Matthews v. Davis

664 S.E.2d 16, 191 N.C. App. 545, 2008 N.C. App. LEXIS 1475
CourtCourt of Appeals of North Carolina
DecidedAugust 5, 2008
DocketCOA07-946
StatusPublished
Cited by8 cases

This text of 664 S.E.2d 16 (Matthews v. Davis) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matthews v. Davis, 664 S.E.2d 16, 191 N.C. App. 545, 2008 N.C. App. LEXIS 1475 (N.C. Ct. App. 2008).

Opinion

BRYANT, Judge.

Defendant James E. Davis appeals from an order awarding damages to plaintiff Chuck Stanley in the amount of $9,243.75, with interests and costs. We affirm the award.

Plaintiffs Ronald Matthews and Chuck Stanley owned adjacent lots in Stella, North Carolina along the White Oak River. In the early summer of the year 2000, Davis met with plaintiffs and as a result of that meeting entered into an oral contract for the construction of a sea wall. The cost of this sea wall to each plaintiff was $9,243.75.

The sea wall was a “rip rap” construction — large stones laid over a small slope extending out approximately 12 feet and standing approximately 8 feet high. Beneath the layer of stone lay a woven filter cloth, and beneath the cloth was sandy soil. The sea wall construction was completed and paid for by 6 November 2000.

Although plaintiffs lots adjoined, the grading and landscaping of their respective properties was “significantly different.” The Matthews property had “sock tile” (a six inch, corrugated black plastic pipe with a nylon sock) in place to assist in draining. The Stanley property did not. The Matthews property was graded to a “shallower or lower grade” with landscape features such as burlap laid over planting beds to enable roots to take hold, rye grass and a row of bushes. The Stanley property did not have the same grade or the landscaping.

*547 By early to mid December 2000, approximately a month after completion of the sea wall, erosion was noted as a result of soil washing from behind the sea wall, leaving large holes on the surface of the Stanley lot. There was some erosion of the Matthews property during this same period but significantly less than the Stanley property. Plaintiffs brought suit for breach of contract, breach of express warranty, breach of implied warranty of fitness for a particular purpose, and unfair and deceptive trade practices.

At trial, plaintiffs submitted the testimony of John Louis Eddy, a professional consulting engineer, who testified as an expert in the field of geotechnical and water resource engineering. In his initial observation of the plaintiffs’ properties, Eddy testified that “[tjhere was some loss of soil from the slope, movement of rip-rap erosion at the top of the drain. . . . There were holes in the fabric and obviously, the fabric was not retaining the soil. . . .”

The fabric used in the sea wall was woven. Eddy testified that “the fabric may not have been the appropriate fabric for use at the site. The soil particles[, relatively fine grain silty sand,] are fine enough that they can go through the woven fabric . . . .” The mechanism for that movement being the flow of water.

Eddy also observed “that the fabric had been placed with the machine direction parallel to the slope so that you have horizontal joints in the fabric. So when there’s tension in that fabric, it tends to pull apart and go down slope leaving openings.” The standard way to install the fabric is vertically, or perpendicular to the shoreline, rather than horizontally. In his opinion the slope of the rip-rap wall was also too steep to remain stable. “It wouldn’t take much to upset [the rip-rap] and cause [the stones] to move down the slope.” And, as there was no cushion layer of small stones between the fabric and the large stones laid on it, the result was that jagged holes appeared in the fabric from the tension created by the rip-rap. According to Eddy the purpose of the fabric under the rip-rap in the sea wall was “to serve as a separation layer between the rip-rap and the soil and retain the soil. . . . [I]f you punch holes in the fabric, you’re going to loose [sic] soil through those holes where it was intended to hold it in place.”

Eddy testified that “[he] reached the conclusion that there had not been adequate surface and sub-surface drainage installed. A rip-rap blanket like that is routinely installed to handle sub-surface drainage issues, but obviously with the problems with the fabric it couldn’t perform that function.” When asked whether he formed an *548 opinion satisfactory to himself to a reasonable degree of engineering certainty as to the cause of the serious distress observed in the rip-rap wall on plaintiffs’ properties, Eddy responded, “that there were problems with the design and construction of the rip-rap wall, basically that the proper fabric was not used.” When asked whether he formed an opinion satisfactory to himself to a reasonable degree of engineering certainty as to whether the rip-rap wall appeared to be capable of performing the function for which it was intended, Eddy responded, “[t]hat it was not.”

Furthermore, Eddy testified that the rip-rap wall “does not meet the standard of first-rate workmanship ....” “[T]he rip-rap is in a marginally stable condition borderline incipient failure . . . [meaning] it wouldn’t take much for it to come down.”

At the conclusion of the plaintiffs’ evidence, the trial court dismissed all but the claims for breach of express warranty and general breach of contract. At the conclusion of the evidence, the trial court found and concluded that the construction of the sea wall was in accordance with Davis’s design and such was not constructed in a workmanlike manner. The orientation of the filter fabric, to be laid in a workmanlike manner, should have been perpendicular to the shoreline rather than parallel, and holes in the fabric, created by stakes driven through it to hold the fabric in place during construction, ultimately allowed soil and sand to pass through the fabric and erode plaintiffs’ lots. The trial court denied Matthews’ claim despite the conclusion that the sea wall was constructed in less than a workmanlike manner on the basis that Matthews evidenced little to no damage to his property. The trial court awarded Stanley $9,243.75. Davis appealed.

Davis presents four questions on appeal: whether the trial court erred in (I) denying Davis’s motion to dismiss at the end of plaintiff’s evidence; (II) awarding damages to Stanley for poor construction of the sea wall; (III) entering judgment for Stanley; and (IV) awarding Stanley $9,243.74.

We note questions II and III are not supported by argument or case law, and according to our rules of appellate procedure those assignments of error are deemed abandoned. See N.C. R. App. P 28(b)(6) (2007) (“Assignments of error not set out in the appellant’s brief, or in support of which no reason or argument is stated or authority cited, will be taken as abandoned.”).

*549 /

Davis argues the trial court erred in denying his motion, pursuant to Civil Procedure Rule 41(b), to dismiss plaintiffs’ breach of contract claim. Davis argues there was no showing the sea wall caused any damage or harm to the property of either plaintiff, and he invites this Court to reexamine the facts.

Under the North Carolina Rules of Civil Procedure, Rule 41(b)
[ajfter the plaintiff, in an action tried by the court without a jury, has completed the presentation of his evidence, the defendant, without waiving his right to offer evidence in the event the motion is not granted, may move for a dismissal on the ground that upon the facts and the law the plaintiff has shown no right to relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woollens v. Hamad
Court of Appeals of North Carolina, 2026
Ds & T II, Inc. v. D & E Tax & Acct., Inc.
2021 NCBC 63 (North Carolina Business Court, 2021)
Brock v. Johnson Breeders, Inc.
775 S.E.2d 925 (Court of Appeals of North Carolina, 2015)
McEwen v. MCR, LLC
2012 MT 319 (Montana Supreme Court, 2012)
Plasma Centers of America, LLC v. Talecris Plasma Resources, Inc.
731 S.E.2d 837 (Court of Appeals of North Carolina, 2012)
Majewski Enterprises Inc. v. Park at Langston, Inc.
711 S.E.2d 454 (Court of Appeals of North Carolina, 2011)
Matthews v. Davis
678 S.E.2d 666 (Supreme Court of North Carolina, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
664 S.E.2d 16, 191 N.C. App. 545, 2008 N.C. App. LEXIS 1475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matthews-v-davis-ncctapp-2008.