Roettinger v. United States

26 Ct. Cl. 391, 1891 U.S. Ct. Cl. LEXIS 11, 1800 WL 1798
CourtUnited States Court of Claims
DecidedJune 8, 1891
DocketNo. 14419
StatusPublished
Cited by4 cases

This text of 26 Ct. Cl. 391 (Roettinger v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roettinger v. United States, 26 Ct. Cl. 391, 1891 U.S. Ct. Cl. LEXIS 11, 1800 WL 1798 (cc 1891).

Opinion

Davis, J.,

delivered the opinion of the court :

This action grows out of a contract, made in June, 1881, with plaintiffs intestate by the engineer in charge of improvements upon the Ohio River, and which, it is urged, was afterwards so interpreted by the Government officer as to cause the contractor serious loss. The subject-matter of the contract was the construction of a dike at “ Puppy Creek Bar,” upon the Kentucky side of the Ohio River,between Owensboro, Ky., and Rockport, Ind.

The first ground of action may be thus stated: The dike was by the contract to be 3,000 feet long, and the substructure was to be entirely completed in the working season of the year 1881, the superstructure to be placed upon it during the season of 1882. In September, 1881, however, Major Merrill, the Government engineer in charge, suspended the work upon the dike for several days, when it was resumed in accordance with another order, which, however, limited the length of the substructure to 1,500 feet, thus reducing the length of the dike one-half. As a consequence of these orders plaintiff’s intestate was damaged.

[407]*407The second cause of action is based upon the allegation that the contract required brush to a large amount to be put into the dike, whereas after the work had been some time in progress, Major Merrill directed the contractor to put in much less brush per running foot and much more riprap stone, which he did, to his loss and damage.

As to the first alleged cause of action:

The specifications'(s. 1) provide that the dike shall be about 3,000 feet long; they provide (s. 4): “ It is the intention that the substructure shall be completed during the first season and that the superstructure shall be placed on it during the ensuing season after the substructure shall have had an opportunity to settle and to become solidified’ by sedimentary deposits; ” they provide that (s. 13) “ during the second season of work the incomplete dike will be capped by a continuous superstructure of timber crib work filled with riprap stone; ” and they provide (s. 36) it is expected that the work of getting out stone and timber for the dike will be begun immediately after the contract is signed, and that the actual construction of the dike will commence as soon as the river is at a favorable stage for work. The substructure of the dike must be completed by December 31, 1881, and the superstructure by December 31, 1882.”

The contract, of which these specifications became a part, contained this provision:

The said Jacob Clark shall commence work under this contract on or before the first day of August, eighteen hundred and eighty-one (1881), and shall complete the same on or before the thirty-first day of December, eighteen hundred and eighty-two.”

Therefore it most distinctly appears that the contractor was bound to complete the entire substructure, 3,000 feet in length, during the season of 1881, and to place the entire superstructure thereon during the season of 1882. Plaintiff’s intestate promptly and properly gathered his materials at the dike and was efficiently performing work upon the substructure when he was stopped by Bateman, the inspector in charge, in consequence of an order from Major Merrill. After the lapse of several days work was again resumed under Major Merrill’s orders, but with the substantial difference that the substructure was ordered by him to stop at 1,500 feet; that is, the amount of [408]*408Vork which the contractor was obliged by the contract to be (prepared to finish in 1881 (and which he was prepared to finish) was reduced one-half.

As a consequence of the temporary suspension the contractor incurred various expenses, and his personal services and presence were required at the dike in the uncertainty of the situation. The losses which the contractor unavoidably and necessarily incurred during said suspension, through the order of the Government agents and by no fault of his, amounted to $812, and this amount plaintiff should recover from defendants.

Plaintiff should also recover, at the contract price, the value of the brush put into the work by the contractor during the suspension. The Government had the benefit of this work, and there is no reason why it should not have been paid for. He should receive upon this account (at the contract price) the sum of $1,593.90.

The piling and waling for 3,000 feet of substructure were at the dike at the time Major Merrill’s orders were given, as herein-above referred to. ' This was proper, and although due care was taken of the materials and they were removed out of the reach of ordinary floods, the extraordinary freshets of the winter of 1881-1882 washed away much of this property and it was lost to the contractor. But for defendants’ action this timber would have been securely in the dike at the close of the season of 1881, and Clark’s losses thereon should be paid.

The contractor’s misfortunes did not stop here. Had he been allowed in 1881 to finish the substructure as provided in the contract, he could have finished the superstructure in 1882; but in 1882 he was obliged not only to build the entire superstructure, but also to finish the substructure. That is, in 1882, through no fault of his, he was forced to build 1,500 feet of substructure in addition to the work which he had contracted to do in that season. This he could not do, therefore hia contract was extended by defendants another season. But in the ensuing winter (1882-1883) another freshet washed away his timber, without fault upon his part, as he had exercised due care in its protection, and he sustained various other losses detailed in the findings. The case is one of hardship, caused by no fault on the contractor’s side, but by the defendants’ agents, who were forced to this action by lack of funds in the autumn of 1881.

[409]*409The whole case (so far as these issues are concerned) is traceable in fact to the order cutting down the amount of substructure to be built in 1881 one-half from the contract requirement. As a result of that order material properly ready at the site in 1881 was lost; as a result of it the superstructure could not be completed in 1882 ; as a result of it plaintiff’s contract was extended into 1883; and as a result of it his material was again washed away in.the winter of 3882-’83. While this is so in-fact, defendants urge that in law they are not financially responsible for the contractor’s losses.

The contract (of which the.specifications are part) clearly shows that time was of its essence; the date of beginning work was fixed; the date of finishing the substructure was fixed; the date of finishing the superstructure was fixed; the intention was explicitly stated to finish the substructure the first season, that it might settle and solidify, to be in readiness for the superstructure in the second season; the work of getting out timber and stone it was “ expected” should be begun immediately ; the Government reserved the right to require an increase of force, and, failing tp secure this, to complete the dike themselves; and there was a forfeiture provision, to be operative should the contractor delay or fail to commence the delivery of materials or the performance of the work on the day specified, or should he fail to prosecute it in accordance with the requirements of the contract. Nothing but

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christensen Construction Co. v. United States
72 Ct. Cl. 500 (Court of Claims, 1931)
American Dredging Co. v. United States
49 Ct. Cl. 350 (Court of Claims, 1914)
Richtman v. United States
47 Ct. Cl. 483 (Court of Claims, 1912)
Lewman v. United States
41 Ct. Cl. 470 (Court of Claims, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
26 Ct. Cl. 391, 1891 U.S. Ct. Cl. LEXIS 11, 1800 WL 1798, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roettinger-v-united-states-cc-1891.