Restigouche, Inc. v. Town of Jupiter

59 F.3d 1208, 32 Fed. R. Serv. 3d 25, 1995 U.S. App. LEXIS 20446
CourtCourt of Appeals for the Eleventh Circuit
DecidedAugust 2, 1995
Docket19-11878
StatusPublished
Cited by72 cases

This text of 59 F.3d 1208 (Restigouche, Inc. v. Town of Jupiter) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Restigouche, Inc. v. Town of Jupiter, 59 F.3d 1208, 32 Fed. R. Serv. 3d 25, 1995 U.S. App. LEXIS 20446 (11th Cir. 1995).

Opinion

ANDERSON, Circuit Judge:

I. BACKGROUND

Restigouche, Inc. (“Restigouche”) owns property the parties refer to as “Maple-wood,” located along Indiantown Road in the town of Jupiter, Florida (the “Town”). In 1988, the Town began a study of land use *1211 along the Indiantown Road Corridor, including the Maplewood property. At that time, Maplewood was zoned to permit automobile sales by special exception. In November 1989, Restigouehe applied to the Town for special exception in order to build an automobile campus on the property. While approval was pending, the Town completed its study of the Indiantown Road Corridor, and adopted a comprehensive plan for land use along the corridor (the “Comprehensive Plan”) and specific zoning regulations applicable to the subdistrict in which the Maple-wood property is located (the “IOZ Regulations”). The IOZ Regulations prohibited automobile sales in the subdistrict. Subsequently, pursuant to the IOZ Regulations, the Town denied Restigouche’s application to build an automobile campus on Maplewood.

Restigouehe appealed the denial of its application to the Town Council. After the Town Council denied its appeal, Restigouehe sought state administrative review pursuant to Fla.Stat.Ann. § 163.3213(7) (West 1990). This administrative challenge was also unsuccessful. Restigouehe then filed suit in state court asserting a number of constitutional and statutory claims. The state court suit is currently pending. Restigouehe has not, however, sought. rezoning, nor has Restigouehe requested approval for the twenty-seven other uses the parties agree are permitted on Maplewood under the IOZ Regulations.

Restigouehe filed the instant action on February 8,1991, claiming that the IOZ Regulations, as applied to Maplewood, are unconstitutional. The Town filed a motion for summary judgment on April 28, 1993, and the motion was fully briefed by June 14, 1993. In the meantime, the case had been assigned by consent of the parties to a magistrate judge pursuant to 28 U.S.C. § 636(e). No hearing was immediately set on the summary judgment motion, and the parties proceeded with discovery. On November 29, 1993, the magistrate court telephonically informed the parties that it would hear argument on the Town’s motion for summary judgment at the pretrial status conference on December 1. Oral argument was heard on the motion at the status conference on December 1, and the magistrate court entered an order granting summary judgment in favor of the Town on December 15.

In its order granting summary judgment, the magistrate court determined that Restigouche’s challenge to the IOZ Regulations raised only two claims: (1) that the Town’s action in passing and applying the IOZ Regulations to Maplewood is arbitrary and capricious as applied (substantive due process); and (2) that the Town’s action prohibiting automobile sales on Maplewood constitutes a taking. 1 The court found Restigouche’s takings claim premature, and granted summary judgment on Restigouche’s substantive due process claim as a matter of law.

In this appeal, Restigouehe asserts that'its just compensation takings claim is ripe. The Town, on the other hand, asserts that both substantive due process and takings claims *1212 should have been dismissed as premature. Restigouche further argues that the district court granted summary judgment without first giving Restigouche the 10-day notice required under Fed.R.Civ.P. 56(c). Finally, Restigouche asserts the district court erred as a matter of law in granting judgment to the Town because genuine issues of material fact existed with respect to its substantive due process claim. We affirm.

II. RIPENESS

Whether Restigouche’s claims are ripe is a jurisdictional issue, which we review de novo. Reahard v. Lee County, 30 F.3d 1412, 1414 (11th Cir.1994), cert. denied, — U.S. —, 115 S.Ct. 1693, 131 L.Ed.2d 557 (1995). The purpose of the ripeness doctrine is “to prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements.” Abbott Laboratories v. Gardner, 387 U.S. 136, 149, 87 S.Ct. 1507, 1515, 18 L.Ed.2d 681 (1967). Therefore, assuming that there is sufficient injury to meet Article Ill’s requirement of a case or controversy, the ripeness inquiry focuses on whether the claim is sufficiently mature, and the issues sufficiently defined and concrete, to permit effective decisionmaking by the court. Johnson v. Sikes, 730 F.2d 644, 648 (11th Cir.1984).

Because substantive due process and takings challenges to the zoning process scrutinize that process in slightly diffex-ent ways, substantive due process and takings claims mature at different points in the process. Eide v. Sarasota County, 908 F.2d 716, 720-26 (11th Cir.1990), cert. denied, 498 U.S. 1120, 111 S.Ct. 1073, 112 L.Ed.2d 1179 (1991). An as applied substantive due process challenge focuses on whether the actual decision to apply the zoning to the property was “arbitrary and capricious.” Thus, such a claim presents a sufficiently concrete question for review when the zoning decision has been finally made and applied to the property. Id. at 724-26. It is undisputed that the IOZ Regulations have been finally made, and that the Town denied Restigouche’s application to zone Maplewood for automobile sales pursuant to those regulations. Therefore, Restigouehe’s substantive due process claim is ripe. Id. at 725 n. 16.

However, a just compensation takings claim matures later in the zoning process. One focus of such a takings challenge is whether a zoning regulation has “gone too far,” i.e., has deprived the owner of all uses that would enable him to derive economic benefit from the property. Id. at 720-21. Thus, Restigouche’s just compensation takings claim is not ripe before the “local authority has determined the nature and extent of the development that will be permitted.” Id. at 720. Unlike in the substantive due process context, this requires more than a final decision to apply the zoning regulation to the property. Such a takings claim is not ripe until the property owner has also sought rezoning and/or variances sufficient to determine the extent of economically beneficial use which remains under the zoning regime. Id. Restigouche has not sought rezoning, nor applied for one of the twenty-seven remaining uses permitted on the property under the IOZ Regulations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
59 F.3d 1208, 32 Fed. R. Serv. 3d 25, 1995 U.S. App. LEXIS 20446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/restigouche-inc-v-town-of-jupiter-ca11-1995.