David Shane Feekes & Megan L. Kriete-Feekes v. Triple M Construction, LLC
Opinion
FILED
JULY 21, 2026
In the Office of the Clerk of Court WA State Court of Appeals, Division III
IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE
DAVID SHANE FEEKES and MEGAN ) No. 41176-1-III L. KRIETE-FEEKES, husband and wife, )
)
Appellants, )
)
v. ) PUBLISHED OPINION )
TRIPLE M CONSTRUCTION, LLC, a ) Washington limited liability company, )
)
Respondent. )
LAWRENCE-BERREY, J. — David Feekes and Megan Kriete-Feekes entered into two contracts with Triple M Construction LLC for construction work on their residential property. The Feekes terminated the contracts after partial performance. Triple M recorded a claim of lien for unpaid work.
The Feekes then brought a motion under RCW 60.04.081 for Triple M to show cause why its claim of lien should not be released as frivolous or reduced as clearly excessive. The trial court denied the Feekes’ motion and awarded Triple M its
Feekes v. Triple M. Constr.
reasonable attorney fees and costs for prevailing. We affirm but deny Triple M its reasonable attorney fees and costs on appeal.
FACTS1
The Feekes sought to have a pole building constructed on their property to serve as their personal residence. Toward that goal, the Feekes entered into two contracts with Triple M. “Contract #1055” was for Triple M to perform excavation work for $27,405.98. Clerk’s Papers (CP) at 123-38. “Contract #1056” was for Triple M to perform concrete work for $32,257.99. CP at 139-57.
The Feekes paid one-half of each contract as a down payment before Triple M began work. The parties later agreed to a change order for Contract #1056, increasing the contract price to $35,509.99.
After Triple M performed most excavation and some concrete work, Mr. Feekes cancelled the contracts by sending Triple M a text message:
1 The parties dispute material facts, and the trial court’s order did not include findings on those disputed facts. Consistent with the notion that a claim of lien should not be dismissed unless it is clearly frivolous, we present the facts favorably for the party resisting dismissal of its lien, Triple M.
Feekes v. Triple M. Constr.
Good day, at your convenience start working on an invoice for me to close the excavation portion of your bid please. I don’t know how to complete the concrete as I would be interested in your guys finish as far as they have gotten but I need to work with them directly if and however that is possible.
I’m getting my plumbing and electrical needs planned now so I will be interested in a frame bid broken down starting on exterior with a start and finish date.
CP at 25.
Triple M sent the Feekes invoices for the remaining balances—$12,321.27 for the excavation work and $328.23 for the concrete work. Because the Feekes refused to pay either invoice, Triple M recorded a claim of lien for the total invoiced balances.
The Feekes filed a motion for Triple M to show cause why its claim of lien should not be dismissed as frivolous or reduced as clearly excessive. The Feekes argued that Triple M’s failure to provide them with the statutory “Notice to Customer”2 rendered its claim of lien frivolous. The Feekes also argued that Triple M’s lien should be reduced because (1) Triple M performed less than one-half of the contract work, (2) Triple M’s work was deficient (in that it failed to place rebar in the footings and because the concrete was cracking), and (3) they had paid Triple M far more than the value they received. Triple M disputed these allegations, and the parties submitted dueling arguments
2 See RCW 18.27.114(1).
Feekes v. Triple M. Constr.
regarding whether the Feekes acted as their own general contractor on the project, which would render Triple M exempt from providing the statutory notice.
The trial court considered the parties’ arguments and determined (1) there were debatable issues regarding whether Triple M’s claim of lien was frivolous, and (2) Triple M’s claim of lien was not clearly excessive. In its oral ruling, the court observed:
Feekes hired Triple M to provide at least some of the work on the structure that they wished to build on their personal property. But at the time they did the initial contract, there was no contract for them to complete all of the work. That was talked about as a possibility, but it was not contracted at the beginning.
Rep. of Proc. at 49.
Based on the two above determinations, the trial court denied the Feekes’ motion and awarded Triple M its reasonable attorney fees and costs.
The Feekes appeal to this court.
ANALYSIS
The Feekes argue the trial court erred by not dismissing Triple M’s claim of lien as frivolous. Alternatively, they argue the trial court erred by not reducing it as clearly excessive. We address each argument separately. But first, we discuss the appropriate standard of review and the summary procedure for dismissing a claim of lien.
Feekes v. Triple M. Constr.
Standard of review When reviewing a trial court’s order granting or denying a release or reduction of a claim of lien under RCW 60.04.081, we review its findings for substantial evidence and its legal conclusions de novo. Intermountain Elec., Inc. v. G-A-T Bros. Constr., Inc., 115 Wn. App. 384, 390-91, 62 P.3d 548 (2003). Here, the trial court did not enter any findings on disputed factual issues. Thus, our review of the trial court’s order is de novo.
Summary procedure for dismissal of a claim of lien RCW 60.04.021 authorizes a lien in the contract amount for those who furnish labor, professional services, materials, or equipment for the improvement of real property at the owner’s request. To perfect such a lien, a claimant must properly record a claim of lien in accordance with RCW 60.04.091.
RCW 60.04.081 authorizes a narrow and limited summary proceeding to determine if a claim of lien is frivolous and made without reasonable cause, or reduce it if it is clearly excessive. Woodley v. Style Corp., 7 Wn. App. 2d 543, 551, 453 P.3d 739 (2019). A court must release the claim of lien if it is frivolous and made without reasonable cause or reduce it if it is clearly excessive. Id.
Feekes v. Triple M. Constr.
A. THE VIABILITY OF TRIPLE M’S CLAIM OF LIEN Having described the standard of our review and the summary procedure, we now address each of the Feekes’ two arguments.
1. Whether Triple M’s claim of lien was frivolous “A lien is frivolous if it is ‘improperly filed beyond legitimate dispute’ and ‘so devoid of merit that it has no possibility of succeeding.’” Id. at 551-52 (internal quotation marks omitted) (quoting Williams v. Athletic Field, Inc., 172 Wn.2d 683, 699, 261 P.3d 109 (2011)). This high standard exists to ensure that those claiming construction liens are not deprived of their right to a trial on a legitimate lien claim. Id. at 552. “Thus, a lien is not frivolous if it presents debatable issues of law and fact.” Id.
The Feekes argue that Triple M’s claim of lien meets the above frivolous standard because Triple M failed to provide them with the Notice to Customer as required by RCW 18.27.114(1). As explained below, we conclude that Triple M was not required to provide the statutory notice to the Feekes.
a. Triple M did not agree to build a residential unit RCW 18.27.114(1) requires a contractor, in certain situations, to provide its customer a statutory notice prior to starting work. The notice generally advises the customer how to protect themselves and their property from lien claims. Id. If the
Feekes v. Triple M. Constr.
situation requires the contractor to provide the notice and the notice is not given, the contractor is precluded from enforcing its lien. RCW 18.27.114(4).
RCW 18.27.114(1) requires a contractor to give a residential customer the statutory notice only if the contractor agrees to repair, alter, or construct “four or fewer residential units or accessory structures.” Here, Triple M did not agree to construct even one residential unit for the Feekes.3 We conclude that Triple M was not required to provide the statutory notice; therefore, its claim of lien was not frivolous.
Free access — add to your briefcase to read the full text and ask questions with AI
David Shane Feekes & Megan L. Kriete-Feekes v. Triple M Construction, LLC (David Shane Feekes & Megan L. Kriete-Feekes v. Triple M Construction, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.