Harvey v. United States

18 Ct. Cl. 470, 1883 U.S. Ct. Cl. LEXIS 42, 1800 WL 1299
CourtUnited States Court of Claims
DecidedApril 30, 1883
DocketNo. 11406
StatusPublished
Cited by2 cases

This text of 18 Ct. Cl. 470 (Harvey v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harvey v. United States, 18 Ct. Cl. 470, 1883 U.S. Ct. Cl. LEXIS 42, 1800 WL 1299 (cc 1883).

Opinion

OPINION.

Davis, J.,

delivered the opinion of the court:

This controversy began in a common-law suit in this court, tried in 1872 — Harvey & Livesey v. The United States (8 C. Cls. R., 501). After -that judgment was. paid, Congress conferred upon this court special equity jurisdiction to enable it to give [476]*476tbe claimants further relief. The suit in equity under that enabling act was first heard on demurrer as to the extent of the relief which the court should give in the new process. (Same v. Same, 12 C. Cls. R., 141.) When this was settled, the case was heard on the merits on the identical proof présented in the common-law suit. (Same v. Same, 13 C. Cls. R., 322.) The Supreme Court sustained the rulings of this court on the demurrer, but reversed the rulings on the merits. (Same v. Same, 105 U. S. R., 671.) The case now comes to ns to have the will of the Supreme Court executed.

I. The controversy grows out of a contract by the claimants to construct the piers and abutments of a bridge to connect Bock Island with Davenport. The first contention related to the evidence of the contract. The claimants contended that there was a material variation to their injury, between the bids and proposals on the one hand and the written contract on the other; that the variation was caused by mutual mistake, and that the court should resort to the bids and proposals for the true evidence of the contract.

This court was unanimous at the common-law trial that it could not look behind the written contract to ascertain the intent of the parties. At the hearing in equity three judges were of opinion that the evidence did not show the mutual mistake which is necessary to enable a court of equity to reform a written agreement. The fourth judge did not concur in this result, and the Supreme Court sustains him. It says:

The written bid, in connection with the advertisement, and the acceptance of that hid, constituted the contract between the parties, so.far as regards the question whether the contract prices embraced the coffer-dam work. (Garfielde v. United States, 93 U. S. R., 242; Equitable Insurance Co. v. Hearne, 20 Wall., 494.) The written contract, in that respect, was intended by both parties to be merely a reduction to form of the statement as to work and prices contained in the bid. * * * We are of opinion that by the actual contract between the parties the appellants were not to do any of the work covered by the claim made by them under item 1 of the petition herein, and that the written contract must be reformed accordingly.

This mandate of the Supreme Court is obeyed in the judgment about to be entered. It is proper before ordering it to call attention to the fact that this suit is in equity; so that the action of the court under its extraordinary special powers is not to be cited as authority in common-law suits.

The claimants’ contract was made with the War Department. [477]*477It came within the provisions of, the Act of June 2, 1862, requiring all contracts with the War, Navy, and Interior Departments to be reduced to writing and signed by the contracting parties with their names at the end. thereof. In the suit at common law we regarded the contract which complied with the provisions of this act as the only contract between the parties. ■ When Congress, however, conferred upon the court the power of reforming this contract, it waived the rigid requirements of the Act of 1862. It authorized us to go behind evidence which that act makes conclusive, and ascertain the agreement of the parties from the proof contained in the bid and proposals.

In the recent case of the South Boston Iron Company (ante, 165), Judge Scofield, for the court, carefully considered the section of the Revised Statutes which codifies this part of the Act of 1862. He said that we regard the provision requiring both parties to sign at the end of the contract as mandatory. Unless an instrument purporting to be a'contract with the War, Navy,, or Interior Department complies with the mandate, or unless Congress waives the requirements of the statute, the instrument can have no validity against the United States in a court, except as evidence of the worth of services or labor actually performed or rendered under it. The court may treat the contract, when signed in conformity with, the provisions of the statute, as relating back, when necessary to protect other interests, as in Adams’s Case (1 C. Cls. R., 192); or when work has been done under it before signing, as in Powers’s Case (ante, 263) and in Shipman v. The District of Columbia (ante, 291), both decided at "the present term; but this does not modify the general rule which requires it to accept as evidence of such a contract only the instrument reduced to writing, in conformity with the provisions of the statute.

II. The next contention related to the cost of the coffer-dams necessary to enable the workmen to construct the piers. On this point the Supreme Court says:

In regard to tie coffer- dams it seems clear to ns that tlie ruling of tire Court of Claims was erroneous. The advertisement begins by inviting proposals for the construction of the piers and abutments of the bridge. Standing . alone this would involve proposals to make coffer-dams and do and furnish everything else necessary to finished work. But this is qualified by what follows. The advertisement goes oñ to say that parties making bids will state (1) the price per cubic yard of solid masonry at which they are willing to complete the work, the'United States furnishing the stone, [478]*478cement, and sand, “ and nothing more.” “To complete the work” there means to construct the piers and abutments complete, including the making of coffer-dams. * * * Then parties making bids are also to make a hid stating (2) separately the price per cubic yard' of solid masonry at which they will undertake to build the piers and abutments, the United States furnishing stone, cement, and sand; and also to make a bid stating (3) separately the price at which they will agree to put in the necessary coffer-dams with their protections. * * * The appellants did not make a hid for the work complete, or say in their bid that thejT were willing to complete the work. They bid only under bid 2. * * * They excluded bid 3 and the coffer-dams, and they excluded bid 1 and the cofferdams in it. This is quite enough to determine the question. The written bid in connection with the advertisement, and the acceptance of that bid, constituted the contract. * * *

Under this ruling we must determine what the claimants did in constructing coffer-dams, and in pumping the water from the space inclosed in them, and in excavations for the preparation of the bed for the masonry. We understand the Supreme Court to hold that the contract related to the masonry only.

There were ten coffer-dams in all. . It was necessary to pump the water out and to keep it pumped out from the space walled in by each. The shale, gravel, and mud above the solid rock had to be excavated in order to prepare beds for the masonry. The piers were in different depths of water, varying from of a foot at low water on the Iowa side to 20^0- feet at low water at pier No.-5.

The amount of excavation to be made after reaching the river bed varied also. At the Davenport abutment there were from to 2 feet of earth, gravel, and loose rock. At pier No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roettinger v. United States
26 Ct. Cl. 391 (Court of Claims, 1891)
Donnelly v. City of Brooklyn
7 N.Y.S. 49 (New York City Court, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
18 Ct. Cl. 470, 1883 U.S. Ct. Cl. LEXIS 42, 1800 WL 1299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harvey-v-united-states-cc-1883.