Pipkin v. Thomas & Hill, Inc.

258 S.E.2d 778, 298 N.C. 278, 4 A.L.R. 4th 667, 1979 N.C. LEXIS 1373
CourtSupreme Court of North Carolina
DecidedOctober 17, 1979
Docket104
StatusPublished
Cited by19 cases

This text of 258 S.E.2d 778 (Pipkin v. Thomas & Hill, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pipkin v. Thomas & Hill, Inc., 258 S.E.2d 778, 298 N.C. 278, 4 A.L.R. 4th 667, 1979 N.C. LEXIS 1373 (N.C. 1979).

Opinion

SHARP, Chief Justice. 1

Initially, the primary relief which plaintiffs sought in this action was a decree ordering defendant to specifically perform its *284 commitment to provide long-term or “permanent” financing to enable plaintiffs to take up CCB’s interim construction loan on their motel-restaurant project. Historically, courts of equity refused to decree specific performance of a contract to lend money on the ground that the disappointed borrower could be fully compensated by damages because, presumably, money could always be found elsewhere. 2 More recently, however, courts have employed the equitable remedy of specific performance when the circumstances of the particular case demonstrate the inadequacy of money damages to afford appropriate relief. 3 In this case the parties’ stipulation that defendant is financially unable to comply with its contract rendered the availability of the remedy of specific performance immaterial. Plaintiffs, therefore, are relegated to such damages as they are legally entitled to recover, and are able to collect, from defendant.

A borrower’s claim for damages resulting from a lender’s breach of a contract to lend money is primarily circumscribed by the rule of Hadley v. Baxendale, 156 Eng. Rep. 145, 151 (Ex. 1854). This rule limits generally the recovery of damages in actions for breach of contract. To recover, a disappointed borrower must not only prove his damages with reasonable certainty, he must also show that they resulted naturally — according to the usual course of things — from the breach or that, at the time the contract was made, such damages were in the contemplation of the parties as a probable result of the breach. Additionally, the borrower must demonstrate that, upon the lender’s breach, he minimized his damages by securing the money elsewhere if available. When alternative funds are unavailable, however, the borrower may recover the damages actually incurred because of the breach, subject to the general rules of foreseeability and certainty of proof. See 5 Corbin, Contracts § 1078 (1964); 11 Williston on Contracts, § 1411 (3d Ed. Jaeger 1968); Annot., 36 A.L.R. 1408 (1925); 22 Am. Jur. 2d Damages §§ 68, 69 (1965); Coles v. Lumber Co., 150 *285 N.C. 183, 63 S.E. 736 (1909); Anderson v. Hilton and Dodge Lumber Co., 121 Ga. 688, 49 S.E. 725, 727 (1905); Bond Street Knitters, Inc. v. Peninsula National Bank, 266 App. Div. 503, 42 N.Y.S. 2d 744 (1943); Davis v. Small Business Investment Co. of Houston, 535 S.W. 2d 740, 742-43 (Tex. Civ. App.-Texarcana 1976).

The rule governing damages for breach of a contract to lend money is nowhere stated more succinctly than in Restatement of Contracts § 343 (1932):

“Damages for breach of a contract to lend money are measured by the cost of obtaining the use of money during the agreed period of credit, less interest at the rate provided in the contract, plus compensation for other unavoidable harm that the defendant had reason to foresee when the contract was made.

“Comment:

a. This Section is an application of the general rules of damages to a special class of contracts. The damages awarded are affected by the fact that money is nearly always obtainable in the market. If the loan was to be repayable on demand, or if the contract rate of interest is as much as the current market rate and the money is available to the borrower in the market, his recoverable damages are nominal only. He is expected to avoid other harm by borrowing elsewhere if he can, the reasonable expenses being chargeable to the defendant. Sometimes inability to borrow elsewhere or the delay caused by the lender’s action results in loss of a specific advantageous bargain, an unfinished building, or an equity of redemption in mortgaged land; damages are recoverable for losses if the lender had reason to foresee them.”

