Realty Co. v. Ellis

61 S.E. 832, 4 Ga. App. 402, 1908 Ga. App. LEXIS 314
CourtCourt of Appeals of Georgia
DecidedJune 18, 1908
Docket1023
StatusPublished
Cited by28 cases

This text of 61 S.E. 832 (Realty Co. v. Ellis) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Realty Co. v. Ellis, 61 S.E. 832, 4 Ga. App. 402, 1908 Ga. App. LEXIS 314 (Ga. Ct. App. 1908).

Opinion

Powell, J.

To state the case without going into any great particularization: Ellis was an architect. Sparks and his associates desired to build certain apartment houses, using in part the materials from an existing structure. Ellis agreed with them to draw the plans and specifications and to supervise the work for the usual percentage, to be based upon the total cost of the work, including a reasonable allowance for old materials. Afterwards Sparks and his associates caused the defendant corporation to be created, and, according to the answer filed in the suit, it assumed the contract with Ellis. It was contemplated originally that the work should be let to contractors; but the defendant finally decided to undertake to do the building through foremen and day-laborers. This proved to be unduly expensive. After a large portion of the work had been done, the defendant discharged Ellis, relieving him from further supervision, but retaining his plans and specifications. Ellis sued, alleging an indebtedness of $4,000, according to a bill of particulars in the following form: “To plans and specifications Apartment House, Lanier Place, 5% of cost of building ($90,000), $4,500; credit by cash on account, $500; balance due, $4,000.” The defendant pleaded, as its excuse for discharging Ellis, that, as a part of his contract of employment, he was to make and did make an estimate of the cost of the buildings; that upon the faith of this estimate the defendant embarked upon the enterprise; that as the work progressed it was found that the cost would grossly exceed and did greatly exceed the estimate given; and that for this they were entitled to discharge him. Ellis made the contention, and supported it by proof, that he had no agreement to make any estimate; that the estimates on which defendant acted were purely bids of contractors, with which he had no further connection than to receive them and to submit them to the officers of the defendant company. Further facts necessary to [404]*404an understanding of the case will be stated in the opinion. The jury gave the plaintiff a verdict for the full amount claimed.

1. At the conclusion of the plaintiff’s testimony the defendant moved for a nonsuit, on the ground that the plaintiff had established by his proof an entire contract by which he was not only to draw plans and specifications but also to supervise the building; that the suit was for plans and specifications only; therefore the plaintiff had not proved his case as laid. To avoid the effect of this motion the plaintiff offered an amendment to his statement of the cause of action, by adding after the words “plans and specifications” the words “and supervision.” The defendant objected to this amendment, on the ground that it added a new and distinct cause of action. The court allowed it and the defendant preserved exceptions.

The petition does not disclose its exact nature; whether it is upon contract or upon account for services rendered. The defendant, in the motion for nonsuit, assumed and urged the legal proposition that the action was based upon the contract itself as an entirety; and the plaintiff, by amending without awaiting the ruling of the court, acquiesced in this interpretation. Even if the defendant’s point as to this were not well taken, when the defendant proposed to give the case this factitious status and the opposite party acquiesced and acted, it would not thereafter lie in the defendant’s mouth to disclaim it. If the plaintiff’s case rested on. an entire contract, and this was the cause of action on which he sued, but, in declaring his case originally, he omitted to state it with that fullness requisite to show the whole contract and the breach, as it was or as his proof showed it to be, surely to insert the omitted details by amendment would not be to add a new and distinct cause of action, but, per contra, would be merely to amplify an abbreviated statement of the same cause of action. That this is permissible will hardly be questioned. Unless the defendant’s point were well taken that the plaintiff’s suit was based on an entire contract, only a part of which was alleged, the motion for nonsuit would have been wholly without merit, for- there was proof as to the value of the services of the plaintiff in the drawing of the plans and specifications, apart from the work of supervision. It is hardly necessary to say that the plaintiff may avoid nonsuit on the ground of variance, by making a permissible amendment [405]*405to the pleadings. Seaboard Air-Line Railway v. Fenn, 120 Ga. 664 (48 S. E. 141); Rice v. Ware, 3 Ga. App. 573 (60 S. E. 301).

