S.A. Healy Company v. Milwaukee Metropolitan Sewerage District

50 F.3d 476, 42 Fed. R. Serv. 90, 1995 U.S. App. LEXIS 5969, 1995 WL 122140
CourtCourt of Appeals for the Seventh Circuit
DecidedMarch 23, 1995
Docket94-3038
StatusPublished
Cited by32 cases

This text of 50 F.3d 476 (S.A. Healy Company v. Milwaukee Metropolitan Sewerage District) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.A. Healy Company v. Milwaukee Metropolitan Sewerage District, 50 F.3d 476, 42 Fed. R. Serv. 90, 1995 U.S. App. LEXIS 5969, 1995 WL 122140 (7th Cir. 1995).

Opinion

POSNER, Chief Judge.

Milwaukee’s sewage authority made a contract with the Healy company for the construction of a vertical shaft 300 feet deep and 13 feet in diameter to carry liquid wastes to storage and treatment facilities. The contract price was in excess of $8.8 million. The contract itself is 2,306 pages long—which demonstrates that detail alone cannot be counted on to prevent disputes. Healy encountered unexpected difficulties in the construction of the dropshaft as a result of a heavy flow of groundwater into the underground work site. These difficulties increased the cost of construction and led Healy to seek an adjustment in the contract price. When that was refused, Healy sued the sewage authority for breach of contract. A jury awarded Healy damages in excess of $1.5 million, inciting this appeal. Wisconsin law controls the substantive issues—though not for the reason given by the appellant, that “a federal court sitting in diversity must apply the substantive law of the forum state.” As we tirelessly remind litigants, a federal court sitting in diversity must first apply the forum state’s choice of law rules, Klaxon Co. v. Stentor Electric Mfg. Co., 313 U.S. 487, 61 S.Ct. 1020, 85 L.Ed. 1477 (1941); Rice v. Nova Biomedical Corp., 38 F.3d 909, 915 (7th Cir.1994); Wood v. Mid-Valley Inc., 942 F.2d 425, 426 (7th Cir.1991), which may or may not select the forum state’s substantive law to govern the dispute. No matter. The contract provides that the law of Wisconsin shall govern disputes arising under it, and Wisconsin enforces such choice-of-law agreements. First Wisconsin National Bank v. Nicolaou, 85 Wis.2d 393, 270 N.W.2d 582, 584 n. 1 (App.1978).

Inflow of groundwater was recognized from the beginning as a potentially serious impediment to the construction of the shaft. One way of controlling such inflow is by means of “consolidation grouting.” Holes are drilled into the ground surrounding the site of the shaft. A mixture of cement and water is poured into the holes under pressure. The mixture seeps into the rock formations surrounding the site and seals gaps in them through which groundwater might flow into the shaft. The contract required the contractor, Healy, to perform consolidation grouting and to construct several pumping test wells, shallower and smaller-bored than the shaft itself, to determine the adequacy of the grouting. The contract recites that “after completion of grouting from the surface, the total quantity of groundwater pumped from each drop shaft pumping test well shall not exceed 25 gpm [gallons per minute].... [I]f the pumping tests do not meet the above criteria, additional grouting may be directed by the Engineer [hired by the sewage authority to monitor the contractor’s performance] followed by additional pumping tests.” Not until the engineer determined that the grouting was adequate could Healy begin excavating for the drop shaft. The expense of this pre-excavation grouting was to be borne by the sewage authority, rather than being folded into the overall contract price.

