S.D. Deacon Corp. v. Gaston Bros. Excavating

150 Wash. App. 87
CourtCourt of Appeals of Washington
DecidedMay 11, 2009
DocketNo. 61702-8-I
StatusPublished
Cited by12 cases

This text of 150 Wash. App. 87 (S.D. Deacon Corp. v. Gaston Bros. Excavating) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.D. Deacon Corp. v. Gaston Bros. Excavating, 150 Wash. App. 87 (Wash. Ct. App. 2009).

Opinion

Becker, J.

¶1 Trial courts should take care not to let the frivolous lien statute be misused to deprive contractors of their right to a trial on a lien claim. The summary release of a lien under RCW 60.04.081 is not to occur unless the lien is so devoid of merit that the claim has no possibility of succeeding. This appeal involves an ordinary contract dispute with factual issues that should not have been decided on affidavits. We reverse and remand for reinstatement of the lien.

¶2 A lien is an encumbrance on property to secure payment of a debt. Kinne v. Kinne, 27 Wn. App. 158, 161, 617 P.2d 442 (1980). A contractor has a lien upon an [90]*90improvement of real property for the contract price of labor and materials furnished:

[A]ny person furnishing labor, professional services, materials, or equipment for the improvement of real property shall have a lien upon the improvement for the contract price of labor, professional services, materials, or equipment furnished at the instance of the owner.

RCW 60.04.021. The term “contract price” means “the amount agreed upon by the contracting parties, or if no amount is agreed upon, then the customary and reasonable charge therefor.” RCW 60.04.011(2).

¶3 The lien procedure can be abused by persons who desire to encumber someone else’s real property improvement without any real basis for doing so. The legislature has created a summary proceeding to enable courts to remove frivolous liens quickly:

Any owner of real property subject to a recorded claim of lien under this chapter, or contractor . . . who believes the claim of lien to be frivolous and made without reasonable cause, or clearly excessive may apply by motion to the superior court. . . for an order directing the lien claimant to appear before the court. . . and show cause, if any he or she has, why the relief requested should not be granted.

RCW 60.04.081(1). We have held that the legislature intended to allow a resolution of factual disputes in this summary proceeding. W.R.P. Lake Union Ltd. P’ship v. Exterior Servs., Inc., 85 Wn. App. 744, 750, 934 P.2d 722 (1997). But the summary resolution of factual disputes must be confined to the limited group of cases where the lien claim is clearly meritless. The summary procedure provided by the statute is not to be used as a substitute for trial where there is a legitimate dispute about the amount of work done and money paid. Williams v. Athletic Field, Inc., 142 Wn. App. 753, 765 n.5, 139 P.3d 426 (2006). “Nowhere in the statute does the legislature give the trial court authority to expand this summary proceeding into a suit to foreclose the lien or to recover on a contractual [91]*91theory.” Andries v. Covey, 128 Wn. App. 546, 550, 113 P.3d 483 (2005).

¶4 The lien claimant bears the ultimate burden of proof when it seeks to enforce the lien. But in a summary proceeding under the frivolous lien statute, the party seeking release of the lien must establish beyond legitimate dispute that the lien was improperly filed. W.R.P., 85 Wn. App. at 752. Every frivolous lien is invalid, but not every invalid lien is frivolous. Intermountain Elec., Inc. v. G-A-T Bros. Constr., Inc., 115 Wn. App. 384, 394, 62 P.3d 548 (2003).

¶5 The lien at issue in this case was recorded by appellant Gaston Brothers Excavating, Inc., against a property in north Seattle because of a debt allegedly owed by general contractor S.D. Deacon Corporation of Washington. Deacon contracted with Gaston to prepare the ground for a fitness center in north Seattle. After Gaston worked for several months, a dispute arose about the contract price.

¶6 Gaston submitted a first bid proposal on April 13, 2007. This bid was for $49,000 for work described as “footings for LA Fitness, swimming pool and depressed slabs.” Gaston submitted a second bid on April 16 for work described as “Capillary Break,” a moisture barrier. This bid set forth three price options: “Pea Gravel” at $78,000, “Type 22 (5/8" crushed)” at $73,000 or “Crushed Glass (5/8")” at $63,000.

¶7 Deacon sent Gaston a letter on May 18 agreeing to award a subcontract in the amount of $112,000. Gaston began work. On June 14, Gaston submitted an application for a progress payment reciting that of the total contract amount of $112,000, 44 percent of the work had been completed. This amounted to a $49,000 charge. After subtracting 10 percent for retention, Gaston requested payment of $44,100. Gaston’s invoice for $44,100 bore the notation “1st Phase” and recited that it was for June 1 through June 30 for “Footings For LA Fitness, swimming pool and depressed slabs.”

[92]*92¶8 On July 13, 2007, Deacon sent Gaston a lengthy subcontract agreement. The agreement stated that Gaston’s bid was for a total of $63,000:

This Subcontractor’s proposal includes labor, materials, equipment, insurances and taxes per the following breakdown:
(Note: this breakdown is for accounting purposes only)
Base Bid $49,000.00
Capillary Break
Crushed Glass 5/8" $14,000.00_
Total $63,000.00

The agreement also contained an integration clause representing that it was the entire agreement between Deacon and Gaston with respect to the fitness project.

¶9 On July 19, Deacon sent Gaston a change order. The order recited that the contract amount of $63,000.00 was changed by agreement to $63,991.75 to include an additional $991.75 for earthwork and utilities. Gary Gaston signed the change order on July 24.

¶10 On August 3, Deacon sent Gaston a check for $44,100 in response to Gaston’s June invoice. The check was attached to a statement reciting that the payment was for work done in June. On October 5, Deacon sent Gaston a check for $10,000 attached to a statement reciting that it was for work done in July.

¶11 Deacon refused to pay more. Deacon maintained that there was one integrated contract for the entire project, including the capillary break work as well as the footings, for a total contract price of $63,991.75. Gaston believed there were two separate subcontracts totaling $112,000.00, the first for the footings and the second for the capillary break. On October 11, Gaston recorded a claim of lien in the amount of $43,191.75. Deacon reacted on October 17 with a “unilateral deductive change order” for $9,891.75, reducing the contract price to $54,100.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Park South LLC v. Denali Construction LLC
Court of Appeals of Washington, 2024
Hindman Construction, Inc., V. Greg Boos
Court of Appeals of Washington, 2023
Lennar Multifamily Builders, Llc, V. Saxum Stone, Llc
492 P.3d 175 (Court of Appeals of Washington, 2021)
Baker v. CMH Homes Inc
W.D. Washington, 2019
Denise Brackett Woodley v. Style Corporation D/b/a
Court of Appeals of Washington, 2019
George Woods v. Johnny Hill, Et Ux
Court of Appeals of Washington, 2014
Gray v. Bourgette Construction, LLC
160 Wash. App. 334 (Court of Appeals of Washington, 2011)
Verbeek Properties, LLC v. GreenCo Environmental, Inc.
159 Wash. App. 82 (Court of Appeals of Washington, 2010)
Verbeek Properties v. Greenco Environ
246 P.3d 205 (Court of Appeals of Washington, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
150 Wash. App. 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sd-deacon-corp-v-gaston-bros-excavating-washctapp-2009.