Rizzo v. MSA, Inc.

18 Pa. D. & C.5th 233
CourtPennsylvania Court of Common Pleas, Lackawanna County
DecidedNovember 5, 2010
Docketno. 06 CV 3330
StatusPublished
Cited by4 cases

This text of 18 Pa. D. & C.5th 233 (Rizzo v. MSA, Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Lackawanna County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rizzo v. MSA, Inc., 18 Pa. D. & C.5th 233 (Pa. Super. Ct. 2010).

Opinion

NEALON, J.,

Following a non-jury verdict in favor of plaintiff Bryan Rizzo (“Rizzo”) on his direct claim and in favor of defendant MSA, Inc. (“MSA”) on its counterclaim, both parties filed motions for post-trial relief seeking judgment in their favor with respect to the other party’s verdict against them. The credible evidence at trial established that: (1) the parties mutually agreed to extend the original completion date for their real estate transaction due to construction delays attributable to a third party contractor; (2) Rizzo breached the parties’ amended agreement by refusing to close on the revised settlement date; (3) MSA suffered consequential damages as a result of Rizzo’s breach; (4) Rizzo paid for certain extra-contractual improvements to the property which enhanced its value for later sale by MSA; and (5) it was inequitable for MSA to retain the benefit of those enhancements without payment of value to Rizzo. As a consequence, neither party has demonstrated the right to judgment notwithstanding the verdicts entered against them and their requests for post-trial relief under Pa. [235]*235R.C.P. 227.1(a)(2) will be denied.

I. PROCEDURAL HISTORY

Rizzo commenced this litigation against MSA on July 10, 2006, after Rizzo declined to consummate the parties’ real estate transaction and MSA refused to refund Rizzo’s deposit or reimburse him for extra-contractual work that Rizzo financed. A certificate of readiness was filed on January 20, 2010 and following a status conference before the undersigned on February 25, 2010, an order was issued scheduling this matter for a non-jury trial on June 3, 2010. (Docket entry nos. 1, 39-40) At the request of counsel for Rizzo, the trial was later postponed to July 7, 2010. (Id., No. 43) During the bench trial on that date, testimony was received from Rizzo and MSA’s President, Justin Sulla, Esquire, and various exhibits were admitted into evidence.

Based upon the credible evidence presented during the non-jury trial, a verdict in the amount of $42,345.04 was entered in favor of Rizzo and against MSA on his unjust enrichment claim only, representing his unrefunded down payment and the value of the extra-contractual improvements to the subject property that were provided by Rizzo. With regard to MSA’s counterclaim against Rizzo, a verdict was entered in favor of MSA in the sum of $37,691.23 for its lost profit and other consequential damages related to Rizzo’s failure to consummate the parties’ agreement. The contractual damages to be paid to MSA were ordered to “bear interest at the legal rate of 6 percent per annum under 41 P.S. §202 from the date that payment became due.” (Id, No. 48) Therefore, not [236]*236including MSA’s accrued statutoiy interest, the non-jury verdict yielded a net award of $4,653.81 ($42,345.04 less $37,691.23) in favor of Rizzo.

On July 19, 2010, Rizzo filed a motion for post-trial relief requesting the entry of judgment in his favor with respect to MSA’s counterclaim. (Id., No. 49) On July 20, 2010, an order was issued directing Rizzo to file his supporting brief by no later than August 24, 2010 and requiring MSA to submit its opposing brief 15 days thereafter on September 8, 2010. In addition, the order of July 20, 2010 scheduled oral argument on the post-trial motion for September 22, 2010 at 1:30 PM. (Id., No. 50)

On July 26, 2010, MSA filed its answer to Rizzo’s post-trial motion and also filed its own motion for post-trial relief seeking judgment in its favor with regard to Rizzo’s unjust enrichment verdict. (Id., Nos. 51-52) Rizzo filed an answer to MSA’s post-trial motion on August 5, 2010, (Id., No. 53), but did not file his supporting brief on August 24,2010 as required by the order of July 20,2010. Rizzo did not submit his supporting brief until September 17, 2010, 24 days after the court imposed deadline of August 24, 2010. (Id., No. 56) In the interim, MSA filed its brief in support of its post-trial motions on August 25, 2010. (Id., No. 55)

Although the undersigned and counsel for MSA were present for the scheduled oral argument on September 22, 2010, Rizzo’s counsel did not appear for that oral argument. MSA filed its opposing brief on September 28, 2010, within 15 days of Rizzo’s belated submission of his brief ((Id., No. 57) At that time, the parties’ post-trial motions became ripe for disposition.

