Servidone Construction Corp. v. United States

36 Cont. Cas. Fed. 75,893, 20 Cl. Ct. 725, 1990 U.S. Claims LEXIS 241, 1990 WL 89040
United States Court of Claims·Decided June 28, 1990·No. No. 282-84C·Published·Cited by 2 cases

Opinion

ORDER ON ATTORNEY FEES, EXPENSES AND COSTS

BRUGGINK, Judge.

This litigation arose out of a contract between the United States Army Corps of Engineers (“Corps”) and Servidone Construction Corporation (“Servidone”), for completion of an earthen dam near Dallas, Texas. The action was brought under the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1982). Plaintiff sought the total amount of $41,877,029. The largest claim, involving embankment work, was based on allegations of a differing site condition, and on defective specifications. On February 2, 1990, judgment was entered for plaintiff in the amount of $14,441,123. The action is presently before the court on plaintiffs application, pursuant to the Equal Access to Justice Act (“EAJA”), 28 U.S.C. § 2412 (1988), for attorney fees and expenses in the amount of $2,484,055.73, and on defendant’s opposition to plaintiff’s bill of costs. For the reasons set out below, the application for fees and expenses is denied in most respects, and the bill of costs is allowed in part.

1. The application for fees and expenses

The EAJA directs a court to award “fees and expenses” to certain parties who prevail in litigation against the United States. To establish entitlement, the act requires: (1) that the claimant be a prevailing party; (2) that the Government’s position was not substantially justified; (3) that no special circumstances make the award unjust; and (4) that the fee application be timely submitted and properly supported. Commissioner v. Jean, — U.S. —, —, 110 S.Ct. 2316, 2317, 110 L.Ed.2d 134 (U.S. June 4, 1990). The only entitlement issue raised by defendant’s opposition to the fees is whether defendant has demonstrated that its position was substantially justified. Defendant also contends that, even if its position was not substantially justified, the application is unsupported in its request for an enhanced hourly rate, in its itemization of certain fees, and with respect to certain expenses and expert fees claimed.

In Pierce v. Underwood, 487 U.S. 552, 108 S.Ct. 2541, 101 L.Ed.2d 490 (1988), the Court clarified the meaning of the term “substantially justified,” used by Congress to limit the circumstances in which fee shifting would be required. The Court opted for the following definition:

“justified in substance or in the main”— that is, justified to the degree that could satisfy a reasonable person. That is no different from the “reasonable basis both in law and fact” formulation adopted by the Ninth Circuit and the vast majority of other Courts of Appeals that have addressed this issue.

Id. at 565, 108 S.Ct. at 2550. The more stringent “justified to a high degree” test was thus rejected. Id.

In its application and in its reply brief, plaintiff relies in part on the argu[727] ment that the agency’s conduct prior to litigation was unjustified. It points to the facts that no contracting officer’s decision was ever rendered, and on the agency’s failure to “seriously” pursue settlement. Servidone suggests that if the agency’s conduct was unreasonable prior to litigation, that is sufficient basis to reject defendant’s contention that its position was substantially justified within the meaning of the EAJA. Plaintiff relies in part on the recent Supreme Court decision in Commissioner v. Jean, 110 S.Ct. 2316. The question addressed by the Court in that case was whether a prevailing party is ineligible for fees incurred in litigating the question of attorney fees if the Government’s position on that aspect of the dispute was substantially justified. The Court concluded that only one threshold determination concerning justifiability of the Government’s position should be made. Commissioner v. Jean, 110 S.Ct. at 2317. From this, Servi-done argues that, because the Government’s conduct at the agency level was unreasonable, it follows that plaintiff is entitled to fees. The court disagrees.

In Essex Electro Engineers, Inc. v. United States, 757 F.2d 247 (Fed.Cir.1985), the trial court had determined, in finding liability, that the agency’s conduct was irrational and arbitrary. See 4 Cl.Ct. 463 (1984). In asking for attorney fees, plaintiff took the position that, a priori, the Government’s position was not substantially justified. The Federal Circuit rejected that view, and held that “the merits of the agency decision constitute only one factor in evaluating the justification for the Government’s litigating position in court.” 757 F.2d at 253. This analysis is fully consistent with Commissioner v. Jean, and has application here. The court will make a single determination of the justifiability of the Government’s position, taking into account both the agency’s conduct and actions before the court. The court considers the agency’s conduct in this instance to be of relatively less importance, however. The lawsuit did not generate a great deal of information about how the agency handled the claim, other than to disclose that there was apparently no interest in settlement, and little regard for the merits of plaintiff's assertions.

Servidone points to the fact that the Contracting Officer did not issue decisions on the claims submitted by plaintiff. That is an eventuality specifically contemplated by the Contract Disputes Act, however. See 41 U.S.C. § 605(c)(5). The claim with respect to embankment work, by far the most substantial one, was presented on March 1,1984. The claim was for over $13 million and was 41 pages long. To say that the embankment claim would raise difficult questions, particularly in the midst of contract performance, is an understatement. The court notes that Servidone contended that it had been ordered to do extra work, and that the extra work constituted a cardinal change in the contract. An allegation of a cardinal change is a suggestion that the contract has been breached; that the work is a drastic modification beyond the original agreement. Air-A-Plane Corp. v. United States, 187 Ct.Cl. 269, 408 F.2d 1030, 1033 (1969). That argument was rejected after trial, but given its seriousness in the midst of the ongoing work, it is not surprising that the Contracting Officer was unable or unwilling to issue a decision within the statutory time period necessary to ripen appeal rights. Plaintiff filed its complaint on June 4, 1984.

The reasonableness of the Government’s settlement posture is peculiarly difficult to assess, and is best considered in light of the Government’s ability to justify its litigating position at trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Servidone Construction Corp. v. United States, 36 Cont. Cas. Fed. 75,893, 20 Cl. Ct. 725, 1990 U.S. Claims LEXIS 241, 1990 WL 89040 (cc 1990).

36 Cont. Cas. Fed. 75,893 (Servidone Construction Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Federal Savings & Loan Ass'n v. United States
88 Fed. Cl. 572 (Federal Claims, 2009)