Hindman Construction, Inc., V. Greg Boos

CourtCourt of Appeals of Washington
DecidedFebruary 13, 2023
Docket83802-4
StatusUnpublished

This text of Hindman Construction, Inc., V. Greg Boos (Hindman Construction, Inc., V. Greg Boos) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hindman Construction, Inc., V. Greg Boos, (Wash. Ct. App. 2023).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

HINDMAN CONSTRUCTION, INC., a No. 83802-4-I Washington corporation, DIVISION ONE Appellant,

v. UNPUBLISHED OPINION

GREG BOOS, an individual, and LAI LAI CHAN, an individual,

Respondents,

WHATCOM EDUCATIONAL CREDIT UNION, a Washington non-profit banking institution,

Defendant.

SMITH, A.C.J. — Hindman Construction contracted with Greg Boos and Lai

Lai Chan in July 2018 for Hindman to renovate Boos’s1 home. Throughout the

renovation, Boos suspected that Hindman was overcharging them and requested

to see back-up receipts and invoices. Hindman did not provide any. After

Hindman issued its final invoice, Boos refused to pay. Hindman then recorded a

lien on Boos’s house and sought to enforce it. Hindman sued to enforce the lien

and for breach of contract, unjust enrichment, and recovery in quantum meruit.

Boos brought successive motions for summary judgment seeking to dismiss

1 Following Boos and Chan’s practice in their briefs, we refer to them

collectively as “Boos.”

Citations and pin cites are based on the Westlaw online version of the cited material. No. 83802-4-I/2

Hindman’s claims, which were granted, and Hindman appeals. Because material

issues of fact exist as to the contract claim, we reverse dismissal of the contract

claim and lien claim, but we affirm the dismissal of the equitable claims. We also

reverse the award of attorney fees.

FACTS

Hindman Construction and Greg Boos and Lai Lai Chan entered into a

construction contract in July 2018 for Hindman to renovate Boos’s home in

Bellingham. Several provisions of the contract are relevant to this appeal.

Article 4

Article 4 covers construction progress and final payments. It states: [T]he Owners shall not . . . occupy or use the Contractor’s work until and unless the Contractor shall have been first provided the signed and written punch list, if any.

Article 7

Article 7 concerns the owners’ responsibilities, including when and how

the owners can reoccupy the house. It states: OCCUPANCY: Owners shall not occupy nor be placed in possession nor will the Contractor deliver full or partial possession to the Owners until the building department of authority has approved the construction and issued an occupancy permit, and the Contractor has been paid in full, including all changes or additions ordered.

Article 11

Article 11 governs changes to the contract and construction plans. These

change requests are called change orders. It sets out how change orders are

submitted and states that any additional charges will be added to the contract

price. It also states:

2 No. 83802-4-I/3

All change requests will be submitted in writing upon individual request. Scanned transmissions are acceptable. Verbal requests for changes are binding under this contract. . . . Owners and Contractor may acknowledge one change order in writing after it has been verbally authorized. The additional charge will be added to the contract price. All change orders shall be incorporated in, and become a part of the contract. ... Change Orders may affect the completion date of the project.

Article 13

Article 13 covers warranty. It provides: Contractor warrants all work for a period of one-year following the date of substantial completion or date of occupancy, whichever occurs first. Contractor will determine date of completion.

Article 13 also provides that: Any claim or cause of action arising out of the terms of the contract, including this warranty, must be filed in a court of competent jurisdiction within 14 days following expiration of the warranty period. Any cause of action based upon breach of contract or warranty, which is not so filed, is waived.

Article 14

Article 14 addresses disputes and remedies. It states: If a dispute should arise between the parties, the parties shall promptly meet and attempt in good faith to resolve it. Openness, calm and good faith are required of both parties. Any unsettled disputes between the parties shall be decided by an action filed in an appropriate court of jurisdiction unless the parties mutually agree otherwise. . . . In the event a dispute or lawsuit arises and one or both parties seek and receive the assistance of legal counsel, the prevailing party shall be paid its attorneys’ fees and costs by the non-prevailing party.

Hindman began work on Boos’s house in July 2018. Boos paid Hindman

according to the contract and paid most of the originally estimated price by

April 2019. Over the course of the renovation, Boos requested several change

3 No. 83802-4-I/4

orders to the original plans. The change orders were not well documented and

Hindman did not request that the orders be requested or issued in writing. In lieu

of issuing written change orders, Hindman issued monthly invoices to Boos that

reflected work completed, including any work requested by change order.

