the geographical territory of the project or materialize later in time, the fact that the project might foreseeably lead to the construction or increased use of a separate project does not mean the agency must con- sider that separate project’s environmental effects. See Public Citizen, 541 U. S., at 767. This is particularly true where, as here, those sepa- rate projects fall outside the agency’s regulatory authority. Pp. 15–21. (c) NEPA does not allow courts, “under the guise of judicial review” of agency compliance with NEPA, to delay or block agency projects based on the environmental effects of other projects separate from the project at hand. Vermont Yankee Nuclear Power Corp. v. Natural Re- sources Defense Council, Inc., 435 U. S. 519, 558. Pp. 21–22. 82 F. 4th 1152, reversed and remanded.

Free access — add to your briefcase to read the full text and ask questions with AI

Seven County Infrastructure Coalition v. Eagle County, 605 U.S. 168 (2025).

605 U.S. 168 (Seven County Infrastructure Coalition v. Eagle County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related