Scott's Excavating Vancouver, LLC v. Winlock Properties, LLC

308 P.3d 791, 176 Wash. App. 335
Court of Appeals of Washington·Decided August 27, 2013·No. No. 42796-6-II·Published·Cited by 53 cases

Opinion

Johanson, J.

¶1 First-Citizens Bank & Trust Co. appeals a trial court’s order concluding that Gibbs & Olson Inc. (G&O) had lien priority over First-Citizens’ deed of trust and that G&O was entitled to foreclose its mechanics’ lien for engineering services provided for development of a 50-acre, 200-lot subdivision. First-Citizens argues that the trial court erroneously determined that (1) several contract amendments related back to the earlier contract between Winlock Properties LLC and G&O, (2) G&O’s mechanics’ lien had priority over First-Citizens’ deed of trust, (3) G&O reasonably mitigated its damages, and (4) First-Citizens was not entitled to an offset.

¶2 We hold that the trial court did not err because (1) substantial evidence supports the conclusion that the parties intended the 2005 contract and the five subsequent amendments to form a single contract, (2) the amendments related back to the initial 2005 contract and, therefore, G&O’s mechanics’ lien had priority over First-Citizens’ deed of trust, (3) under the circumstances, G&O acted reasonably in mitigation, and (4) First-Citizens is not entitled to an offset. Accordingly, we affirm. We also award attorney fees and costs to G&O as the prevailing party under RCW 60.04.181(3).

[339] FACTS

¶3 In February 2005, G&O sent a proposal to Winlock for engineering and surveying services on Winlock’s new housing and commercial development called the Grand Prairie subdivision.1 Winlock planned to turn its undeveloped 50-acre pasture land into a 200-lot subdivision. In July, the parties executed a contract based on the February proposal. The contract required G&O to provide preliminary design work for the entire 50-acre project. It also required G&O to help obtain government approval for the entire project and to provide final design work and other engineering work on portions of the project. Additionally, it contained contract estimates for the cost of completion of design work and a description of further engineering services necessary to complete the entire project, to be accomplished in five phases. The contract provision for future amendments stated:

Following completion of the Final Design Phase Services, and after receipt of written authorization from [Winlock], [G&O] shall prepare an amendment to this Agreement for completion of the construction phase and operational phase services. Upon approval of the amendment, [G&O] shall proceed with the work on this project.

Ex. 3, at 3. The contract price for G&O’s initial work was $112,000, and any costs exceeding that amount needed Winlock’s approval.

¶4 Prior to January 10, 2006, Winlock provided G&O’s engineering work to First-Citizens’ predecessor (Venture Bank) to support Winlock’s loan application. Thus, Venture had notice that G&O began work on the property before the $3.7 million loan from Venture was approved. On January 10, 2006, Venture secured the loan by recording a deed of [340] trust against the property. Venture did not obtain a subordination agreement from G&O that would have assured Venture’s first priority position for its deed of trust.

¶5 As the first phase progressed, Winlock and G&O revised the scope and cost of the work that G&O would perform. The revisions were memorialized in written “Amendments.” Exs. 4-10. In April 2006, the parties agreed to three such amendments. By June 2006, G&O completed the first phase of the development, and Winlock paid G&O in full for it.

¶6 In September 2006, the parties agreed to two more amendments. The first paragraph of each Amendment included the following language:

This Amendment revising the Scope of Work, Schedule, and Budget for Engineering Services is hereby attached to and made a part of the Agreement for Engineering Services dated July 22, 2005, between [Winlock] and [G&O]. This Amendment authorizes [G&O] to perform Construction . . . Services for [Winlock], as more fully described herein.

Ex. 5, at 1; Ex. 6; Ex. 7, at 2; Ex. 9; Ex. 10, at 1.

¶7 From July 2006 through January 2008, G&O continued performing its obligations under the amendments, but after October 2006, Winlock made only one more payment. Winlock assured G&O every few weeks that it was working on financing and that it would eventually pay G&O. Finally, on February 4, 2008, G&O stopped work for lack of payment. By that time, Winlock had failed to pay G&O $155,755.59, plus interest. On March 7, G&O recorded a lien claim in compliance with chapter 60.04 ROW for the unpaid amount. On July 18, G&O sued to foreclose the lien.

¶8 Winlock also defaulted on its loan with Venture, and Venture foreclosed on its deed of trust. On August 31, 2009, Venture filed its trustee’s deed and became the owner of the 50-acre parcel, except for lots 1, 2, 3, 7, and 18 and tract A [341] of phase one of the subdivision.2 In May 2010, Venture transferred its ownership to First-Citizens by filing a receiver’s deed. First-Citizens then substituted for Venture in G&O’s foreclosure lawsuit.

¶9 At a bench trial in September 2011, the primary issue before the court was whether G&O’s lien had priority under chapter 60.04 RCW over Venture’s recorded deed of trust. First-Citizens asserted affirmative defenses of laches, failure to mitigate, and statute of limitations. The trial court ruled that (1) there was a single contract between Winlock and G&O, (2) G&O’s mechanics’ lien had priority over First-Citizens’ deed of trust, (3) G&O reasonably mitigated its damages, and (4) First-Citizens was not entitled to an offset. First-Citizens appeals.

ANALYSIS

¶10 First-Citizens assigns error to several of the trial court’s findings of fact and conclusions of law. We conclude that First-Citizens’ claims fail.

I. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Scott's Excavating Vancouver, LLC v. Winlock Properties, LLC, 308 P.3d 791, 176 Wash. App. 335 (Wash. Ct. App. 2013).

308 P.3d 791 (Scott's Excavating Vancouver, LLC v. Winlock Properties, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re The Estate Of Joan Lanzner
Court of Appeals of Washington, 2026
B&b Welding, Inc., V. Scarsella Bros., Inc.
Court of Appeals of Washington, 2025
Sandra Bain v. Zachary Stidman
Court of Appeals of Washington, 2025
Mark Matthews v. Terrance Williams
Court of Appeals of Washington, 2025
Estate Of Dean Roy Lacy
Court of Appeals of Washington, 2025
Elizabeth Settles, V. Dustin Gnewuch And Jamie Gnewuch
Court of Appeals of Washington, 2023
Cheryl & Terry Staley, V. Lynette Hoffman
Court of Appeals of Washington, 2022
Penny Arneson, V. Gary Nordlund
Court of Appeals of Washington, 2022
Avanti Markets, Inc., Et Ano., V. Happay, Inc.
Court of Appeals of Washington, 2021
Katherine Fray Obo E.f., V. Z.c.
Court of Appeals of Washington, 2021
Steven M. Crosetti v. Alexander Pawloff
Court of Appeals of Washington, 2021
Natasha Powell v. Tomasz Fraczek
Court of Appeals of Washington, 2021