School Town of Winamac v. Hess

50 N.E. 81, 151 Ind. 229, 1898 Ind. LEXIS 83
CourtIndiana Supreme Court
DecidedApril 22, 1898
DocketNo. 18,307
StatusPublished
Cited by7 cases

This text of 50 N.E. 81 (School Town of Winamac v. Hess) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School Town of Winamac v. Hess, 50 N.E. 81, 151 Ind. 229, 1898 Ind. LEXIS 83 (Ind. 1898).

Opinion

McCabe, J.

The appellant sued the appellees Hess and Myers as principals, and Gilmore and Cor-bin as sureties, on a bond executed by them to appellant on May 26, 1892, conditioned that Hess and Myers should, as contractors, construct a school building in the town of Winamac for $16,896.60, in all respects according to and in compliance with the terms, stipulations, and specifications of a contract executed by them on the same day to appellant. The defendants Hess and Myers, filed a cross-copaplaint, seeking to recover a judgment against the plaintiff. A trial of the issues resulted in a special finding of [230]*230the facts,, upon which the court stated conclusions of law favorable to the appellees, upon which the court rendered judgment, in effect, that the plaintiff take nothing by its suit, and that the defendants, Hess and Myers, recover judgment, against the plaintiff on their cross-complaint for $1,182.27.

The substance of the facts found is that in March, 1892, the only schoolhouse in Winamac was destroyed by fire, and it became necessary to construct a new one to provide common schools for the 400 children of school age residing in said town. The town owned a suitable tract of ground within said town for such a building, and the school trustees procured plans and specifications for a school building of suitable size at a probable cost of $19,000.00. The school town then asked the town to issue and sell bonds to the amount of $15,000.00, and turn the proceeds over to the school town, to be used in the proposed building. The proper steps were taken, and the order made for the issue 'of such bonds in April, 1892; and on May 26, 1892, appellant and appellees Hess and Myers, entered into a written contract, by which said appellees bound themselves to furnish the material and construct the building on said piece of ground according to the plans and specifications, for which appellant was to pay them $16,896.60. This written contract is set out in full in the special findings.., On the same day the contractors as principals, and appellees, Gilmore and Corbin as sureties, executed to appellant a bond in the penalty of $10,000.00, conditioned for the faithful performance of the building contract. This bond, also, is set out in full in the findings. Among other things, it was stipulated in the building contract that the contractors should begin work at once, gnd should complete said building on or before November 1, 1892, and if they failed to [231]*231prosecute the work with diligence the appellant might terminate the contract, take charge of and complete the building, and should the cost of so completing the building exceed the amount due the contractors at the contract price, the contractors should pay to appellant the difference. It was also stipulated therein that the contractors, among other things, should pay $10.00 per day for each day the building remained unfinished after the 1st day of November, 1892. The contractors began work at once, and continued at work until October 18, 1892, and then refused to proceed further with the' work; The architect, as the contract authorized him to do, certified to the trustees of appellant that this was a sufficient excuse for the termination of the building contract. The trustees then notified the sureties upon the bond, as the contract authorized and required them to do, of the failure on the part of the contractors, and that if the work was not resumed, the appellant would terminate the contract, enfploy other workmen, and complete the building. The bondsmen refused to complete the work, and thereupon the employment of the appellees as contractors was terminated by the appellant, and it took charge of the work, and completed it according to the contract. This contract provided that appellant should pay the contractors at stated periods, as follows: At the end of each three weeks, or thereabouts, the architect should make an estimate and certify to the school board the amount of work completed, and thereupon the school town should pay to the said Myers and Hess the amount of said estimate, less fifteen per cent, thereof. It further provided that, in case of the termination of the contract by the appellant, it should take possession of any unused material on the premises, and thereafter the contractors [232]*232should not be entitled to any further payment until the work should be wholly finished, and if thereupon the unpaid balance of the contract price should exceed the expense incurred by appellant in finishing the work, no further payment should be made to the contractors, and in case such unpaid balance did exceed such expense, such excess should be paid to the contractors by appellant; that while Myers and Hess were at work upon said building, the architect from time to time made estimates in writing of the work and material furnished by them, delivered said estimates to appellant, and gave a copy thereof to said Hess and Myers, and upon presentation of said copy to appellant’s trustees, they paid to Hess and Myers the amount of each estimate, less ten per cent, thereof, the dates and amounts of which estimates, and time of payment thereof is as follows: The first estimate June 22, 1892, for $1,211,22, paid $1,090.10; second, July 13, 1892, for $1,055.23, paid $947.71; third, August 8, 1892, for $565.50, paid $508.95; fourth, September 1, 1892, for $551.50, paid $496.35; fifth, September 20, 1892, for $833.00, paid $749.70; sixth, October 12,1892, for $916.00, paid $824.40. Making the total estimates $5,132.46, and the total payments $4,619.21. That after the board of trustees of the civil town had ordered the issue and sale of the $15,000.00 of bonds already mentioned, a taxpayer of said town began suit in the circuit court of the county to enjoin the issue and sale of said bonds, after the oi^der had been made but before their issue, on the ground that the issue and sale of that amount of bonds would exceed the constitutional limit of two per cent, of the taxable property of said incorporated town. A perpetual injunction was awarded by the circuit court, which judgment on appeal to this court was affirmed. Town of Winamac v. Huddletson, 132 [233]*233Ind. 217. That the-assessed valuation of all the property within the town of Winamac for the year 1891 was $336,000.00. At the time of the contract there were bonds of said town outstanding and unpaid amounting to $2,700.00, the proceeds of which had gone into the school building previously destroyed by fire. And appellant, at’said date of May 26, 1892, was further indebted upon school orders aggregating $149.54. The salary of its trustees for the year ending June 1, 1892, aggregating $90.00 was unpaid.

It had a contract with Joseph E. Mills by which it was to pay him for preparing plans and overseeing the work the sum of $700.00, to be paid, $200.00 when the contract was let, $200.00 when the brick walls were up, $200.00 when the building was plastered, and $100.00 when the buildingwas complete. And neitherthe town of Winamac nor the school town was otherwise indebted. On the day of the execution of the contract and bond aforesaid, the school town of Winamac had on hands, cash belonging to its special school fund, for use in the construction of a public school building, the ¡sum of $4,800.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlantic Bitulithic Co. v. Town of Edgewood
87 S.E. 183 (West Virginia Supreme Court, 1915)
Southern Railway Co. v. Bretz
104 N.E. 19 (Indiana Supreme Court, 1914)
Jordan v. City of Logansport
99 N.E. 1060 (Indiana Supreme Court, 1912)
Caldwell v. Bauer
99 N.E. 117 (Indiana Supreme Court, 1912)
McGillivray v. Joint School District No. 1
58 L.R.A. 100 (Wisconsin Supreme Court, 1901)
Herman v. City of Oconto
86 N.W. 681 (Wisconsin Supreme Court, 1901)
Cason v. City of Lebanon
55 N.E. 768 (Indiana Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
50 N.E. 81, 151 Ind. 229, 1898 Ind. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-town-of-winamac-v-hess-ind-1898.