Cape Ann Granite Co. v. United States

20 Ct. Cl. 1, 1885 U.S. Ct. Cl. LEXIS 71, 1800 WL 1304
CourtUnited States Court of Claims
DecidedJanuary 12, 1885
DocketNo. 11960
StatusPublished
Cited by10 cases

This text of 20 Ct. Cl. 1 (Cape Ann Granite Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cape Ann Granite Co. v. United States, 20 Ct. Cl. 1, 1885 U.S. Ct. Cl. LEXIS 71, 1800 WL 1304 (cc 1885).

Opinion

Weldon, J.,

delivered the opinion of the court:

In the year 1869, the claimant, a corporation of the State of' Massachusetts, made two written contracts with the United States, and, among other things, agreed to deliver to them an indefinite quantity of granite, to be used in the erection of a, post-office and sub-treasury building in the city of Boston.

The first agreement was made on the 13th of July and the-second on the 26th of October, 1869, both of which were ex[7]*7tended by act of the parties. The contracts ~and extensions will be found in finding I, or so muela of them as is material to be considered in the discussion and determination of the issues of this controversy.

The contract dated July 13 relates to the foundation material for said building, and the one dated October 26 to the material of the superstructure.

The contracts are very similar in their provisions, except as to the price to be paid by the defendants. In both it is provided that a certain per cent, shall be paid monthly as the delivery progresses, and the residue when the contracts shall_be fulfilled to the satisfaction of the United States.

Under the contract of July 13 claimant delivered 21,355 cubic feet of stone prior to September 30,1871, each stone exceeding 20 feet in contents, and 52,188 cubic feet under the extension of said contract.

Under the contract of October 26 claimant delivered 98,679 cubic feet of similar stone, and under the extension there of 94,234 feet, aggregating under both contracts 266,456 feet, as will be seen by reference to the findings.

For this amount of stone delivered under both contracts the defendants have paid the claimant, as it alleges, 20 cents per cubic foot less than it is entitled to; and this suit is prosecuted to recover the sum of $53,291.48 withheld by the government upon the construction of the contracts by the officers instrusted with the payment of the money.

The difference between the litigants originates as to the proper construction of the agreements in the amount to be paid for stone having a greater cubic content than 20 feet.

This controversy commenced in the early period of the work, and was a subject of contention at several times during the progress of the same.

In February, 1875, a voucher was certified by the proper officer of the government, for granite delivered by claimant under the different contracts, amounting to $141,976.03, with credits to the government of $137,666.38, leaving a balance due the claimant of $4,309.65. With that voucher there was presented to the claimant a receipt, bearing date on said day; and after reciting the amount of money, the receipt concluded with the following words: “In full payment of the above account, and in full of all claims that have arisen or may arise [8]*8under tbe contracts above specified, and in final and absolute settlement of tbe same.”

Tbe receipt thus worded was executed by tbe president of tbe company, who at tbe same time, and as a part of tbe transaction, filed with said receipt, and attached to it, a written protest, in substance that the receipt does not cover certain claims which are not included in tbe voucher on file for tbe amount for which the receipt is given; “ that the receipt in full is a receipt for the claims represented by these vouchers only.”

The papers so executed were delivered to the' agent of the •defendants who paid the said sum of $4,309.65.

The phraseology of the protest of February 23, 1875, was, on the 27th of March, changed, by the consent of the parties, in ■order to identify it more accurately with the voucher and receipt, its legal effect from its mere words remaining the same.

On the 7th of October, 1882, another receipt was given by the claimant for stock supplied under said contracts, amounting to $30,000, which was “in full of the above account.”

Again, on the 24th of July, 1883, a voucher was made showing a balance due claimant of $7,357.33, and the claimant, by its president, executed a receipt for said balance, “ in full payment of the above account,” accompanying it with a written ¡protest “ that it does not cover certain claims which the Cape Ann Granite Company has, which are not included in the vouchers on file for the amount of which this receipt is given; that the receipt in full is a receipt for claims represented by this voucher only.”

The payments to the claimant were made on the assumption that the price per cubic foot for each stone is found by increasing the contract price per cubic foot for like stone, measuring 20 cubic feet or under, by as many cents, minus 20, as there are cubic feet in the given stone, thus making the price per •cubic foot of a superstructure stone containing 30 cubic feet 65 cents (55+30 — 20=65).

To the claimant’s right of recovery the defendants interpose «three objections: ' t

First. That by a proper and legal construction of the contracts the claimant has received as much as it is entitled to be paid. Second. That having executed a receipt in full, it is barred from recovering further compensation. Third. That as [9]*9to a portion of the claim the statute of limitations destroys the right of action.

We will consider these defenses in the order named. In the contract of the 13th of July the doubtful phraseology is as follows : The party of the first part “ agrees to pay the sum of 39§ cents when the dimension does not exceed 20 cubic feet in each stone, with 1 cent additional for every cubic foot in any single stone beyond said 20 cubic feet each.”

In the contract of October 26 the words are “55 cents per cubic foot for all stones the quarried dimensions of which do not exceed 20 cubic feet in each stone, and 1 cent additional for every cubic foot of those having such dimensions exceeding 20 cubic feet.”

The words used in each contract are so similar that a construction of one is necessarily a construction of the other.

The question as to the proper construction of the agreements is not anew one in the jurisdiction of this court. In the case of Dix Island Granite Company v. United States (12 C. Cls. R., 624) a petition was filed embracing substantially the same cause of action asserted by the averments of the petition in this case. A demurrer was interposed, which was sustained by a majority of the court on the main question of the petition, and by all the court upon matters of detail. The case was finally heard on its merits before additional judges, and a judgment entered for the claimant, based upon the theory of compensation sought to be maintained by the claimant in this proceeding. The case was appealed to the Supreme Court, and is reported in 105 U. S. R., 37.

In the decision of the Supreme Court it is said:

“ Where a party who delivered granite was by the terms of his contract to receive the sum of 65 cents per cubic foot for all the stones when the quarried dimensions do not exceed 20 feet in each stone, and 1 cent additional for each cubic foot of those having such dimensions exceeding 20 cubic feet: Held, that where the dimensions exceed 20 cubic feet he is entitled for each cubic foot 65 cents, and 1 cent additional for each cubic foot of the entire stone.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Needles ex rel. Needles v. United States
101 Ct. Cl. 535 (Court of Claims, 1944)
Southern Pacific Co. v. United States
59 Ct. Cl. 36 (Court of Claims, 1924)
Chicago & Alton Railroad v. United States
57 Ct. Cl. 300 (Court of Claims, 1922)
New Hampshire v. United States
36 Ct. Cl. 563 (Court of Claims, 1901)
Pneumatic Gun-Carriage & Power Co. v. United States
36 Ct. Cl. 71 (Court of Claims, 1901)
Cotton v. United States
29 Ct. Cl. 207 (Court of Claims, 1894)
Roettinger v. United States
26 Ct. Cl. 391 (Court of Claims, 1891)
Buck v. United States
25 Ct. Cl. 120 (Court of Claims, 1890)
Mosby v. United States
24 Ct. Cl. 1 (Court of Claims, 1888)
Dowdy v. United States
23 Ct. Cl. 97 (Court of Claims, 1888)

Cite This Page — Counsel Stack

Bluebook (online)
20 Ct. Cl. 1, 1885 U.S. Ct. Cl. LEXIS 71, 1800 WL 1304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cape-ann-granite-co-v-united-states-cc-1885.