Save the Sound, Inc. v. FAA

Court of Appeals for the D.C. Circuit·Decided July 21, 2026·No. 24-1028·Published

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued December 12, 2025 Decided July 21, 2026

No. 24-1028

SAVE THE SOUND, INC., PETITIONER

v.

FEDERAL AVIATION ADMINISTRATION AND BRYAN BEDFORD, IN HIS CAPACITY AS ADMINISTRATOR OF THE FEDERAL AVIATION ADMINISTRATION, RESPONDENTS

AVPORTS LLC AND TWEED NEW HAVEN AIRPORT AUTHORITY, INTERVENORS

Consolidated with 24-1029

On Petitions for Review of an Order of the Federal Aviation Administration

Dana Hrelic argued the cause for petitioners. With her on the briefs were James T. Shearin, Roger Reynolds, Jessica Roberts, and Dara Illowsky. 2 Rebecca Jaffe, Attorney, U.S. Department of Justice, argued the cause for respondents. With her on the brief were Adam R.F. Gustafson, Assistant Attorney General, and Robert J. Lundman and Kevin W. McArdle, Attorneys.

W. Eric Pilsk, Catherine M. van Heuven, and David J. Monz were on the brief for intervenor Tweed New Haven Airport Authority in support of respondents. Peter J. Kirsch entered an appearance.

Kenneth P. Quinn and David F. Knapp were on the brief for intervenor Avports LLC in support of respondents.

Kelley J. Halliburton was on the brief for amicus curiae City of New Haven, Connecticut in support of respondents.

Before: SRINIVASAN, Chief Judge, WILKINS and KATSAS, Circuit Judges.

Opinion for the Court filed by Circuit Judge KATSAS.

KATSAS, Circuit Judge: The National Environmental Policy Act requires federal agencies to prepare reports discussing the environmental effects of major federal actions. Its requirements are modest, purely procedural, and serve only to facilitate informed agency decision-making. In this case, an environmental group and a town challenge the Federal Aviation Administration’s approval of a construction project at a small Connecticut airport. They allege numerous NEPA violations, but their theories would require us to override reasonable agency judgments or explanations. Neither NEPA nor the Administrative Procedure Act permits this, so we deny the petitions for review. 3 I

A

NEPA requires federal agencies to prepare reports on the environmental effects of “major Federal actions.” 42 U.S.C. § 4332(2)(C). The report must discuss “reasonably foreseeable environmental effects.” Id. § 4332(2)(C)(i).

An agency may issue its report in one of two forms. When a project does not have “reasonably foreseeable significant effect[s]” on the environment, an agency must prepare an environmental assessment (EA). 42 U.S.C. § 4336(b)(2). Such an EA must “concise[ly]” set forth the agency’s reasons for finding no significant environmental effects. Id. If a project is expected to have significant environmental effects, the agency must prepare a longer environmental impact statement (EIS). Id. § 4336(b)(1). But neither an EA nor an EIS may go on endlessly. In 2023, Congress prohibited EAs that exceed 75 pages and EISs that exceed 150 pages absent extraordinary circumstances. Id. § 4336a(e).

In Seven County Infrastructure Coalition v. Eagle County, 605 U.S. 168 (2025), the Supreme Court stressed that courts play a modest role in reviewing agencies’ NEPA reports. The Court ordered a “course correction … to bring judicial review under NEPA back in line with the statutory text and common sense.” Id. at 184. This correction was necessary because lower courts had “strayed and not applied NEPA with the level of deference demanded by the statutory text” and judicial precedent. Id. at 183. For example, the Court explained that NEPA’s “textually mandated focus” is “the ‘proposed action’—that is, the project at hand.” Id. at 186–87 (quoting 42 U.S.C. § 4332(2)(C) (2018)). Therefore, agencies need not evaluate the environmental effects of a “possible future” project or a “geographically distant” one. Id. at 187. Similarly, 4 although NEPA requires “detailed” agency reports, it does not specify what details must be included, and it prohibits bloated reports. Id. at 180–81 & n.3. “So the question of whether a particular report is detailed enough in a particular case itself requires the exercise of agency discretion—which should not be excessively second-guessed by a court.” Id. at 181. Summing up, the Court held that “the central principle of judicial review in NEPA cases is deference.” Id. at 179.

Finally, the Court reiterated the settled principle that “NEPA is a purely procedural statute” that “does not require the agency to weigh environmental consequences in any particular way.” Seven County, 605 U.S. at 173; see also id. at 180 (“NEPA imposes no substantive constraints on the agency’s ultimate decision to build, fund, or approve a proposed project.”). An agency therefore may conclude that “other values outweigh the environmental costs” of a project, and we must respect that determination so long as the agency has reasonably explained it. Id. at 177–78 (cleaned up).

B

Tweed New Haven Airport is a regional Connecticut airport managed by the Tweed-New Haven Airport Authority. Tweed is one of the most underserved airports in the country. In September 2021, the only airline flying there stopped doing so. As of late 2023, only one airline had stepped in to fill the void—a short-haul carrier called Avelo.

Tweed has no shortage of problems, but two are relevant here. First, its only active runway is too short. At 5,600 feet, it cannot accommodate the weight of full-capacity flights on one of the most common passenger planes—the Boeing 737- 800. To comply with the runway’s current weight limits, Avelo must reduce the capacity on such flights from 189 to 162 seats. Second, Tweed’s passenger terminal is undersized and 5 outdated. The existing terminal was built as a hangar in 1980 and then converted to a passenger terminal. It is cramped, inefficient, and prone to flooding.

To address these and other problems, the Airport Authority prepared a Master Plan. Running over 250 pages, it laid out proposed upgrades for the next several decades. To target the specific problems noted above, the Authority proposed an expansion project that would (1) extend the runway by roughly 1,000 feet to accommodate 737-800 aircraft at full capacity and (2) build a new passenger terminal.

The Master Plan also proposed to improve Tweed’s unusual taxiways. A taxiway is a road for planes to travel between hangars and runways. Tweed’s taxiways have atypical signage and acute rather than right-angle connections to the runway. The Airport Authority proposed construction projects to address these taxiway issues. The Authority preliminarily projected that these taxiway upgrades would have significant environmental effects on nearby water or wetlands.

C

The FAA bifurcates its approval process for airport expansion projects. To start, an airport may seek conditional approval to evaluate whether a proposed project is safe. At this initial stage, the project is still too tentative for environmental review. In the FAA’s words, environmental review is “not yet needed and … not ripe for decision.” FAA Order 5050.4B (2006) (reprinted at J.A. 762). Later, the airport may seek final approval, which requires NEPA review.

The Airport Authority received conditional approval for all the projects in its Master Plan, but it sought final approval only for the runway extension and new terminal. The FAA treated the runway extension and new terminal as a single 6 project.

Free access — add to your briefcase to read the full text and ask questions with AI

Save the Sound, Inc. v. FAA, (D.C. Cir. 2026).

Save the Sound, Inc. v. FAA (Save the Sound, Inc. v. FAA) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related