W.R.P. Lake Union Ltd. Partnership v. Exterior Services, Inc.

934 P.2d 722, 85 Wash. App. 744
CourtCourt of Appeals of Washington
DecidedApril 30, 1997
Docket37437-1-I
StatusPublished
Cited by38 cases

This text of 934 P.2d 722 (W.R.P. Lake Union Ltd. Partnership v. Exterior Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.R.P. Lake Union Ltd. Partnership v. Exterior Services, Inc., 934 P.2d 722, 85 Wash. App. 744 (Wash. Ct. App. 1997).

Opinion

Baker, C.J.

Exterior Services, Inc. (Exterior) asks us to determine whether a mechanics’ and materialmen’s lien should be released as frivolous and without reasonable cause in the summary proceeding created by RCW 60.04.081 1 based upon disputed assertions that Exterior *747 did not comply with two statutory prerequisites to lien filing. Because a summary proceeding is not intended to substitute for a trial and because an ultimate ruling against a lienor does not make a lien per se frivolous, we hold that the trial court erred in releasing this lien. Moreover, the record does not adequately set forth the trial court’s rationale for releasing the lien to allow appellate review. We therefore reverse the release of the lien and remand for its reinstatement.

Exterior also challenges the attorney fees award to W.R.P. Lake Union Limited Partnership (WRP). In light of our holding that the lien release was improper, we reverse the trial court’s fee award to WRP and remand for calculation of attorney fees for Exterior both below and on appeal.

FACTS

WRP is the owner and developer of a multi-use building, which includes parking, commercial space, and 20 residential units. WRP contracted with Western Exterior Siding Specialist (WESS) to provide and install siding, flashing, and downspouts at this building. The contract contained a clause prohibiting assignment of the contract without WRP’s express written approval.

When the contract was made, WESS was a sole proprietorship owned by Mark and Desiree Hodgson. Shortly thereafter, Hodgson incorporated, re-registered, and obtained a new bond under the name Exterior. Hodgson maintains that Exterior was the incorporated version of WESS, as evidenced by the fact that Exterior employed all of WESS’s employees. WESS notified WRP of the change by letter. WRP did not object to the change in ownership; however, WRP did not give WESS written approval of the assignment of the contract to Exterior.

WRP knew that Exterior was performing the work under the WESS contract, as evidenced by part of WRP’s *748 correspondence that was addressed to Exterior. WRP made four payments under the contract; however, those payments were made payable to WESS. The contract was then terminated based upon allegations of nonperformance.

Within 30 days, Exterior filed a lien for $26,608.38 plus costs and notified WRP of the lien. The lienor was identified as "Exterior Services, Inc. dba Western Exterior.” 2 Exterior did not give WRP a notice of a right to claim a lien or a notice to customer before filing the lien. 3

WRP claimed that the lien was frivolous because it contracted with WESS, not Exterior, and thus Exterior had to serve a notice of its right to claim a lien before filing the lien. WRP demanded that the lien be released, but Exterior refused.

WRP then obtained an order to show cause why the lien should not be released as frivolous and without reasonable cause. WRP argued that (1) WESS and Exterior were different entities, 4 (2) Exterior failed to provide the written notice of its right to claim a lien, which was required because WRP did not contract with Exterior or approve the contract assignment, (3) Exterior failed to provide a notice to customer, (4) Exterior would not be harmed by the release because it had other contractual rights, and (5) the lien was excessive.

Exterior responded that neither notice was required because (1) the change in ownership structure was not equivalent to an assignment, (2) the lien was primarily for labor costs, and (3) the project had more than four resi *749 dential units. Exterior also argued that WRP waived its objection to any assignment that may have occurred by not responding to Exterior’s letter regarding the change. Exterior also requested attorney fees.

At the hearing, WRP raised additional arguments that (1) notice to customer was required because Lake Union Terrace was a commercial building, (2) WRP’s correspondence and dealings were solely with WESS, and (3) WESS insured the project.

