Pneumatic Gun-Carriage & Power Co. v. United States

36 Ct. Cl. 71, 1901 U.S. Ct. Cl. LEXIS 132, 1900 WL 1386
CourtUnited States Court of Claims
DecidedFebruary 18, 1901
DocketNo. 21034
StatusPublished
Cited by9 cases

This text of 36 Ct. Cl. 71 (Pneumatic Gun-Carriage & Power Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pneumatic Gun-Carriage & Power Co. v. United States, 36 Ct. Cl. 71, 1901 U.S. Ct. Cl. LEXIS 132, 1900 WL 1386 (cc 1901).

Opinion

Howry, J.,

delivered the opinion of the court:

Plaintiff, on April 25, 1888, entered into a contract with the defendants, represented by the Secretary of the Navy, to furnish all necessary labor and material and erect and construct upon the monitor Terror all the machinery and appurtenances necessary to the complete application of power known as the pneumatic system for the'manning and working of the turrets and a part of the armament of the monitor, to the steering- of the vessel, and to the permanent maintenance thereon of a uniform refrigerating temperature. The contract price was fixed at $228,750, and plaintiff agreed to deliver the machinery and appurtenances upon the monitor at the navy-yard, Boston, Mass., and commence the work of installation within six months from the date of the contract. The Terror was then under construction at the navy-yard in Brooklyn, N. Y. Shortly after the execution of the contract, plaintiff procured the South Boston Iron Works, a manufacturing concern in Boston, to manufacture the machinery in that city and to install the same when the Terror should be brought to Boston. The subcontractor proceeded in accordance with the terms of plaintiff’s contract with the defendants, and at the expiration of the six months had the machinery completed, as far as the same could be finished in the shops. Plaintiff was aware of the unfinished condition of the vessel, but no notice was given to it by the defendants of their inability to bring the vessel to Boston, and its subcontractor was compelled to hold the machinery until such time as the monitor might appear at Boston. This state of uncertainty continued until a contract was entered into between plaintiff and the United States, by which it was agreed, for the further sum of $11,500 to be paid to plaintiff, that the machinery should be delivered at the Brooklyn Navy-Yard within sixty days from the date of the contract. The subcontractor, acting for plaintiff, proceeded under the supplemental contract to remove the machinery to Brooklyn, and on January 8, 1891, had it all there ready to begin the work of installation. The monitor, however, was not sufficiently completed to receive the machinery in its proper place, and by reason of the uncompleted condition of the vessel and interferences with [88]*88workmen engaged in its construction plaintiff was debited in the work of applying and fitting the machinery.

The findings establish damages in the sum of $14,612.88, occasioned by these acts of the defendants.

But for these acts it is claimed that whatever damages arose accrued to the subcontractor and not to plaintiff, and that for this reason the action can not be maintained.

It appears that there has been no accounting between plaintiff and the subcontractors; that no money has passed between these concerns, and no claims have been presented by the subcontractors to their principal; and, in consequence, it is argued that plaintiff can only recover such damages as it appears it alone has suffered, without reference to ivhat injury subcontractors may have sustained.

At the time plaintiff entered into the contract it had no plant of its own for the manufacture of machinery. The arrangement made bjr plaintiff with the South Boston Iron Works to manufacture and install the machinery proceeded until in turn the Hunt-Spiller concern, another company, was engaged to go on with the work.

The defendants- had no contract relations with the South Boston Iron Works or with the Hunt-Spiller Company, and can not be held to answer directly to those concerns. Defendants’ responsibility is direct only to the other principal party to the agreement, while the subcontractors must look alone to their principal for whatever damages may have arisen to them in consequence of delay or interruption of the work of that principal affected by the acts of the other principal. If plaintiff can not recover, then the whole loss must fall upon the party not in fault unless plaintiff shall hereafter pay the subcontractors, and then within the limit of time allowed by law to bring suit to recover. This, the- defendants insist, they should do before the damages can realty become a claim against the United States. But this theory ignores the fact of any subcontract being necessary to the fulfillment by plaintiff of its contract with the defendants, a fact which defendants knew in the progress of the work, if not in the beginning.

Subcontracts are the common incidents of building and other similar enterprises. They are ordinarily entered into preliminary to undertakings of the character shown here, and [89]*89in case of delays and interferences caused by a party ordering work and material the measure of damages done the other principal is usually the measure of compensation due subcontractors by the principal not in fault. There is no element of uncertainty in what the damages to subcontractors should be after it is ascertained that the principals have caused.damages in a precise and definite sum. Such is the case here. Those cases of subcontract where damages sustained by the subcontractor should not enter into the estimate of the amount recoverable against the party first causing the damage rest upon the idea that the party having no control over or participation in the making of the subcontracts should not be compelled to assume them if improvidently entered into, and the further idea of assuming that the party complaining is necessariljr compelled to break all his subcontracts as the consequence of the breach of the principal one. But here the case is different. We know the subcontractor sustained the same helajes and interruptions as did the plaintiff. There is nothing-hypothetical or remote in the sums claimed or in the amounts that the subcontractors can claim of the plaintiff. The acts of the defendants operated precisely upon all the other parties alike in proportion to the extent of their respective interests. The defendants are not liable for any subcontracts improvidentty made. It is certain that plaintiff’s contract with the South Boston Iron Works was broken by the fault of the United States. We think defendants should answer at this time without waiting for plaintiff to first pay the damages sustained by the subcontractors, because these damages would not have been caused had the United States kept faith with the other principal to the agreement.

The work of installation proceeded so slowty a board of naval officers was appointed November 20, 1894, by the Secretary of the Navy to make an estimate of the actual cost of completing the work. This board estimated the time at seventy working days, at a total cost of $11,553, and in February, 1895, another supplemental contract was entered into in consequence of the delays, largely attributable to the failure of the Government to complete the construction of the hull of the monitor, but also in consequence of the subcontractor being without financial means at that time to go on under the [90]*90original contract. Defendants took charge of the work but did not complete the same until May 29, 1897, at a cost of $41,221.08.

When the work was completed plaintiff submitted a request to the Secretary of the Navy to examine a statement (then being prepared by plaintiff) of extra expenses incurred by reason of defendants’ unreadiness and delays in connection with the contract, and to expedite the settlement plaintiff requested the Secretary to organizo a board to examine the whole subject, hear the company’s representatives, and receive the evidence presented by the company, and report what in their judgment was a fair settlement to be made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
Houdaille Industries, Inc. v. United States
151 F. Supp. 298 (Court of Claims, 1957)
H. Herfurth, Jr., Inc. v. United States
89 Ct. Cl. 122 (Court of Claims, 1939)
McShain v. United States
87 Ct. Cl. 581 (Court of Claims, 1938)
In re Claim of Hodges
84 Ct. Cl. 380 (Court of Claims, 1937)
W. S. King & Co. v. United States
80 Ct. Cl. 325 (Court of Claims, 1934)
Noel Construction Co. v. United States
50 Ct. Cl. 98 (Court of Claims, 1915)
William Clamp & Sons Ship v. United States
41 Ct. Cl. 164 (Court of Claims, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
36 Ct. Cl. 71, 1901 U.S. Ct. Cl. LEXIS 132, 1900 WL 1386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pneumatic-gun-carriage-power-co-v-united-states-cc-1901.