Clearly, the plaintiffs in this case have been injured by defendant’s breach of contract. Without defendant’s commitment to provide long-term financing they would not have begun construction of the motel project. When it was completed and the construction loan from CCB became due they were unable to obtain alternative long-term financing because none was available at any rate of interest. Plaintiffs were able to forestall foreclosure only by refinancing the construction loan with a demand note at a fluctuating rate of interest which varied from 2 to 3°/o above CCB’s *286 prime rate and was always in excess of the contract rate. At the time of the trial CCB was still carrying the construction loan. 4 Thus, this case differs significantly from those cases involving a disappointed developer-borrower who, unable to obtain specific performance or an alternative permanent loan, either suffers foreclosure 5 or obtains alternative permanent funds at additional expense, for a shorter time, or at a higher but constant rate of interest. 6

Specifically, the question for our determination is the following:

What is the measure of damages for breach of a contract to make a loan of $1,162,500 at 9V2°/o interest per annum, the loan to be amortized over 300 monthly installments and to be used to take out a short-term construction loan, when a substitute loan was unobtainable upon any terms at the time of the breach and, in order to forestall foreclosure, the borrowers had to refinance the construction loan by a demand note at a fluctuating rate of interest for a period of 18 months?

At trial plaintiffs sought to recover — and the judge purported to assess — their past, present and prospective damages. The case was tried upon the fiction that at the time of trial plaintiffs had obtained a permanent loan at 10V2°/o interest, which the court found was the lowest prevailing rate of interest for a comparable long-term commercial loan as of 1 October 1974, the date of the breach. In attempting to fashion a rule which would appropriately measure plaintiffs’ damages the trial judge analogized this case to those in which the borrower actually obtained another loan. On this theory, the trial court awarded plaintiffs general damages in the amount of $120,000, this amount being the difference between the interest on a 25-year loan of $1,162,500 at 10V2°/o per annum and a similar loan at 9V2°/o, reduced to present value and “discounted for the likelihood of early payment.” As special damages, Judge McKinnon awarded plaintiffs $5,888.12, the total of amounts which plaintiffs reasonably expended in *287 refinancing their construction loan with CCB to prevent foreclosure, and in their unsuccessful attempts over 18 months to secure a replacement long-term loan. The judge, however, refused to allow any recovery of the $184,619.49 in interest which plaintiffs paid CCB on the demand note during that 18-month interim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woollens v. Hamad
Court of Appeals of North Carolina, 2026
State of West Virginia v. William Bevel
745 S.E.2d 237 (West Virginia Supreme Court, 2013)
Majewski Enterprises Inc. v. Park at Langston, Inc.
711 S.E.2d 454 (Court of Appeals of North Carolina, 2011)
Beroth Oil Co. v. Whiteheart
618 S.E.2d 739 (Court of Appeals of North Carolina, 2005)
State Properties, LLC v. Ray
574 S.E.2d 180 (Court of Appeals of North Carolina, 2002)
Broussard v. Meineke Discount Muffler Shops, Inc.
958 F. Supp. 1087 (W.D. North Carolina, 1997)
Quate v. Caudle
381 S.E.2d 842 (Court of Appeals of North Carolina, 1989)
Doyle v. Oregon Bank
764 P.2d 1379 (Court of Appeals of Oregon, 1988)
McGarity v. CRAIGHILL, RENDLEMAN, INGLE & BLYTHE, PA
349 S.E.2d 311 (Court of Appeals of North Carolina, 1986)
Starling v. Sproles
318 S.E.2d 94 (Court of Appeals of North Carolina, 1984)
Stacy v. Merchants Bank
482 A.2d 61 (Supreme Court of Vermont, 1984)
Lincoln National Life Insurance v. NCR Corp.
603 F. Supp. 1393 (N.D. Indiana, 1984)
Meyers v. Imperial Cas. Indem. Co.
451 So. 2d 649 (Louisiana Court of Appeal, 1984)
Harsha v. State Savings Bank
346 N.W.2d 791 (Supreme Court of Iowa, 1984)
Rubin v. Pioneer Federal Savings & Loan Ass'n
334 N.W.2d 424 (Nebraska Supreme Court, 1983)
United Roasters, Inc. v. Colgate-Palmolive Co.
649 F.2d 985 (Fourth Circuit, 1981)
Carolina Wire & Cable, Inc. v. Finnican
264 S.E.2d 138 (Court of Appeals of North Carolina, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
258 S.E.2d 778, 298 N.C. 278, 4 A.L.R. 4th 667, 1979 N.C. LEXIS 1373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pipkin-v-thomas-hill-inc-nc-1979.