RICHARD A. PULASKI CONSTRUCTION CO. v. Air Frame Hangars, Inc.

950 A.2d 868, 195 N.J. 457, 2008 N.J. LEXIS 797
CourtSupreme Court of New Jersey
DecidedJuly 1, 2008
StatusPublished
Cited by39 cases

This text of 950 A.2d 868 (RICHARD A. PULASKI CONSTRUCTION CO. v. Air Frame Hangars, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RICHARD A. PULASKI CONSTRUCTION CO. v. Air Frame Hangars, Inc., 950 A.2d 868, 195 N.J. 457, 2008 N.J. LEXIS 797 (N.J. 2008).

Opinion

Justice RIVERA-SOTO

delivered the opinion of the Court.

In this appeal, we consider whether New Jersey recognizes a cause of action in prima facie tort and, if so, the contours of that cause of action. Assuming, without deciding, that our common law may admit of a cause of action for prima facie tort, it is solely a gap-filler. That is, the availability of the prima facie tort doctrine is limited exclusively to those instances of intentional and culpable conduct unjustified under the circumstances that, as a threshold matter, do not fall within a traditional tort cause of action.

I.

Although procedurally complex, the facts underlying this case are readily stated. In February 1996, Air Frame Hangars, Inc. (Air Frame), 1 a foreign business corporation authorized to conduct *461 business in New Jersey, entered into a lease with the County of Mercer for the development of “condominium-style” aircraft hangars for private airplane owners at the Mercer County Airport; at all times material to this action, defendant Bruce W. Ritterson was the president and a shareholder of Air Frame. In July 1996, Air Frame entered into an agreement with plaintiff Richard A. Pulaski Construction Co., Inc., whereby plaintiff agreed to perform site work for the aircraft hangars in exchange for the contract sum of $167,113. By all accounts, plaintiff performed on its contract. Air Frame, however, failed to pay plaintiff as agreed, even though Air Frame completed and sold a number of the condominium-style hangars to third parties. By mid-July 1997, plaintiff claimed that it was owed a total of $105,932 for construction site work performed but not paid.

Because they were unable to resolve their differences, in August 1997, plaintiff filed a construction lien against the improved realty. That lien claim later was declared defective, as it identified the municipality in which the realty was located as Trenton, when the Mercer County Airport in fact is located in Ewing Township. The filing and service of the lien claim triggered a number of settlement discussions between the parties, which were ultimately unsuccessful. As a result, in October 1997, as required by their contract, plaintiff filed a demand for arbitration against Air Frame, seeking the full unpaid contract sum it earlier demanded. In February 1998, during the pendency of the arbitration, plaintiff filed its first complaint against Air Frame and Mercer County— but not against to collect on its unpaid contract balance. By agreement, that suit was later dismissed without prejudice while “preserving” the statute of limitations. 2 Air Frame later defaulted in the arbitration proceeding and, in April 1999, an award for the contract balance plus interest, totaling $136,816.50, was entered against Air Frame.

*462 On May 6, 1999, plaintiff filed a verified complaint seeking to confirm that arbitration award into a judgment. The complaint repeated the claims first set forth in the dismissed complaint against Air Frame and Mercer County. It also added as defendants those purchasers who acquired aircraft hangars from Air Frame after plaintiff filed its construction lien claim; 3 again, that complaint did not list defendant as a party. Concededly, plaintiff did not file a notice against Mercer County pursuant to the Tort Claims Act, N.J.S.A. 59:1-1 to 59:12-3, until September 20, 1999. On November 1, 1999, plaintiff filed a second amended verified complaint, repeating its earlier allegations and, for the first time, adding a fraud claim against defendant. 4 Finally, on March 13, 2000, plaintiff filed a third amended verified complaint, additionally alleging negligence by the Mercer County Clerk in improperly indexing plaintiffs construction lien claim.

Defendant moved for summary judgment. The trial court granted that application, explaining that, even assuming defendant had made fraudulent misrepresentations to the aircraft hangar purchasers as to the quality of title, a fraud cause of action did not lie as between plaintiff and defendant because plaintiff never detrimentally relied on those representations. Plaintiff then voluntarily dismissed its negligence claim against Mercer County, thereby making the trial court’s judgment final and eligible for appeal. 5

*463 Plaintiff appealed. It alleged, among other things, that the trial court erred in granting summary judgment in favor of defendant. The Appellate Division, in an unpublished opinion, affirmed the dismissal of the fraud claim against defendant applying the same rationale relied on by the trial court: that a viable claim of fraud requires reasonable reliance by the plaintiff on the misrepresentations made by a defendant. As the trial court had, the panel reasoned that, assuming the falsity of defendant’s representations to the third-party purchasers of the aircraft hangars, plaintiff had made no showing that it had relied on any of those representations.

The Appellate Division, however, went further. Although the claim had not been pled in plaintiffs several complaints and was not raised until the appeal, the panel “agree[d] with plaintiffs contention that the matter should be remanded for a determination of whether the facts alleged could support a cause of action against [defendant] on a different tort theory, namely, for ‘prima facie tort.’ It also noted that “[o]n remand, the court should also consider plaintiffs unaddressed contention that the facts support a claim against [defendant] for intentional interference with prospective economic advantage, or tortious interference with economic advantage or contractual relations.” It noted that “[b]y remanding plaintiffs claims against [defendant], [it did] not suggest that plaintiffs claims are supportable in law or in fact, just that [it] believe[d] plaintiff should have an opportunity to try to demonstrate that they are.”

*464 On remand, and upon defendant’s application to dismiss, the trial court embraced the existence of a prima facie tort claim patterned on Section 870 of the Restatement (Second) of Torts. It explained that

Section 870 says “[o]ne who intentionally causes injury to another is subject to liability to the other for that injury[,] if his conduct is generally culpable and not justifiable under the circumstances. This liability may be imposed [although] the actor’s conduct does not come within [a] traditional category of tort liability.”
That’s Section 870, which the Court would be prepared to instruct the jury if it got to that point as to what plaintiff needs to prove in order to hold [defendant] liable.
[ (Editing marks added).]

The case was tried without a jury, and the sole issue was whether defendant was liable to plaintiff under a prima facie tort theory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kusum Foods, Inc. v. Rajput Foods, LLC
New Jersey Superior Court App Division, 2025
GU v. WANG
D. New Jersey, 2025
Ejk Realty LLC v. Akr Contracting Inc.
New Jersey Superior Court App Division, 2024
KONSTANTINOVA v. GARBUZOV
D. New Jersey, 2021
MAGNANI v. MADDALUNA
D. New Jersey, 2020
IACONE v. JANOFF
D. New Jersey, 2020

Cite This Page — Counsel Stack

Bluebook (online)
950 A.2d 868, 195 N.J. 457, 2008 N.J. LEXIS 797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richard-a-pulaski-construction-co-v-air-frame-hangars-inc-nj-2008.