2, 3. One of the contentions of the defendant is that at the time the suit was brought the buildings had not been completed, and that under the contract the sums sued for were not to be due until after the work was finished. There was some dispute in the evidence as to this question, but we do not think it is in the case at all; for the defendant joined issue on the merits without pleading that the suit was prematurely brought. Such a defense does not go to the merits of the plaintiffs case, and should be asserted at the first term by a demurrer or a proper plea. Horne v. Rodgers, 103 Ga. 649 (30 S. E. 562); Goodrich v. Atlanta Association, 96 Ga. 803 (22 S. E. 585). Further, the plaintiff, when the defendant wrongfully discharged him, had the right to sue at once and to prove, and to recover for, all damages which may have accrued up to the date of the trial. Roberts v. Rigden, 81 Ga. 440 (7 S. E. 742).

4. The defendant also complains that the jury gave the plaintiff a verdict for commissions on the total cost of the buildings, though a considerable portion of the work was done after the plaintiffs discharge and, therefore, without his supervision. In such an action the measure of damages is the full loss sustained by the discharged agent by reason of the breach of the contract. It is subject, however, to diminution by any amount which the proof shows the agent profited, or in the exercise of reasonable diligence should have profited, by reason of his release from the performance of the services. Civil Code, §3017. The burden of proving that the discharged agent did profit or by ordinary diligence could have profited himself by reason of his release from the employment is upon the opposite party. Roberts v. Crowley, 81 Ga. 429, 439 (7 S. E. 740). In the case at bar there was no evidence of any facts warranting a diminution of the damages Ellis sustained by reason of the wrongful discharge.

5. The defendant pleaded, that the discharge of Ellis. was warranted by reason of the unskilful estimates which, it is claimed, he made as a part of the contract, and that he was not entitled to recover in the suit; it further pleaded, as a recoupment, that certain enumerated damages had ensued to it as a result of this unskilful advice, and prayed judgment against the plaintiff [406]*406for that sum. The court charged the jury that if Ellis agreed to make estimates and made the unreasonably small estimates alleged, and furnished them to the defendant, he could not recover; he also submitted to them the question of damages under the plea of recoupment. The jury found for the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kinetic Concepts, Inc. v. Kinetic Concepts, Inc.
601 F. Supp. 496 (N.D. Georgia, 1985)
Smith v. Georgia Power Co.
205 S.E.2d 916 (Court of Appeals of Georgia, 1974)
Ponce De Leon Properties, Inc. v. Walton
152 S.E.2d 667 (Court of Appeals of Georgia, 1966)
Harper v. Nu-Air Manufacturing Co.
128 S.E.2d 554 (Court of Appeals of Georgia, 1962)
Brandwein v. Greenfield
122 S.E.2d 316 (Court of Appeals of Georgia, 1961)
Carpenter v. Forshee
120 S.E.2d 786 (Court of Appeals of Georgia, 1961)
Norwood Realty Co. v. P. & H. Homes, Inc.
107 S.E.2d 292 (Court of Appeals of Georgia, 1959)
Reserve Life Insurance Co. v. Peavy
105 S.E.2d 465 (Court of Appeals of Georgia, 1958)
Metropolitan Life Insurance v. Lovett
179 S.E. 253 (Court of Appeals of Georgia, 1935)
North American Accident Insurance v. Scarborough
176 S.E. 671 (Court of Appeals of Georgia, 1934)
Smith v. Gholstin
164 S.E. 217 (Court of Appeals of Georgia, 1932)
Clift & Goodrich Inc. v. Mincey Manufacturing Co.
152 S.E. 136 (Court of Appeals of Georgia, 1930)
Gary v. Central of Georgia Railway Co.
141 S.E. 819 (Court of Appeals of Georgia, 1928)
Massee v. Stetson
107 S.E. 362 (Court of Appeals of Georgia, 1921)
Chapman v. State
98 S.E. 243 (Court of Appeals of Georgia, 1919)
Louisville & Nashville Railroad v. Rogers
94 S.E. 321 (Court of Appeals of Georgia, 1917)
Phosphate Mining Co. v. Atlanta Oil & Fertilizer Co.
93 S.E. 532 (Court of Appeals of Georgia, 1917)
Linam v. Anderson
78 S.E. 424 (Court of Appeals of Georgia, 1913)
Georgia, Florida & Alabama Railway Co. v. Parsons
76 S.E. 1063 (Court of Appeals of Georgia, 1913)
Jones v. Pope
67 S.E. 280 (Court of Appeals of Georgia, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
61 S.E. 832, 4 Ga. App. 402, 1908 Ga. App. LEXIS 314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/realty-co-v-ellis-gactapp-1908.