[237]*237II. FACTUAL BACKGROUND

In 2005, MSA was engaged in the business of purchasing real estate, constructing residential homes on that land, and thereafter selling the newly constructed residences and accompanying land to third parties. (Transcript of Proceedings (T. P.) on 7/7/2010, pp. 20-21) At that time, MSA regularly contracted with KAB construction (“KAB”) to build homes on MSA’s properties for eventual sale to third parties. {Id., pp. 22-25) On September 23, 2005, MSA entered into an agreement of sale with Rizzo by virtue of which Rizzo agreed to purchase a Jefferson Township property upon which a residence would be constructed by KAB and sold to Rizzo for the sum of $387,000.00. (Joint pre-trial order (“JPO”) dated 7/2/10, pp. 1,9; T. P. 7/7/10, pp. 31-32)

Under the terms of the parties’ agreement, Rizzo made a down payment of $5,000.00 and the closing was scheduled to be conducted on January 31, 2006. (JPO, pp. 2,9; plaintiff’s exhibit No. 1) Paragraph 5 of the agreement notes that “time is of the essence” and provides that the settlement date of January 31, 2006 could “only be extended by mutual written agreement of the parties.” (T. P. 7/7/10, pp. 32-38; plaintiff’s exhibit No. 1, p. 2 of 22) The agreement also contains a mortgage contingency clause making the sale contingent upon Rizzo obtaining mortgage financing of $309,600.00 for a thirty year term at an interest rate not to exceed 6.5 percent. (Plaintiff’s exhibit No. 1, p. 2 of 22; JPO, pp. 2, 9) The mortgage contingency provision obligated Rizzo to “make a completed, written mortgage application for the mortgage terms stated above” within ten days of September 23, 2005. (Plaintiff’s exhibit No. 1, p. 2 of 22) [238]*238Furthermore, paragraph 6(C) states that if Rizzo “fail[ed] to cooperate in good faith in processing the mortgage loan application” and did not secure the requisite mortgage loan commitment as a result, Rizzo would be deemed “in default of this agreement.” (Id. ) Finally, the mortgage contingency clause provides that if Rizzo did not secure a mortgage commitment by November 30, 2005, the parties “agree[d] to extend the mortgage commitment date until [MSA] terminates this agreement by written notice to [Rizzo].” (Id.)

In anticipation of a closing date on or before January 31, 2006, MSA retained KAB to build Rizzo’s home. (JPO, pp. 2, 9; T. P. 7/7/10, pp. 55, 66) As per the parties’ understanding, Rizzo dealt directly with KAB relative to any changes or additions to the construction contract specifications. (JPO, pp. 2,9) In that regard, Rizzo paid KAB $34,500.00 for a concrete driveway, landscaping, a concrete sidewalk, hardwood flooring, and kitchen cabinets that were not included in the MSA-Rizzo contract. (Docket entry no. 48; JPO,pp. 4,10) Additionally, Rizzo purchased $2,845.09 worth of appliances which were installed in the Jefferson Township property. (Docket entry no. 48)

Because of financial problems that were being experienced by KAB, the home construction did not progress on a timely basis and the residence was not substantially completed by January 31,2006. (T.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott Township Sewer & Water Autority v. Tellip
45 Pa. D. & C.5th 197 (Lackawanna County Court of Common Pleas, 2015)
Peoples Neighborhood Bank v. Layo
42 Pa. D. & C.5th 100 (Lackawanna County Court of Common Pleas, 2014)
Czarkowski v. Jennings
34 Pa. D. & C.5th 303 (Lackawanna County Court of Common Pleas, 2013)
Dunbar v. Rivello
34 Pa. D. & C.5th 87 (Lackawanna County Court of Common Pleas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
18 Pa. D. & C.5th 233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rizzo-v-msa-inc-pactcompllackaw-2010.