Harvey v. United States

8 Ct. Cl. 501
CourtUnited States Court of Claims
DecidedDecember 15, 1872
StatusPublished
Cited by7 cases

This text of 8 Ct. Cl. 501 (Harvey v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harvey v. United States, 8 Ct. Cl. 501 (cc 1872).

Opinions

Milligan, J.,

delivered the opinion of the court:

This action is prosecuted to recover $230,400, damages, which the claimants allege resulted from breaches of a written contract, a copy of which is appended to and made a part of the original petition in this case. The sum claimed is itemized in the petition, and set down under eight distinct heads, all of' which, in the view we have taken of the case, need not be separately considered. The principal difficulty, as well as the-greater amount of damages claimed, arises on the construction of the contract.

The contract was let in the ordinary way, under public advertisements soliciting sealed proposals for the work, which were responded to by the claimants and the work regularly awarded to them. Much stress was laid in the argument on the preliminary papers leading to the written agreement, which is the foundation of this suit. On the one side, it was insisted that the advertisement and bid constitute a substantive part of the contract, and may be looked to in its construction; and on the other, this position was denied, and the subsequently written contract claimed as the only paper to which, in the absence-[506]*506of all uncertainty in its language, the court can look in giving-effect to the agreement of the parties.

The law requiring advertisements and proposals for public contracts, obviously was intended by Congress to invite competition among bidders, and to prevent favoritism and fraudulent combinations in awarding contracts ; but the advertisement and bid under which the contract was awarded were never supposed to constitute any part of the contract. On the contrary, the Act June 2d, 1861, (12 Stat. L., 411, § 1,) expressly requires that every contract be reduced to writing and signed by the contracting parties with their names at the end thereof.”

Outside of the statute, and on general principles, the written contract is the last and most deliberate act of the parties, and must be looked upon as the consummation of all previous negotiations, and the exact expression of the parties’ final purpose. No evidence external to the contract, whether written or in parol, as a general rule, is admissible in aid of the interpretation of its language, and therefore all preliminary papers passing between the parties while the contract was in fieri, are merged in the written agreement and inadmissible to contradict or vary the written agreement. (2 Parsons on Contracts, 60; 2 Kent’s Com., 11th ed., 746; 1 Greenleaf’s Evidence, 12th ed., § 275; Nash v. Towne, 5 Wall. R., 689, 703.)

Passing from this question, and dealing with the contract as the parties executed it, the first and most prominent obligation assumed by the claimants was, “to construct the piers and abutments for the new rail and wagon bridge to be built to connect Rock Island with the city of Davenport, in accordance with such plans and specifications as may be fixed by proper authority acting for the United States.”

The obligation here imposed on the claimants ex vi termini, carries with it the performance of all labor necessary to complete the construction of the piers and abutments according to the plans and specifications furnished by the officer in charge of the work.

If doubts existed as to the interpretation of this clause of the contract, they are removed by a subsequent provision, whicli sets out in terms what part the United States are to perform in the fulfillment of the contract. They are bound “ to furnish stone, cement, sand, and all necessary templets required for the work, and nothing more.”

[507]*507The parties having undertaken to define the reciprocal duties and obligations of each other, the law holds each bound to his own agreement. This is the rule'on general principles, and especially is it rigorously enforced when there is a positive negation of any other or further obligation in this respect on the part of the Government inserted in the contract. The maxim, -expressio unuis est exelusio alterius, applies here, and excludes everything not included in the contract.

It follows, therefore, that it was the duty of the claimants to build the coffer-dams, pump the water therefrom, and prepare the bed of the river for the piers and abutments, 'which they were bound to construct.

Next to this question, and of kin to it, arises another, which must also find its solution in the construction of the contract. It is proven that the dimensions of the piers, as indicated in' the drawings shown to the claimants before they sent in their bid for the contract, were somewhat diminished by the officer in charge of the work, after the execution of the contract, and thereby rendered less valuable to the contractors. This reduction, it is claimed, was unlawful, and entitles the claimants to damages.

It is certainly true, if the claimants undertook to do a specific piece of work, and they were wrongfully prevented from performing it according to the terms of the contract, that that would be a breach of the contract, for which the defendants -would be answerable in damages. And there is no valid distinction between the wrongful termination of a contract, and an unlawful diminution of the quantity of the work stipulated to be performed under it. Both alike work a breach, for which the law gives damages, but in unequal amounts.

But the question here presented is one of authority. Had the officer in charge of the work the power, under the contract, to make the alteration complained of? Discarding, as in the former part of this opinion, the preliminary negotiations of the parties, and looking alone to the written agreement, it seems clear that the claimants conceded this right when they executed the contract. By the very words of the agreement they bound themselves “to construct the piers and abutments in accordance with such plans and specifications as may he fixed hy proper authority acting for the United States." The right of the United States to fix the plans and specifications for the piers [508]*508and abutments is not disputed, and the question now to be decided is, whether or not that right was exhausted when the-specifications and drawings* were exhibited to the claimants, before they sent in their proposals for the contract. To hold that it was, would be to defeat the purpose of the after written contract, and render nugatory its leading stipulations. Such-was not the intention of the parties, nor will the language employed in the contract bear any such interpretation. It clearly has a future signification; and the claimants having conceded the right to the United States to fix the working plans and specifications, they cannot now claim its exercise worked a-, breach of the contract, for which the defendants are answerable-in damages.

Conceding the right of the United States to locate the piers- and abutments, and to furnish the plans and working draughts thereof, they could not delay the exercise of this right beyond a reasonable time. And what is a reasonable time must be determined by the court, from the facts and circumstances surrounding each case. No exact* definition can perhaps ever be-given of “reasonable time;” but it must always be that time-which preserves for each party the rights and advantages he possesses, and protects each from losses he ought not to suffer.

The contract in this case was executed on the 1st day of June,.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frazier-Davis Construction Co. v. United States
100 Ct. Cl. 120 (Court of Claims, 1943)
Milliken Imprinting Co. v. United States
40 Ct. Cl. 81 (Court of Claims, 1904)
Louisville & Nashville Railroad v. Hollerbach
5 N.E. 28 (Indiana Supreme Court, 1886)
Harvey v. United States
18 Ct. Cl. 470 (Court of Claims, 1883)
Brawley v. United States
11 Ct. Cl. 522 (Supreme Court, 1875)

Cite This Page — Counsel Stack

Bluebook (online)
8 Ct. Cl. 501, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harvey-v-united-states-cc-1872.