Shurtleff v. Occidental Building & Loan Ass'n

181 N.W. 374, 105 Neb. 557, 1921 Neb. LEXIS 61
CourtNebraska Supreme Court
DecidedJanuary 19, 1921
DocketNo. 21113
StatusPublished
Cited by10 cases

This text of 181 N.W. 374 (Shurtleff v. Occidental Building & Loan Ass'n) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shurtleff v. Occidental Building & Loan Ass'n, 181 N.W. 374, 105 Neb. 557, 1921 Neb. LEXIS 61 (Neb. 1921).

Opinion

Day, J.

This action was brought by William B. Shurtleff, in •the district court for Lancaster county, against the Occidental Building & Loan Association to recover special damages claimed to have been sustained by him for an alleged breach of contract on the part of the defendant to lend the plaintiff $16,000.

The petition alleges in apt terms the making of the contract for the loan, the unwarranted breach' thereof by the defendant, and the. items going to make up his claim for special damages, which may be epitomized as damages arising out of the increased cost of the building; the loss of prospective rents; and the court costs and attorney fees incurred in perfecting his abstract to meet the' requirements of the defendant, a more detailed statement of which will hereinafter appear.

At the close of the testimony, on motion of the defendant, the court directed the jury to return a verdict for the defendant, which was accordingly done, and judgment rendered thereon for the defendant. The plaintiff has appealed.

The only question presented by the appeal is whether the court erred in instructing a verdict for the defendant.

It was the theory of the trial court, as disclosed by its remarks in ruling on the defendant’s motion for a directed verdict in its favor, that, conceding .that the plaintiff had established the making of the contract for the loan, and conceding the unwarranted breach thereof by the defendant, still the plaintiff must fail for the reason that no damages such.as the law recognizes for a breach of a contract to lend money had been shown. The trial court took the view that the measure of damages in such cases is the .difference between the contract rate of interest and the rate the borrower would have been required to pay in procuring the money elsewhere; and, there being no [559]*559testimony that a greater rate of interest would have been required, that therefore no damages would lie. It was also the view of the trial court that the damages claimed were too remote and speculative to form the basis of recovery.

In passing upon the correctness of the ruling of the court, we must consider the testimony tending to support the plaintiff’s theory of the case in its most favorable aspect. In support of the plaintiff’s theory, the testimony tends to shoAV that on October 5, 1916, the plaintiff made an application to the defendant for a loan of $25,000 upon an apartment house Avhich the plaintiff contemplated building upon a lot then OAvned by him in the city of Lincoln, Nebraska. At the time of the application the plaintiff exhibited to the. defendant the plans of the proposed building, which the defendant examined, figured the cost of the building, and informed the planitiff that his estimates were too high, but finally agreed to make a loan of $16,000 upon the premises, the money to be advanced from time to time as the building progressed toAvard completion. This proposition Avas accepted by the plaintiff, and in furtherance of the agreement on October 23,1916, he signed a note for $16,000 payable to the defendant, and plaintiff and his Avife duly executed a mortgage upon the premises to secure the payment of said note. The mortgage and note were delivered to the defendant and accepted by it, and the mortgage was duly filed for record the folloAving day. The testimony also shows that plaintiff, relying upon his contract, commenced the erection of the building in November, 1916, in accordance Avith the plans exhibited to the defendant; that plaintiff submitted to the defendant an abstract of his title, to Avhich objections Avere made, and, in order to satisfy the requirements of the defendant, plaintiff commenced tAvo suits to clear the clofid upon his title, and in the -end, about March 1, 1917, submitted an abstract Avhich met all the requirements of the defendant; that meanwhile the plaintiff had proceeded Avith the construction of the building, and had expended thereon about $12,000; that he had [560]*560let contracts for the heating and the plumbing, and the building had progressed to the stage that it was ready for plastering; the roughing in on the contracts for heating and plumbing had been done, and the radiation delivered on the premises; that on several occasions the defendant had examined the building, and made no complaint or objections to the manner of its construction; that on March 5, 1917, the defendant again examined the building, and then, for the first time, informed the plaintiff that the building would not stand a loan of $16,000, and offered to make a new loan of $12,000, which the plaintiff refused; that thereupon the defendant returned to plaintiff .the note, marked canceled, the mortgage, a release of the mortgage, and the abstract, and refused to carry out the contract for the loan; that the plaintiff made efforts to borrow the money elsewhere, and used due diligence in that behalf, but did not succeed in making a new loan until September or October, 1917, and then was able to borrow but $11, 000; that, by reason of the failure of the defendant to advance the money, the plaintiff was unable to meet the payments on the contracts for heating and plumbing, so that his contractors ceased work and refused to carry out their contracts, and the materials on the ground which were not in place in the building were removed by the contractors; that in completing the building in accordance with the plans, after procuring the money to do so, the plaintiff was obliged to pay for the plumbing the sum of $150 above the original contract price; that he was required to pay the sum of $250 above the original contract price for the heating, and, to even do this, reduced the amount of radiation called for in the original contract; that if the same amount of radiation had been put in as called for by the original contract, the increased cost would have been from $800 to $1,000 more; that there was a delay of several months in the completion of the building occasioned by the breach of the contract, and that by reason thereof the plaintiff lost prospective rents; that the gross rental was $875 a month, and that there was a great [561]*561demand for houses, and that the building could have been rented; that he paid out in costs and attorney fees in perfecting his title to meet the requirements of the defendant the sum of $150.

The measure of damages for a branch of a contract to lend money is usually, as announced by the trial court, the difference between the contract interest rate and the increased interest rate the borrower is obliged to pay in procuring a new loan. There are certain exceptions to this rule, one of which is that, where it appears that the specific purpose for which the loan was made was communicated to the lender at the time the contract was entered into, and where it further appears that the borrower has suffered special damages by the breach, Avhich are pleaded and proved, the damages recoverable are such as may fairly and reasonably be supposed to have been in the contemplation of the parties at the time of making the contract, as the probable result of a breach of it. The leading case upon this general subject, and one frequently cited by the courts, is Hadley v. Baxendale, 9 Exch. (Eng.) *341, *354, in Avhich it is said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Western Bank v. LJC Development, LLC
362 P.3d 1037 (Court of Appeals of Arizona, 2015)
Poppen v. Residential Mortgage Services, Inc.
556 N.W.2d 49 (Nebraska Court of Appeals, 1996)
Rayman v. American Charter Federal Savings & Loan
75 F.3d 349 (Eighth Circuit, 1996)
United California Bank v. Prudential Insurance Co. of America
681 P.2d 390 (Court of Appeals of Arizona, 1983)
Rubin v. Pioneer Federal Savings & Loan Ass'n
334 N.W.2d 424 (Nebraska Supreme Court, 1983)
Pipkin v. Thomas & Hill, Inc.
236 S.E.2d 725 (Court of Appeals of North Carolina, 1977)
Higgins v. Arizona Savings and Loan Association
365 P.2d 476 (Arizona Supreme Court, 1961)
Doddridge v. American Trust & Savings Bank
189 N.E. 165 (Indiana Court of Appeals, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
181 N.W. 374, 105 Neb. 557, 1921 Neb. LEXIS 61, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shurtleff-v-occidental-building-loan-assn-neb-1921.