W. S. King & Co. v. United States

80 Ct. Cl. 325, 1934 U.S. Ct. Cl. LEXIS 196, 1934 WL 2031
CourtUnited States Court of Claims
DecidedDecember 3, 1934
DocketNo. M-91
StatusPublished
Cited by1 cases

This text of 80 Ct. Cl. 325 (W. S. King & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. S. King & Co. v. United States, 80 Ct. Cl. 325, 1934 U.S. Ct. Cl. LEXIS 196, 1934 WL 2031 (cc 1934).

Opinion

Booth, Olvief Justice,

delivered the opinion of the court:

The plaintiff is incorporated under the name of W. S. King & Company, and is engaged in construction and repair [331]*331work. The office of the corporation is in Philadelphia, Pa. On April 11, 1930, plaintiff and defendant, the latter acting through the Militia Bureau of the War Department, signed a contract obligating the plaintiff to reroof sixty-three buildings at Camp Beauregard, Louisiana, for which it was to receive $8,750. The work was to commence immediately and be completed by June 11, 1930.

The plaintiff at once assembled the materials and laborers required to do the work and commenced performance on time. From the very beginning of performance until the completion of the contract work differences and disputes arose between the plaintiff’s representative and-the representative of the contracting officer on the work, and this case involves said differences and disputes, the plaintiff alleging illegal contractual exactions, which occasioned it expense, and the imposition of extra and additional work which under the contract it was not required to perform. The defendant challenges practically every item claimed, and,, in addition, files a counterclaim.

Item 1. Paragraph 8 of the specifications provided in part as follows

“ 8. Liability itok damages : The contractor will be held responsible for all damage to the work under construction, whether from fire or other causes, during performance and until final completion and acceptance. * * * ”

The contracting officer, construed this as compelling the plaintiff to take out fire-insurance policies upon the group of buildings upon which work was in progress, for and in behalf of the United States. The plaintiff protested but was compelled to yield when faced with a stoppage of all work unless this was done. The insurance was obtained at a cost of $223.15 and the policies were made payable to the United States and retained in the custody of the contracting-officer.

The defendant contests this item upon the theory that the plaintiff having assumed liability for damages caused by fire and being financially irresponsible, the contracting officer was within his contractual rights in exacting the insurance. The defendant says that insurance against fire was as bene[332]*332ficial to the plaintiff as to the United States. With this latter proposition we have nothing to do: The United States inserted article 8 into the specifications, and the indemnity provided in case of fire was restricted to the plaintiff corporation and the bond executed by it. The United States was willing to accept the contractor’s responsibility without compelling it to provide against the contingency by taking out fire insurance. The principle of law involved is akin to what this court said in Leary Construction Company v. United States, 63 C. Cls. 206, and Pneumatic Gun-Carriage Company v. United States, 36 C. Cls. 71. We think the contracting officer misinterpreted this article of the specifications and the item is allowable. The item is manifestly foreign to a claim for extra work or material under article 5 of the contract.

Item 2 relates to the small sum of $13.50 and is the subject of sharp conflict in the testimony. Article 6 of the contract provided for an inspection of all materials to be used in performing the contract. The roofing material was-to be Carey extra heavy roll roofing slate surfaced ‘ las-tile.’ ” The contracting officer required the plaintiff to deliver to him for inspection six full rolls of roofing paper purchased for use under the contract specifications. The plaintiff under protest delivered the paper, and for some unexplained reason the same was never even opened, much less inspected. The plaintiff says the paper was never redelivered to it. The defendant says the plaintiff gave a written order to the contracting officer to deliver the same to plaintiff’s subcontractor, who was placing the roofing. We are unable to find a written order to this effect in the record, and no proof that it has been lost or misplaced. The evidence does show that plaintiff’s subcontractor had possession of the paper and that none of it went upon the roofs of the buildings, the subcontractor retaining it for his own purposes.

The defendant does not disavow the right of the plaintiff to have the paper returned for use by it, and the record establishes that the plaintiff was denied the right to use it. The contracting officer in doing what he did had a con[333]*333tractual right to exact the delivery of the paper for inspection, bnt clearly he had no contractual right to retain it un-inspected and then dispose of it in the manner proved. The contracting officer’s authority was stated in the contract, and if he chose to enter into the relationship existing between the plaintiff and its subcontractor that was a matter completely outside the terms of the contract. His manifest duty under the facts established was to return the paper to the plaintiff. We can find no competent evidence in the record that the plaintiff authorized the delivery of the paper to its subcontractor. The item will be allowed.

Item 3. In considering this item it will be necessary to set forth the following provisions of the contract and specifications :

“ Aetiole 15. Disputes. — Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within thirty days to the head of the department concerned, whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed.”
“ EemoviNG old ROOKING: The contractor shall remove all old roofing and metal edging and shall clear sheeting of all old roofing nails.”
“ Defective sheeting : Cracked, rotten, and broken sheeting and sheeting having knot holes one (1") inch in diameter or larger shall be considered defective. This sheeting shall be removed and replaced with new sheeting #2 long leaf yellow pine, squared on four sides, or shiplap, depending on whether boards or shiplap was used previously for sheeting on building being covered.”
“Longitudinal cracks: All longitudinal cracks more than one-half (%") inch wide will be closed by removing old sheeting and relaying or replacing with new sheeting so as to close crack.”
“ Length of sheeting : No new or salvaged sheeting less than six (60 feet long will be used.”

It is to be observed that under the specifications the plaintiff was to first remove all of the old roofing in place upon the buildings. The old sheeting upon which the old roof had been nailed was to be removed wherever defective and [334]*334replaced with new sheeting as provided. Old sheeting was to be classified as defective whenever it fell within the provisions set forth in the specifications. Fifteen of the buildings were erected in 1917 and were known as the “ wartime group.” The roofs on all these buildings were in bad condition. The remaining 48 were constructed in 1926 and the roofs were not so dilapidated. ■

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Centaur Construction Co. v. United States
69 F. Supp. 217 (Court of Claims, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
80 Ct. Cl. 325, 1934 U.S. Ct. Cl. LEXIS 196, 1934 WL 2031, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-s-king-co-v-united-states-cc-1934.