The pumping test wells were built, some grouting was done, and tests were conducted. The amount of groundwater exceeded 25 gpm in the tests, so the sewage authority’s engineer directed Healy to do more grouting, which it did, at the sewage authority’s expense. Additional tests were then conducted, and showed that the amount of groundwater had fallen to 19 gpm. The engineer therefore authorized Healy to begin excavating. Healy soon encountered inflows of groundwater that exceeded 25 gpm, and the excess groundwater slowed the project and increased Healy’s costs. Healy asked the sewage authority for relief under the clause of the contract entitled “Differing Site Condition,” which so far as relevant to this case *479 entitles the contractor to a price adjustment on the basis of “subsurface or latent physical conditions at the site differing materially from those indicated in this Contract.” (This is a standard clause in government construction contracts. See, e.g., Iacobelli Construction, Inc. v. County of Monroe, 32 F.3d 19, 23-24 (2d Cir.1994); Granite-Groves v. Washington Metropolitan Area Transit Authority, 845 F.2d 330, 332 n. 3 (D.C.Cir.1988); Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1580 (Fed.Cir.1987); Youngdale & Sons Construction Co. v. United States, 27 Fed.Cl. 516, 528 (1993).) Healy’s position, which the jury accepted, is that the contract “indicated” 25 gpm to be the maximum inflow of groundwater that Healy should expect to encounter, so that anything significantly above that level would “differ materially” from the contractual indication and entitle Healy to the adjustment. Healy based this interpretation not only on the language of the contract but also on testimony as to what the parties had said in the negotiations that led up to the signing of the contract.

The sewage authority advances a number of grounds for reversal. The most fundamental is that the contract is unambiguous, so that its meaning should not have been submitted to the jury and extrinsic evidence should not have been admitted to illuminate that meaning. The contract, which contains the usual integration clause stating that it is the entire agreement between the parties, provides that the contractor “shall be solely responsible for all construction means, methods, techniques, and procedures.” This means, argues the sewage authority, that if Healy encountered unexpected impediments to construction it bore the full responsibility for surmounting them except insofar as the “Differing Site Condition” clause might entitle it to relief. But the clause is inapplicable, the authority argues, because nowhere does the contract “indicate” that Healy should not expect to encounter more than 25 gpm of groundwater inflow. That number refers solely to the pumping test wells. Once the wells passed the 25 gpm groundwater test, Healy was obliged to go forward with the excavation and became responsible for coping at its own expense with any excess groundwater that it encountered.

This is a possible reading of the contract but it is not so inevitable as to justify withdrawing the issue of meaning from the jury or depriving the jury of testimony about what the negotiators thought. We do not understand the sewage authority to disagree with the proposition that inflows of groundwater can greatly increase the cost of excavating an underground shaft. Since it was a fixed-price contract, the contractor would naturally be anxious about the possibility of encountering unexpectedly large groundwater inflows during the course of construction; and since the construction was underground, the contractor could not determine the volume of groundwater by simple inspection before beginning to excavate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Earls, Barry v. Menard, Inc.
W.D. Wisconsin, 2020
Dean Buchanan v. Jerry Gray
Court of Appeals of Washington, 2017
Loparex, LLC v. MPI Release Technologies, LLC
964 N.E.2d 806 (Indiana Supreme Court, 2012)
ZIMMER, INC. v. Sharpe
651 F. Supp. 2d 840 (N.D. Indiana, 2009)
Carolina Casualty Insurance v. Estate of Studer
555 F. Supp. 2d 972 (S.D. Indiana, 2008)
Armstrong v. HRB Royalty, Inc.
392 F. Supp. 2d 1302 (S.D. Alabama, 2005)
Shannon L. Haslund v. Simon Property Group, Inc.
378 F.3d 653 (Seventh Circuit, 2004)
Swierczynski v. Arnold Foods Co., Inc.
265 F. Supp. 2d 802 (E.D. Michigan, 2003)
United States v. Nekis Atwater
272 F.3d 511 (Seventh Circuit, 2001)
United States v. Atwater, Nekis
Seventh Circuit, 2001
Clay v. American Tobacco Co.
188 F.R.D. 483 (S.D. Illinois, 1999)
Meyer v. Buderus Hydronic Sys
D. New Hampshire, 1999
Johnson v. Land O' Lakes, Inc.
181 F.R.D. 388 (N.D. Iowa, 1998)
Pmc, Inc. v. Sherwin-Williams Company
151 F.3d 610 (Seventh Circuit, 1998)
Kuehn v. Childrens Hospital
119 F.3d 1296 (Seventh Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
50 F.3d 476, 42 Fed. R. Serv. 90, 1995 U.S. App. LEXIS 5969, 1995 WL 122140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sa-healy-company-v-milwaukee-metropolitan-sewerage-district-ca7-1995.