Republic of the Philippines v. Westinghouse Electric Corp.

43 F.3d 65
CourtCourt of Appeals for the Third Circuit
DecidedDecember 20, 1994
Docket93-5667
StatusUnknown
Cited by12 cases

This text of 43 F.3d 65 (Republic of the Philippines v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Republic of the Philippines v. Westinghouse Electric Corp., 43 F.3d 65 (3d Cir. 1994).

Opinion

OPINION OF THE COURT

LEWIS, Circuit Judge.

This case raises important issues at the intersection of two principles: our deep-seated belief that a district court must be permitted to protect the integrity of its fact-finding process, and the settled considerations which courts in the United States must heed when considering whether to enjoin the executive activities of a foreign sovereign carried out in that sovereign’s own territory. The district court found that the Republic of the Philippines was harassing witnesses who had testified against it in a suit it had brought in federal court in New Jersey. Thus, the court enjoined the Republic from continuing this harassment. The court also denied interlocutory certification of an underlying jury verdict so as to enforce its injunction, and ordered that any settlement in the case be conditioned upon acceptance of the court’s continuing jurisdiction to enforce its injunctions. Because the district court exceeded its authority, we will reverse.

I.

A.

In 1988, the Republic of the Philippines (the “Republic”) and the National Power Corporation (“NPC”) filed a complaint against Westinghouse Electrical Corporation and Westinghouse International Projects Company (collectively ‘Westinghouse”) and Burns and Roe Enterprises, Inc. (“Burns and Roe”) concerning the construction of a nuclear power plant in Bagac, Bataan. The fif *68 teen-count complaint alleged breach of contract, fraud, tortious interference with fiduciary duties, negligence, civil conspiracy, violations of state and federal racketeering statutes, and violations of the Robinson-Patman Act and the New Jersey Consumer Fraud Act. The district court determined that all but two of the counts against Westinghouse were subject to international arbitration. Republic of the Philippines v. Westinghouse Electric Corp., 714 F.Supp. 1362 (D.N.J.1989). Thus, most of the Republic’s claims against Westinghouse were referred to arbitration under the Rules of Conciliation and Arbitration of the International Chamber of Commerce. 1 In the remaining two counts, the Republic and NPC alleged that Westinghouse and Burns and Roe had conspired to bribe then-President Ferdinand Marcos in order to win the power plant contract, and had thus tortiously interfered with the fiduciary duties that Marcos had owed the people of the Philippines.

While preparation for the trial on the tor-tious interference counts proceeded in New Jersey, arbitration implicating the other counts proceeded apace in Geneva. In late 1991, reaching the bribery allegations in the context of the Republic’s challenge to the validity of the contract’s arbitration clause, the arbitrators found that the Republic had failed to show that Westinghouse had bribed President Marcos. When the arbitrators included this finding in a preliminary award in favor of Westinghouse and Burns and Roe entered in December, 1991, the defendants moved for summary judgment in the district court, claiming the arbitrators’ preliminary award collaterally estopped the Republic and NPC from litigating the bribery and tortious interference claims. The district court denied the motion and, when settlement discussions broke down, the case went to trial in March, 1993.

As the district court noted in the opinion supporting the order now before us, “[f]rom all accounts in the Philippine press, [the filing of the suit against Westinghouse and Burns and Roe and the arbitration in Geneva] assumed enormous importance in the eyes of Philippines leaders.” District Court Opinion (“Op.”) at 5. The court explained that “[construction of the power plant had been undertaken to help solve the desperate electrical power shortage in the Philippines. Huge foreign loans were incurred to pay for the project.” Id. When Marcos left the Philippines and the Aquino government suspended construction of the power plant, “the Republic found itself with a partially completed plant which was producing no electricity, an ever worsening shortage of electrical power, and a huge foreign debt burden on which, it is said, interest alone amounts to $300,000 each day.” Id. Thus, the court surmised that “[i]t appears that the leaders of the Republic looked to a judgment in this case and in the arbitration proceedings as the solution to these staggering problems.” Id. The court further surmised that this factual context “may provide some explanation of the untoward events which transpired after the jury rendered a verdict against the Republic.” Id.

During the trial, two Filipino Westinghouse workers, Pedro A. Padre, Jr. and Jerry R. Orlina, testified for Westinghouse. In addition, Westinghouse introduced an affidavit from Perfecto V. Fernandez, a professor of law at the government-owned University of the Philippines. The affidavit had been rendered two years prior to the trial, when Westinghouse had moved for summary judgment, and discussed Philippine law relevant to the issues in the case. This testimony, the súbsequent actions threatened and taken by the Republic against the witnesses, and the court’s responses are the subjects of this appeal.

B.

After a lengthy trial, the jury returned a verdict for Westinghouse and Burns and Roe on the bribery and tortious interference counts. Because the other claims were still stayed pending arbitration, the Republic filed a motion for certification pursuant to Fed. R.Civ.P. 54(b) to appeal the issues that had *69 been adjudicated. At a hearing held on June 28, 1993 to consider this motion, the court was inclined to grant certification, stating that “there is no case more appropriate for certification than this one” (Joint Appendix (“J.A.”) at 41) and that “clearly [the case] should be certified” (J.A. at 44).

However, Westinghouse then advised the court that it had evidence that Padre, Orlina and Fernandez were being harassed and subjected to retaliation by Philippine officials because of their testimony on behalf of Westinghouse. When these allegations were brought to its attention, the court abruptly changed its mind about certification, stating that although the facts needed to be developed,

if there is a basis to [the allegation of harassment], it is a very, very serious charge, because nobody could come into this Court and then abuse people who come and testify. Some very dramatic, drastic remedies would have to be provided ... It would be destructive of our whole system. No foreign government should be allowed to use our court system and then not play fair with the witnesses in the case. I can’t think of anything more destructive of our system, and simply could not permit it.

J.A. at 49-50. The court concluded that it must “hold off’ on signing the Rule 54(b) certification because it would lose jurisdiction once the notice of appeal was filed. Id. at 50.

The court ordered briefing and requested a motion from Westinghouse formally requesting relief from the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
43 F.3d 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/republic-of-the-philippines-v-westinghouse-electric-corp-ca3-1994.