David Shane Feekes & Megan L. Kriete-Feekes v. Triple M Construction, LLC

Court of Appeals of Washington·Decided July 21, 2026·No. 41176-1·Published

Opinion

FILED JULY 21, 2026 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

DAVID SHANE FEEKES and MEGAN ) No. 41176-1-III L. KRIETE-FEEKES, husband and wife, ) ) Appellants, ) ) v. ) PUBLISHED OPINION ) TRIPLE M CONSTRUCTION, LLC, a ) Washington limited liability company, ) ) Respondent. )

LAWRENCE-BERREY, J. — David Feekes and Megan Kriete-Feekes entered into

two contracts with Triple M Construction LLC for construction work on their residential

property. The Feekes terminated the contracts after partial performance. Triple M

recorded a claim of lien for unpaid work.

The Feekes then brought a motion under RCW 60.04.081 for Triple M to show

cause why its claim of lien should not be released as frivolous or reduced as clearly

excessive. The trial court denied the Feekes’ motion and awarded Triple M its No. 41176-1-III Feekes v. Triple M. Constr.

reasonable attorney fees and costs for prevailing. We affirm but deny Triple M its

reasonable attorney fees and costs on appeal.

FACTS1

The Feekes sought to have a pole building constructed on their property to serve as

their personal residence. Toward that goal, the Feekes entered into two contracts with

Triple M. “Contract #1055” was for Triple M to perform excavation work for

$27,405.98. Clerk’s Papers (CP) at 123-38. “Contract #1056” was for Triple M to

perform concrete work for $32,257.99. CP at 139-57.

The Feekes paid one-half of each contract as a down payment before Triple M

began work. The parties later agreed to a change order for Contract #1056, increasing the

contract price to $35,509.99.

After Triple M performed most excavation and some concrete work, Mr. Feekes

cancelled the contracts by sending Triple M a text message:

1 The parties dispute material facts, and the trial court’s order did not include findings on those disputed facts. Consistent with the notion that a claim of lien should not be dismissed unless it is clearly frivolous, we present the facts favorably for the party resisting dismissal of its lien, Triple M.

2 No. 41176-1-III Feekes v. Triple M. Constr.

Good day, at your convenience start working on an invoice for me to close the excavation portion of your bid please. I don’t know how to complete the concrete as I would be interested in your guys finish as far as they have gotten but I need to work with them directly if and however that is possible. I’m getting my plumbing and electrical needs planned now so I will be interested in a frame bid broken down starting on exterior with a start and finish date.

CP at 25.

Triple M sent the Feekes invoices for the remaining balances—$12,321.27 for the

excavation work and $328.23 for the concrete work. Because the Feekes refused to pay

either invoice, Triple M recorded a claim of lien for the total invoiced balances.

The Feekes filed a motion for Triple M to show cause why its claim of lien should

not be dismissed as frivolous or reduced as clearly excessive. The Feekes argued that

Triple M’s failure to provide them with the statutory “Notice to Customer”2 rendered its

claim of lien frivolous. The Feekes also argued that Triple M’s lien should be reduced

because (1) Triple M performed less than one-half of the contract work, (2) Triple M’s

work was deficient (in that it failed to place rebar in the footings and because the concrete

was cracking), and (3) they had paid Triple M far more than the value they received.

Triple M disputed these allegations, and the parties submitted dueling arguments

2 See RCW 18.27.114(1).

3 No. 41176-1-III Feekes v. Triple M. Constr.

regarding whether the Feekes acted as their own general contractor on the project, which

would render Triple M exempt from providing the statutory notice.

The trial court considered the parties’ arguments and determined (1) there were

debatable issues regarding whether Triple M’s claim of lien was frivolous, and (2) Triple

M’s claim of lien was not clearly excessive. In its oral ruling, the court observed:

Feekes hired Triple M to provide at least some of the work on the structure that they wished to build on their personal property. But at the time they did the initial contract, there was no contract for them to complete all of the work. That was talked about as a possibility, but it was not contracted at the beginning.

Rep. of Proc. at 49.

Based on the two above determinations, the trial court denied the Feekes’ motion

and awarded Triple M its reasonable attorney fees and costs.

The Feekes appeal to this court.

ANALYSIS

The Feekes argue the trial court erred by not dismissing Triple M’s claim of lien

as frivolous. Alternatively, they argue the trial court erred by not reducing it as clearly

excessive. We address each argument separately. But first, we discuss the appropriate

standard of review and the summary procedure for dismissing a claim of lien.

4 No. 41176-1-III Feekes v. Triple M. Constr.

Standard of review

When reviewing a trial court’s order granting or denying a release or reduction of

a claim of lien under RCW 60.04.081, we review its findings for substantial evidence and

its legal conclusions de novo. Intermountain Elec., Inc. v. G-A-T Bros. Constr., Inc.,

115 Wn. App. 384, 390-91, 62 P.3d 548 (2003). Here, the trial court did not enter any

findings on disputed factual issues. Thus, our review of the trial court’s order is de novo.

Summary procedure for dismissal of a claim of lien

RCW 60.04.021 authorizes a lien in the contract amount for those who furnish

labor, professional services, materials, or equipment for the improvement of real property

at the owner’s request. To perfect such a lien, a claimant must properly record a claim of

lien in accordance with RCW 60.04.091.

RCW 60.04.081 authorizes a narrow and limited summary proceeding to

determine if a claim of lien is frivolous and made without reasonable cause, or reduce it if

it is clearly excessive. Woodley v. Style Corp., 7 Wn. App. 2d 543, 551, 453 P.3d 739

(2019). A court must release the claim of lien if it is frivolous and made without

reasonable cause or reduce it if it is clearly excessive. Id.

5 No. 41176-1-III Feekes v. Triple M. Constr.

A. THE VIABILITY OF TRIPLE M’S CLAIM OF LIEN

Having described the standard of our review and the summary procedure, we now

address each of the Feekes’ two arguments.

1. Whether Triple M’s claim of lien was frivolous

“A lien is frivolous if it is ‘improperly filed beyond legitimate dispute’ and ‘so

devoid of merit that it has no possibility of succeeding.’” Id. at 551-52 (internal

quotation marks omitted) (quoting Williams v.

Free access — add to your briefcase to read the full text and ask questions with AI

David Shane Feekes & Megan L. Kriete-Feekes v. Triple M Construction, LLC, (Wash. Ct. App. 2026).

David Shane Feekes & Megan L. Kriete-Feekes v. Triple M Construction, LLC (David Shane Feekes & Megan L. Kriete-Feekes v. Triple M Construction, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

W.R.P. Lake Union Ltd. Partnership v. Exterior Services, Inc.
934 P.2d 722 (Court of Appeals of Washington, 1997)
Williams v. ATHLETIC FIELD, INC.
261 P.3d 109 (Washington Supreme Court, 2011)
Intermountain Elec., Inc. v. GAT BROS. CONST., INC.
62 P.3d 548 (Court of Appeals of Washington, 2003)
Wachovia SBA Lending, Inc. v. Kraft
200 P.3d 683 (Washington Supreme Court, 2009)
Pacific Northwest Shooting Park Ass'n v. City of Sequim
144 P.3d 276 (Washington Supreme Court, 2006)
Wachovia SBA Lending, Inc. v. Kraft
165 Wash. 2d 481 (Washington Supreme Court, 2009)
Intermountain Electric, Inc. v. G-A-T Bros. Construction, Inc.
115 Wash. App. 384 (Court of Appeals of Washington, 2003)