The trial court released the lien and awarded WRP attorney fees, without prejudice to any contractual rights. The order does not explain the court’s rationale for releasing the lien.

ANALYSIS

No appellate decision has yet analyzed the procedures to be followed under RCW 60.04.081. The interpretation and construction of a statute is a question of law that we review de novo. 5 In conducting such a review, we construe a statute according to its plain language and give effect to the legislative intent. 6

This statute creates a summary proceeding in which a property owner may quickly obtain the release of a lien that is frivolous and made without reasonable cause or is clearly excessive. 7 The moving party must provide the court with affidavits setting forth the facts supporting the lien’s release. 8 Following a hearing on the motion, the trial court determines whether the lien is frivolous and made without reasonable cause or is clearly excessive. 9

Exterior analogizes the procedure under this statute to a hearing on a motion for summary judgment and *750 argues that if the lienor raises a material issue of fact, the lien cannot be released. We disagree. The statutory procedure is more in the nature of a trial by affidavit. We believe the Legislature intended to allow a resolution of factual disputes in this summary proceeding. To the extent that the trial court’s ruling is based upon a resolution of factual disputes, we will review the ruling to determine whether the factual determinations are supported by substantial evidence, and whether the trial court has made an error of law that may be corrected on appeal. 10 When the record contains no clear resolution of factual disputes, we will accord the decision no deference and proceed with a de novo review in light of the applicable burden of proof. 11

The trial court here did not enter any findings of fact. Indeed, Exterior argues that the trial court erred by failing to enter an express finding that the lien was frivolous and without reasonable cause. Although the statute contains no requirement for entry of findings of fact and conclusions of law, their use would clearly be preferable for purposes of appellate review. At a minimum, the trial court’s reasoning for entering the order should be clearly set out in the order itself.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeffrey Riordan v. Matthew T. Vogt & April D. Vogt
Court of Appeals of Washington, 2026
Park South LLC v. Denali Construction LLC
Court of Appeals of Washington, 2024
Lennar Multifamily Builders, Llc, V. Saxum Stone, Llc
492 P.3d 175 (Court of Appeals of Washington, 2021)
Candace Noll v. Special Electric Co
Court of Appeals of Washington, 2020
Denise Brackett Woodley v. Style Corporation D/b/a
Court of Appeals of Washington, 2019
Granville Condominium Homeowners Ass'n v. Kuehner
312 P.3d 702 (Court of Appeals of Washington, 2013)
Williams v. ATHLETIC FIELD, INC.
261 P.3d 109 (Washington Supreme Court, 2011)
Gray v. Bourgette Construction, LLC
160 Wash. App. 334 (Court of Appeals of Washington, 2011)
J.D. Construction, Inc. v. IBEX International Group, LLC
240 P.3d 1033 (Nevada Supreme Court, 2010)
Williams v. Athletic Field, Inc.
228 P.3d 1297 (Court of Appeals of Washington, 2010)
SD Deacon Corp. v. Gaston
206 P.3d 689 (Court of Appeals of Washington, 2009)
S.D. Deacon Corp. v. Gaston Bros. Excavating
150 Wash. App. 87 (Court of Appeals of Washington, 2009)
City of Wenatchee v. Owens
145 Wash. App. 196 (Court of Appeals of Washington, 2008)
Quality Food Centers v. MARY JEWELL T, LLC
142 P.3d 206 (Court of Appeals of Washington, 2006)
Andries v. Covey
113 P.3d 483 (Court of Appeals of Washington, 2005)
Pacific Industries, Inc. v. Singh
86 P.3d 778 (Court of Appeals of Washington, 2003)
Geo Exchange Systems, LLC v. Cam
65 P.3d 11 (Court of Appeals of Washington, 2003)
Intermountain Elec., Inc. v. GAT BROS. CONST., INC.
62 P.3d 548 (Court of Appeals of Washington, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
934 P.2d 722, 85 Wash. App. 744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wrp-lake-union-ltd-partnership-v-exterior-services-inc-washctapp-1997.