Cason v. City of Lebanon

55 N.E. 768, 153 Ind. 567, 1899 Ind. LEXIS 84
CourtIndiana Supreme Court
DecidedDecember 13, 1899
DocketNo. 18,480
StatusPublished
Cited by28 cases

This text of 55 N.E. 768 (Cason v. City of Lebanon) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cason v. City of Lebanon, 55 N.E. 768, 153 Ind. 567, 1899 Ind. LEXIS 84 (Ind. 1899).

Opinion

Monks, J.

This action was brought by appellant, a resident and taxpayer of the city of Lebanon, to enjoin said city from letting a contract for the improvement of a street in said city. Afterwards supplemental complaints were filed making additional parties defendant. Each of the appellees filed a demurrer for want of facts to the complaint and the same were sustained, and appellant refusing to plead further judgment was rendered against him on demurrer.

The assignment of errors calls in question the action of the court in sustaining each of said demurrers.

Omitting the formal parts of the complaint, it is averred that the tracks of the appellee, “the Chicago and Southeastern Railway Co., occupy the center of east Railroad street, along the full length thereof, and the same is used by the railroad company as a part of its line of railroad; that before said railroad was constructed on said street, said street had been improved by grading and graveling, according to the general plan of street improvement in said city; that said .railroad was located on said street, and said railroad grade established,, and said street cut down and excavated by the Anderson, [569]*569-Lebanon & St. Louis Railroad Company, the first owners of said railroad property; that said railroad company was allowed and permitted by the town, now city, of Lebanon, and the owners of property abutting on said street, so to locate said railroad tracks and make said grade and cut down and'excavate said street, upon the express agreement and consideration that said railroad company should, and would, regrade and gravel said street, and plaee the same in good condition and keep the same in good repair; that the track was constructed by the Midland Railway Company, a subsequent owner, which company also agreed to carry out the contract of the first owner; that the appellee, the Chicago & Southeastern Railway Company, one of the appellees herein, is now the owner of said railroad property, and that it assumed all the agreements, liabilities, debts, and legal obligations of said former railroad companies, and thereby assumed and agreed to improve said street by regrading and graveling the same according to the general plans for street improvement in said city; that said railroad companies have each and all failed and neglected to improve and repair said street; that the common council of the city of Lebanon, over the remonstrance of more than two-thirds of the property owners abutting on said street, without authority of law, entered into a pretended agreement with the Chicago & Southeastern Railway Company for the improvement of said street at the cost and expense of the property owners and city, releasing said railroad company from its obligations to improve said street and keep the same in repair at its own cost; that to carry into effect said agreement the common council of said city, on the 26th day of April, 1897, without any petition, passed a resolution for the partial improvement of said street, assuming to proceed under an act of the General Assembly of March 8, 1889, by paving with brick a strip thirteen feet wide on each side of the space occupied by the railroad track; also by constructing cement sidewalks on each side of said street, five feet in width, for the full length of the improvement; the [570]*570property abutting on said street to be assessed for said improvement, except part occupied by street and alley crossings, the cost of which was to be paid by the city. That after-wards on the 14th day of June, 1897, to further carry out said agreement, with said railroad company for the improvement of said street, the common council passed an ordinance for the improvement of said street in accordance with said resolution; that at the time of passing said special ordinance the common council and the railroad company entered into a pretended contract which provided that, in consideration that the city of Lebanon pave said street with brick on each side of the railroad track to a width not less than thirteen feet, and otherwise improve said street, and bind the contractor doing the improvement of said street and sidewalk to ship all material for the improvement over said railroad, provided rates were equal (the railroad to furnish the gravel, and transport it to a suitable point to unload on said street, at sixty cents per cubic yard), and pay said railroad company ten-cents per cubic yard for loading the same. The railroad company was to improve said street by placing under its tracks new ties, good gravel under the same, and plank on inside and outside of its rails throughout the entire length of said street, and otherwise improve between its tracks by filling in with gravel and tamping same. This contract was executed June 4, 1897. That, in pursuance to said resolution and special ordinance and agreement with the railroad company, said city gave notice to contractors to let the improvement of the street on the 12th day of July, 1897, at 7:30 o’clock, p. m. That to improve said street according to the plans and specifications, the city will incur a debt on account of street and alley crossings of about $1,500 which, it is alleged, is in violation of the Constitution of this State.” After setting out the value of the taxable property within said city, and the amount of the indebtedness, it is averred “that the indebtedness of said city exceeds two per centum of all the taxable property, and that the taxes and income of [571]*571said year hare already been anticipated; that the city cannot pay cash for said improvement, for it has not and will not have the money; that said improvement will not increase the value of the property on said street to the amount of the assessment to pay for such improvement; that said proposed improvement is not in accordance with the general plan of improvement in said city, and is not and will not be of public utility.”

