Majewski Enterprises Inc. v. Park at Langston, Inc.

711 S.E.2d 454, 211 N.C. App. 525, 2011 N.C. App. LEXIS 821
CourtCourt of Appeals of North Carolina
DecidedMay 3, 2011
DocketCOA10-496
StatusPublished
Cited by2 cases

This text of 711 S.E.2d 454 (Majewski Enterprises Inc. v. Park at Langston, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Majewski Enterprises Inc. v. Park at Langston, Inc., 711 S.E.2d 454, 211 N.C. App. 525, 2011 N.C. App. LEXIS 821 (N.C. Ct. App. 2011).

Opinion

BEASLEY, Judge.

The Park at Langston, Inc. (Defendant) appeals from the trial court’s judgment in favor of Majewski Enterprises, Inc. (Plaintiff), concluding Defendant breached an enforceable agreement between the developer parties by collecting a disproportionate share of credits from the Town of Cary (Town), which were intended to reimburse the parties for certain costs incurred in the installation of water and *526 sewer lines servicing the lots on their respective properties. We affirm in part, but because it is unclear whether the damages awarded Plaintiff were calculated with reasonable certainty or if any portion thereof was based on speculation, we remand in part for additional findings of fact, regarding Plaintiffs damages.

On 4 August 2008, Plaintiff filed a complaint alleging breach of contract or, in the alternative, unjust enrichment related to the parties’ respective subdivision development projects. A non-jury trial commenced on 20 July 2009, and the evidence presented tends to show the following.

Both parties to this action are real estate developers engaged in subdivision development on contiguous properties in Apex, North Carolina. Where public water and sewer services were not available to either Plaintiff or Defendant’s properties, the parties learned that the Town of Cary would permit them to extend such utilities to their developments and would reimburse certain construction costs involved therein if the water and sewer lines were built with capacity to serve additional properties in the future. Based on this understanding, the parties entered into a written agreement on or about 12 October 2001 (Co-Development Agreement), which provided for their division of the costs associated with bringing the municipal water and sewer lines to their respective subdivisions and detailed their specific arrangement. They “agreed to share the development responsibilities and the costs and expenses” incurred in the extension of water and sewer services “on a pro rata basis according to the number of lots” each party undertook to develop following final site plan approval.-As such, Plaintiff would pay 63% of the costs and expenses, and Defendant bore responsibility for 37% thereof. The Co-Development Agreement also provided that Plaintiff would pay Defendant the sum of $7,500.00 for supervising construction of the utility lines. Aside from a final $1,866.00 invoice from Defendant to Plaintiff, where Plaintiff had withheld the payment thereof due to a dispute regarding the bill, the parties duly paid their respective shares of the water and sewer line construction and attendant costs.

On 21 October 2002, Plaintiff and Defendant entered into a Reimbursement Contract with the Town of Cary, pursuant to which the Town agreed to reimburse the parties for costs incurred in constructing a sewer line, water line, and appurtenances (the Project) by crediting such costs against the related development, or “impact,” fees related thereto. Because there were two types of development *527 costs associated with the Project — (i) construction costs and (ii) development fees — “[reimbursements [would] be made based upon the cost of construction upon completion of the Project less the estimated water and sanitary sewer development fees which [were] considered prepaid by the Developer.” Of the $470,122.00 incurred in total construction costs, $353,394.00 represented the sewer line construction, and $116,728.00 represented construction of the water line. These component figures thus constituted the amount of credit available for each utility, from which each reimbursement would be debited. In this manner, “[w]ater and sanitary sewer development fees [would] be considered prepaid for [the parties’ subdivisions] ... up to the value of the water and sanitary sewer construction cost respectively identified.” Accordingly, when the parties’ builders went to obtain a building permit from the Town, they would “cash in” their respective credits, and the reimbursements would be docked from those values, representing the amount of impact fees deemed to have been prepaid and collected by the Town, until no credits remained. In the case that the parties’ costs were not fully reimbursed, because “the cost of the project exceeded] their fee needs or otherwise, the Reimbursement Contract provided for cash reimbursements “as other people connect to the line and pay their fees.” Specifically, “reimbursement of half of the water and sanitary sewer development fee [would] be . . . applicable for connection from other properties within the drainage area of the project” if other developers later sought to tap into the lines and thereby get the benefit of the parties’ construction.

As proof of entitlement to the development fee credits, the Reimbursement Contract required a letter “signed by the Developer” authorizing the use of such credits in order for any building permit to be issued pursuant to the reimbursement arrangement. Therefore, the parties, with the Town’s assistance, created certificates to provide to their builders, who could then turn the forms over to the Town when they were ready to have a particular lot permitted for sewer and water. Each certificate was signed by both parties, and allocated to each lot a water credit of $1,904.00 and a sewer credit of $2,866.00, based on the Town’s development fee schedule for water and sewer connections, respectively, in place at the time. The Town would accept the signed certificate and waive its impact fees for water and sewer hook-up connection — as assessed “at the time of site development” — in lieu of requiring payment from the builder. When the parties met in 2004 to apportion the water and sewer credits, it was their intention to receive those credits at the same percentage at which *528 they bore costs and expenses under the Co-Development Agreement: 63% to Plaintiff and 37% to Defendant. After signing and allotting the certificates between them, the parties independently issued the certificates for individual lots in their respective subdivisions and made them available to their builders for submission to the Town when applying for building permits.

Defendant’s lots were purchased by six or seven different builders. In selling its lots, Defendant would add the face-value price of the certificate by including that amount as a closing cost. Thus, a builder who purchased a lot in Defendant’s subdivision would pay Defendant not only the purchase price of the real estate but also a separate $4,770.00, representing the dollar amount of the combined water and sewer credits available for the subject property. In exchange for the additional cost, Defendant would provide the builder with a certificate at closing so that the builder could redeem the credits when it was ready to permit the lot with the Town, eliminating the builder’s obligation to pay the water and sewer fees. Plaintiff’s method of selling certificates to its builders was conducted differently, as it did not charge its customers any additional fee up front at closing. Where Plaintiff had only two tract builders — Old South Homes (Old South) and K Hovnanian Homes (K Hov) — these entities did not want to bear the added expense of multiple certificates at the time they purchased various lots from Plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woollens v. Hamad
Court of Appeals of North Carolina, 2026
MedShift, LLC v. Pelle, LLC
W.D. North Carolina, 2022
Pittman v. Henry Moncure Motors, Inc.
Court of Appeals of North Carolina, 2015

Cite This Page — Counsel Stack

Bluebook (online)
711 S.E.2d 454, 211 N.C. App. 525, 2011 N.C. App. LEXIS 821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/majewski-enterprises-inc-v-park-at-langston-inc-ncctapp-2011.