Rubin v. Pioneer Federal Savings & Loan Ass'n

334 N.W.2d 424, 214 Neb. 364, 1983 Neb. LEXIS 1110
CourtNebraska Supreme Court
DecidedMay 20, 1983
Docket82-040
StatusPublished
Cited by6 cases

This text of 334 N.W.2d 424 (Rubin v. Pioneer Federal Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rubin v. Pioneer Federal Savings & Loan Ass'n, 334 N.W.2d 424, 214 Neb. 364, 1983 Neb. LEXIS 1110 (Neb. 1983).

Opinion

Per Curiam.

The appellant, Pioneer Federal Savings & Loan Association (Pioneer), appeals from a jury verdict in the amount of $45,025.71 entered in favor of the appellee, Abner Rubin, and against Pioneer. The action was originally commenced by Rubin in the District Court for Douglas County, Nebraska, against Pioneer, seeking to recover damages allegedly sustained by Rubin as a result of Pioneer’s breach of a contract to lend Rubin money.

The evidence discloses that Rubin and the managing officer and executive vice president and treasurer of Pioneer began negotiating the terms of a *365 takeout loan in February or March of 1980. After obtaining authorization from Pioneer’s board, a commitment letter was prepared. The letter committed Pioneer to loan Rubin $400,000. The loan was to be secured by a first mortgage on an apartment complex to be constructed by Rubin. The commitment was subject to certain conditions, including that the complex, when constructed, would have an appraised value of at least $850,000. Pioneer committed to an interest rate of 14.50 percent, but provided that the rate was to be valid only for a 6-month period beginning March 3, 1980, and ending September 3, 1980. A further provision of the commitment was that the specific improvements, consisting of 40 units, must be substantially completed prior to executing the permanent mortgage. The letter defines “substantially completed” to be 90 percent or more. Specifically, the letter provided in part: “The percentage of completion shall be designated after inspection by Association personnel and the percentage of completion shall be determined by Association personnel at the time it is called for.” The letter further provided that the interest rate of 14.50 percent was dependent upon the improvements being 90-percent or more completed within the 6-month time frame. In the event that that condition was not met, then the interest rate was to be adjusted in accordance with a formula contained in the letter. On March 5, 1980, Rubin paid to Pioneer a $4,000 commitment fee and proceeded with the construction of the apartment complex. His next reported contact with Pioneer occurred in the latter part of August 1980, when he had a conversation with Pioneer’s secretary. The evidence is in conflict as to exactly what was discussed at that time. According to Rubin, he informed the secretary that the project was 90-percent completed and offered to drive her or someone else from Pioneer to Omaha for an inspection on September 3, 1980. He testified that she called him back a few days later and of *366 fered to waive inspection and “take his word for it.” They then discussed closing the loan after the first of the year. However, the secretary testified that only the closing date was discussed at that time and that she “didn’t remember” discussing the inspection.

Sometime in early December of 1980 Rubin hired a licensed real estate appraiser to inspect the property. As a result of the inspection, Rubin obtained a written appraisal of the property, in the amount of $1.4 million. Rubin forwarded this appraisal to Pioneer. Shortly thereafter, Rubin had an attorney draft a letter to Pioneer, advising that he was ready to close the loan and requesting Pioneer to furnish the necessary documents and schedule the closing date within 10 days. Rubin received no response from Pioneer until February of 1981. In a letter dated February 7, 1981, Pioneer informed Rubin that the loan was ready to close and that, in accordance with the commitment letter, the interest rate would not be 14.50 percent but, rather, 2 percent above the 10-year fixed-rate advance rate from the federal home loan bank. Based on the current quote, Pioneer predicted the rate to be 15.625 percent. In response to that letter Rubin filed suit.

In his petition Rubin alleged that he had a valid and binding commitment from Pioneer; that he had performed and fulfilled all of the conditions required of him to be performed pursuant to the commitment letter, and he was therefore entitled,to the loan in accordance with the commitment letter at an interest rate of 14.50 percent; that Pioneer refused to perform the agreement after formal demand was made; and that, by reason of Pioneer’s breach, Rubin was compelled to seek other financing “at a substantially higher cost than that provided by the commitment.” Rubin prayed for general damages and the return of $4,000, representing his commitment fee, plus interest and costs.

At trial both parties introduced considerable evidence on the question of whether the project was *367 substantially completed by September 3, 1980. Over Pioneer’s objection, the court instructed the jury that Pioneer had failed to inspect the complex prior to that date and thus voluntarily waived its right to make such inspection.

The trial court instructed the jury, in instruction No. 6, in part as follows: “The burden is on the defendant to prove by a preponderance of the evidence that the 40-apartment complex was less than 90% complete on September 3, 1980. If the defendant has proved the foregoing proposition by a preponderance of the evidence, your verdict will be for the defendant. ’ ’

The court further instructed the jury, in instruction No. 14, in part as follows: “The measure of damages in such event would be the difference between that amount which the plaintiff would be required to pay at 14.5% interest on a $400,000.00 loan for the duration of the loan and what he would be required to repay at an interest rate of 15.625% over the duration of the loan.”

And, finally, the court instructed the jury, in instruction No. 15, in part as follows: “The sum of $4,000.00 must be added to the present cash value of the plaintiff’s damages.” Apparently, it was the court’s view that if the jury found for the plaintiff in any amount, it was required to award the commitment fee to the plaintiff, in addition to his damages.

Pioneer has assigned three errors. They are: (1) The trial court erred in instructing the jury that Pioneer had the burden of proving that the complex was less than 90-percent complete on September 3, 1980, and Rubin’s noncompliance with that condition of the agreement. (2) The trial court erred in not instructing the jury on the proper measure of damages. (3) The evidence was insufficient to support the verdict.

We shall take up the errors in the order in which they have been assigned. Pioneer’s contention that the trial court erred in instructing the jury that *368 Pioneer had the burden of proving that the complex was less than 90-percent complete on September 3, 1980, is correct. Under the terms of the commitment, Pioneer agreed to loan Rubin $400,000 at an interest rate to be determined when the project was substantially completed. Substantially completed was to mean more than 90-percent completed. If this event occurred within the specified 6-month period ending on September 3, 1980, the loan would be made at 14.50 percent. If the project had not reached that stage of completion by that date, the interest rate would then be adjusted upward in accordance with a formula set out in the letter.

Further, Rubin, in his petition, alleged that he had performed all of the conditions required by him to be performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nebraska Nutrients, Inc. v. Shepherd
626 N.W.2d 472 (Nebraska Supreme Court, 2001)
Poppen v. Residential Mortgage Services, Inc.
556 N.W.2d 49 (Nebraska Court of Appeals, 1996)
Rayman v. American Charter Federal Savings & Loan
75 F.3d 349 (Eighth Circuit, 1996)
Hoeft v. Five Points Bank
539 N.W.2d 637 (Nebraska Supreme Court, 1995)
Coppi v. West American Insurance
524 N.W.2d 804 (Nebraska Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
334 N.W.2d 424, 214 Neb. 364, 1983 Neb. LEXIS 1110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rubin-v-pioneer-federal-savings-loan-assn-neb-1983.