On the 17th day of July, 1897, the appellant filed a supplemental complaint. It is shown in this complaint that since the filing of the original complaint the common council of the city of Lebanon, in pursuance to special ordinance and notice, as in said complaint alleged, let the contract for the improvement of said street to C. G. Wills & Co., composed of Charles G. Wills, William A. Gray, and Thomas W. Huckstep, alleging that said Iluckstep and one David M. Burnes are partners, and work and have an office together in the business of civil engineering; that Iluckstep is a son-in-law of Burnes; that as such civil engineers they are in the employ of said city as the deputies of one Enoch James; that Iluckstep and Burnes made the plans and specifications for the improvement of said street; that Burnes is to superintend the work, make the estimates and accept the same upon the part of the city. After stating the cost of the improvement, it is alleged that the bid and contract price for making said improvement is far in excess of the cost and expense of making the same; that said C. G. Wills & Co., have not commenced to construct said improvement but are about to enter upon said work, and that they are necessary parties; then follows the prayer for relief.

On September 14, 1897, the appellant, Samuel L. Cason, filed his additional supplemental complaint, setting up additional facts relating to the matters in controversy, to some extent restating matters contained in the complaint ánd first supplemental complaint, and charging that the work was not being done according to the contract, and that the materials [572]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town Council of New Harmony v. Parker
726 N.E.2d 1217 (Indiana Supreme Court, 2000)
Town of Syracuse v. Abbs
694 N.E.2d 284 (Indiana Court of Appeals, 1998)
City of Hammond v. Northern Indiana Public Service Co.
506 N.E.2d 49 (Indiana Court of Appeals, 1987)
Book v. Indianapolis-Marion Bldg. Authority
126 N.E.2d 5 (Indiana Supreme Court, 1955)
Heffernen v. City of Green Bay
64 N.W.2d 216 (Wisconsin Supreme Court, 1954)
Edward E. Gillen Co. v. City of Milwaukee
183 N.W. 679 (Wisconsin Supreme Court, 1921)
South Park Floral Co. v. City of Newcastle
113 N.E. 5 (Indiana Supreme Court, 1916)
Town of Sheridan v. Rothschild
104 N.E. 66 (Indiana Supreme Court, 1914)
Caldwell v. Bauer
99 N.E. 117 (Indiana Supreme Court, 1912)
Southern Indiana Railway Co. v. Railroad Commission
87 N.E. 966 (Indiana Supreme Court, 1909)
Martindale v. Town of Rochester
86 N.E. 321 (Indiana Supreme Court, 1908)
Jordan v. City of Logansport
86 N.E. 47 (Indiana Supreme Court, 1908)
City of Logansport v. Jordan
85 N.E. 959 (Indiana Supreme Court, 1908)
Menzie v. City of Greensburg
85 N.E. 484 (Indiana Court of Appeals, 1908)
Duniway v. Portland
81 P. 945 (Oregon Supreme Court, 1905)
Giles v. Dennison
1904 OK 95 (Supreme Court of Oklahoma, 1904)
Hall v. Breyfogle
70 N.E. 883 (Indiana Supreme Court, 1904)
Brown v. Central Bermudez Co.
69 N.E. 150 (Indiana Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
55 N.E. 768, 153 Ind. 567, 1899 Ind. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cason-v-city-of-lebanon-ind-1899.