Boos claimed they discovered in reviewing an invoice that Hindman had

significantly overcharged for the work. Boos also asserted that Hindman refused

to produce supporting receipts when asked about the invoice. According to

Boos, the parties decided in April 2019 that Hindman would not charge Boos

more than $58,415.27 for the work remaining.2 Hindman disputes that it agreed

to convert the contract into a “lump-sum project.” Boos moved back into the

house in June 2019 following a final inspection by the city of Bellingham.

Hindman subsequently issued an invoice in June for $87,590.68 and

another, final invoice in August for $5,332.22. Boos did not pay. In December

2019, Hindman filed a lien against the property with the Whatcom County

Auditor’s office for the money owed. Boos claimed that after the project ended,

they performed an accounting of all Hindman’s invoices and discovered

significant overcharges.

Discussions to resolve the payment dispute broke down in mid-2020 and

Hindman initiated a lawsuit in August 2020 to foreclose its lien, claiming breach

of contract, unjust enrichment, and seeking recovery in quantum meruit.

2 In support of this contention, Boos provided an e-mail to Hindman stating

as much. But Boos did not provide any response from Hindman confirming the arrangement and Hindman asserts that it at no time agreed to convert the parties’ contract to a “fixed price” contract.

4 No. 83802-4-I/5

Hindman claimed that Boos “strung [him] along for many months” and abruptly

ended negotiations. Boos denied all of Hindman’s claims.

Boos moved for summary judgment, asserting that Hindman’s claims were

time barred by the claims limitation period set out in the contract. The trial court

granted Boos’s motion as to the contract claim, but denied it as to the other

claims. Boos then moved for partial summary judgment to dismiss Hindman’s

equitable claims, which the trial court granted. Finally, Boos moved for summary

judgment to dismiss Hindman’s lien claim, asserting that it could not survive

without the contract claim. The court granted the motion. Several months later,

Boos moved for attorney fees and costs, which the court granted. Hindman

appeals.3

ANALYSIS

On appeal, Hindman assigns error to the trial court’s grant of summary

judgment as to Hindman’s contract claim, equitable claims, and lien foreclosure

claim. It also assigns error to the trial court’s attorney fees award. We conclude

that the trial court erred in granting summary judgment as to the contract claim,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartley v. State
698 P.2d 77 (Washington Supreme Court, 1985)
Palmer v. Jensen
913 P.2d 413 (Court of Appeals of Washington, 1996)
Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
Byrne v. Ackerlund
739 P.2d 1138 (Washington Supreme Court, 1987)
Hemenway v. Miller
807 P.2d 863 (Washington Supreme Court, 1991)
Dowler v. Clover Park School District No. 400
258 P.3d 676 (Washington Supreme Court, 2011)
Burton v. Twin Commander Aircraft LLC
254 P.3d 778 (Washington Supreme Court, 2011)
Hearst Communications v. Seattle Times Co.
115 P.3d 262 (Washington Supreme Court, 2005)
Geo Exchange Systems, LLC v. Cam
65 P.3d 11 (Court of Appeals of Washington, 2003)
Owen v. Burlington Northern and Santa Fe RR Co.
108 P.3d 1220 (Washington Supreme Court, 2005)
SD Deacon Corp. v. Gaston
206 P.3d 689 (Court of Appeals of Washington, 2009)
Colorado Structures v. Blue Mountain Plaza
246 P.3d 835 (Court of Appeals of Washington, 2011)
Young v. Young
191 P.3d 1258 (Washington Supreme Court, 2008)
Boguch v. Landover Corp.
224 P.3d 795 (Court of Appeals of Washington, 2009)
Chandler v. Washington Toll Bridge Authority
137 P.2d 97 (Washington Supreme Court, 1943)
Robert Boyd Et Al., Appellants, v. Sunflower Properties LLC, Respondent
197 Wash. App. 137 (Court of Appeals of Washington, 2016)
Kiona Park Estates, V. Avera Lee Dehls
491 P.3d 247 (Court of Appeals of Washington, 2021)
Adler v. Fred Lind Manor
103 P.3d 773 (Washington Supreme Court, 2004)
Owen v. Burlington Northern Santa Fe Railroad
153 Wash. 2d 780 (Washington Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Hindman Construction, Inc., V. Greg Boos, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hindman-construction-inc-v-greg-boos-washctapp-2023.