George Leary Construction Co. v. United States

63 Ct. Cl. 206, 1927 U.S. Ct. Cl. LEXIS 333, 1927 WL 2960
United States Court of Claims·Decided February 23, 1927·No. No. D-39·Published·Cited by 9 cases

Opinion

Booth, Judge,

delivered the opinion of the court:

The contract furnishing the basis of this suit provided in part as follows:

Adjustment of wages. — If, after the date of the contract, there shall be any increase in the rates of wages prevailing in the vicinity of a place where work contemplated by the contract is done that shall necessitate payment by the contractor on account of labor employed exclusively upon such work of rates of wages in excess of those prevailing in such vicinity at the date of the contract, he shall receive additional compensation in a sum equal to one-half the amount of the increase in the rates of wages so required to be paid by him over the rates prevailing at the date of the contract: Provided, that in determining such additional compensation wages paid by the contractor at any time during the continuance of the contract in excess of the rates prevailing in the vicinity at the time of such payment shall be disregarded to the extent of such excess: and provided further, that any increase over wage rates prevailing at the date of the contract before being granted by the contractor shall be notified to and approved in writing by the Bureau of Yards and Docks. For the purposes of this paragraph, rates of wages prevailing in the vicinity of a place where work contemplated by the contract is done shall be understood to mean the established rates of wages in the nearest navy yard or station, if there be one within 50 miles of such place, or, if there be none within that distance, the rates of wages paid under a well-established wage scale, if any, in such vicinity, or, if there be none, such reasonable rates of wages as may be determined by the Navy Department, Bureau of Yards and Docks. The burden shall be upon the contractor of establishing to the complete satisfaction of the Bureau of Yards and Docks all facts upon which any claim for additional compensation hereunder shall rest, and all questions growing-out of any such claim shall be determined by the Navy [222] Department, Bureau of Yards and Docks, whose decision thereon shall be final and conclusive. Determination of such claims shall be deferred until the completion of the contract.”

The plaintiff stated its claim for increase in wages arising under this provision and fixed the amount at $15,897.92, $4,825.60 of this total amount representing cash outlay for subsistence of the men employed by the plaintiff in the performance of the contract. When the claim reached the Bureau of Yards and Docks the item of $4,825.60 was disallowed and $10,572.32 allowed. The bureau determined that subsistence furnished was not wages paid. We need not discuss the merits of the disallowance now sued for. The clause under which the allowance and disallowance were authorized provided that the board’s decision in this respect should be final. The authorities sustaining the conclusiveness of the board’s decision are too many to warrant citation. Yale & Towne Mfg. Co. v. United States, 58 C. Cls. 633.

Subsequently an additional claim arose under this same clause of the contract. The facts are these: July 31, 1918, the plaintiff sublet a part of the work under its contract to James Stewart & Company, and with the Stewart Company the plaintiff agreed that any sum allowed for increase of wages as per plaintiff’s contract with the Government would be paid by the plaintiff to the Stewart Company, and if the Government made no allowance the plaintiff was to pay nothing to the Stewart Company, both parties realizing that the question of an allowance depended upon the final action of the Bureau of Yards and Docks. The James Stewart Company performed its subcontract; the work was done and was satisfactory to the Government. When the contract was completed, the increase in wages, accurately kept, was claimed by the plaintiff, and the amount stated was approved by the public-works officer and finally transmitted to the Bureau of Yards and Docks for final action. The Bureau of Yards and Docks in its decision uses this language, found in Finding XXI:

“ The bureau is of the opinion that the general contractor is entitled to reimbursement on account of wage increases of subcontractors only after he has himself actually reimbursed the subcontractor, and then only to the extent of one-half the amount paid the subcontractor.”

[223] Again, on September 9,1920, tbe bureau found as follows:

“ Subject: Contract No. 2690, December 12, 1917, for dredging and filling at naval operating base, Hampton Eoads, Norfolk, Va.
“ Gentlemen : Your letter dated July 2, recently delivered to the bureau, with reference to your claim for increased-wage adjustment under contract No. 2690, has had consideration.
“ The stand heretofore taken by the bureau in this matter, that under the terms of paragraph 2 of specification No. 2690 you are entitled, on account of the wage increase paid by your subcontractor, to but one-half the amount in which you are required .to, and do, reimburse your subcontractor for such increase, is believed to be proper, and it is therefore confirmed.”

In its final analysis the decision of the bureau was a refusal to allow what the plaintiff’s contract with the Government expressly entitled the plaintiff to receive, because the plaintiff had not shown payment by it to its subcontractor. The bureau had no jurisdiction over the contract between the plaintiff and its subcontractor. It was no affair of the bureau’s whatever with respect to this claim. The plaintiff was within its rights in subcontracting a portion of the work, and no complaint as to performance of the work was lodged against the plaintiff or the subcontractor. The Government looked to the plaintiff for the performance of the subcontractor’s contract, and it would create a most unusual situation that a sum admittedly due under the plaintiff’s contract may be legally withheld from it on the pretense that the plaintiff had not settled with or discharged its obligations to its subcontractor. The payment to the plaintiff of the amount claimed discharged the Government from its liability under the contract. The subcontractor could not sue for the amount, and the bureau manifestly exceeded its jurisdiction in disallowing the claim for the reasons stated. Merritt v. United States, 267 U. S. 338.

Free access — add to your briefcase to read the full text and ask questions with AI

George Leary Construction Co. v. United States, 63 Ct. Cl. 206, 1927 U.S. Ct. Cl. LEXIS 333, 1927 WL 2960 (cc 1927).

63 Ct. Cl. 206 (George Leary Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Roof-Techs International, Inc. v. State
57 P.3d 538 (Court of Appeals of Kansas, 2002)
Morrison Knudsen Corp. v. Fireman's Fund Insurance
175 F.3d 1221 (Tenth Circuit, 1999)
Schwartz v. United States
65 F. Supp. 391 (Court of Claims, 1946)
McShain v. United States
87 Ct. Cl. 581 (Court of Claims, 1938)
In re Claim of Hodges
84 Ct. Cl. 380 (Court of Claims, 1937)
W. S. King & Co. v. United States
80 Ct. Cl. 325 (Court of Claims, 1934)